Deax-Duck Lumber Supply Co. v. Allen

10 So. 2d 242, 1942 La. App. LEXIS 237
CourtLouisiana Court of Appeal
DecidedJune 2, 1942
DocketNo. 6507.
StatusPublished
Cited by1 cases

This text of 10 So. 2d 242 (Deax-Duck Lumber Supply Co. v. Allen) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Deax-Duck Lumber Supply Co. v. Allen, 10 So. 2d 242, 1942 La. App. LEXIS 237 (La. Ct. App. 1942).

Opinion

Plaintiff instituted this suit for damages based upon the breach of a contract. It alleged that it was in the building and supply business and that in July, 1940, defendants, being desirous of building a residence and garage near LeCompte, Louisiana, did enter a contract with it for the furnishing of material and the construction of same. That defendants were unable to finance the project and it was necessary to place a mortgage on the property to secure the contract price and to obtain a purchaser of the mortgage note or notes, which defendants were unable to do; and that for the benefit of defendants it sought and found a purchaser of the notes. That it spent much time in making the arrangements for defendants to finance the building project.

Plaintiff further alleged that the contract price agreed upon was $2600 and that it discussed the plans and specifications for the building with the defendants and the specifications were reduced to writing. That it was thoroughly understood by defendants and that after the specifications were furnished defendants and discussed with them, they confirmed the contract by letter. That the contract called for the demolishing of an old building on the premises and the building of a garage with the material salvaged therefrom.

Plaintiff alleged that it proceeded under the contract to wreck the old building, which was a five-room house with hall, porches, brick chimney and flue, and that it cleared off the premises for the erection of the dwelling house and garage. It alleged it drew the nails from the old lumber, separated the materials cleaned the mortar off the old brick, hauled material from its plant to begin the construction and did partially construct the garage and had begun the construction of the residence, at which time defendants began to interfere with the contract and its execution. Plaintiff alleged that defendants wanted to change the specifications, especially as to the grade of lumber; that they wanted a fence put around the house and other changes and additions, all of which the contract did not provide.

In an effort to please defendants, plaintiff agreed to the changes and additions and the work proceeded under said changed *Page 243 specifications until the defendants presented to plaintiff the previously agreed to specifications with material changes therein; and that defendants changed the specifications by adding a clause that defendants would not be obligated to pay anything on the contract if there was the slightest deviation, even to the extent that if one board could be found in the structure that was not up to grade. That defendants' attitude was so unreasonable that it was impossible for it to continue with the work; and that defendants notified it that unless it agreed to the modified specifications, they would abandon the contract and that it therefore became impossible for plaintiff to continue under the contract.

Plaintiff also alleged it had incurred the following expense in attempting to fulfill its contract:

Labor ................................................... $120.00 Hauling ................................................. 31.00 Supervision ............................................. 25.00 Insurance ............................................... 15.00 Return of Material previously placed on premises ............................................ 15.00

Plaintiff further alleged it would have made a profit of $300 on the construction of the house and garage if it had been allowed to complete its contract and prayed for judgment against defendants in the sum of $500.

Defendants in answer denied owing plaintiff anything. They admitted they entered into a contract with plaintiff to demolish an old house and construct a garage with the material therefrom at an agreed price of $40 and that they undertook to agree but never actually agreed on the construction of a new dwelling house. That they discussed plans and specifications and that plaintiff submitted specifications which were not in accord with the specifications verbally agreed upon between plaintiff and them; that they changed the specifications to comply with the verbal agreement and that plaintiff never agreed to the changes, and therefore no actual contract was ever entered into. That it was understood between the parties that the specifications would be agreed upon and signed by both parties before the work began and that this was never done.

Defendants admitted that the old building was demolished but denied that the nails were removed from the old lumber. They denied that plaintiff cleared off the site for the garage, removed the mortar from the old brick or separated the materials, but admitted that it did haul certain material to be used in the construction of a new house, which material was rejected by defendants because of inferior grade. They admitted they objected to the grade of lumber plaintiff undertook to supply, which was not up to the grade verbally agreed upon.

Defendants further admitted plaintiff agreed to some changes in the specifications submitted by it but never agreed to the changes with reference to materials to be used in the roofing, the porch ceiling, inside ceiling and floor, the water tank, the floor of the garage, glass doors and in many other respects. They alleged that when they discovered that plaintiff was undertaking to furnish materials different from that agreed upon, they wrote into the specifications, "Any deviation from any statements as to materials, etc., by Contractor makes contract null and void"; and such a clause was necessary in order to protect them from the low grade of material plaintiff was attempting to put into the building.

Defendants further alleged that the sole and only reason plaintiff stopped work was because it was unwilling to comply with its verbal contract and to furnish materials of the kind and quality designated by the defendants. They alleged that they assisted plaintiff in every possible way in the prosecution of the work; that they loaned its workmen tools and loaned it the use of their labor and assisted in many other ways; and that when they discovered plaintiff was not going to perform its contract according to the verbal agreement, they submitted to plaintiff a proposition to stop and that they would make adjustment of all their difficulties at that time, which offer was refused. Defendants prayed that plaintiff's demands be rejected at its cost.

The lower court awarded judgment for plaintiff in the sum of $106, consisting of the following:

For insurance ............................................ $15.00 For hauling .............................................. 31.00 For labor ................................................ 60.00

and both plaintiff and defendants have perfected a devolutive appeal to this court.

A correct determination of the issues involved is not without difficulties because of the unbusiness-like methods employed by both plaintiff and the defendants in their *Page 244 dealings with each other and this was no doubt due to the confidence each had in the other doing the right thing. The record makes one thing clear and that is that plaintiff and defendants had discussed the plans and specifications fully and had agreed on them before the specifications were put in writing. Sometime previous defendants had a bid from another concern on the same work, which was several hundred dollars less than the price asked by plaintiff. When asked by defendants why the price was higher, they were told, "You have asked for the best and that is what we are going to give you and you have to pay for it."

Both defendants testified to the above conversation and it is not denied by plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
10 So. 2d 242, 1942 La. App. LEXIS 237, Counsel Stack Legal Research, https://law.counselstack.com/opinion/deax-duck-lumber-supply-co-v-allen-lactapp-1942.