Dean v. Stewart

143 P. 966, 49 Mont. 506, 1914 Mont. LEXIS 85
CourtMontana Supreme Court
DecidedOctober 20, 1914
DocketNo. 3,407
StatusPublished
Cited by6 cases

This text of 143 P. 966 (Dean v. Stewart) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dean v. Stewart, 143 P. 966, 49 Mont. 506, 1914 Mont. LEXIS 85 (Mo. 1914).

Opinion

MR. JUSTICE SANNER

delivered the opinion of the court.

The plaintiffs brought this action in the district court of Missoula county to recover from the defendants, Stewart & Welch, a balance of $51,205.85, alleged to be due for labor and materials furnished in the construction of the railway and roadbed of the defendant Chicago, Milwaukee & St. Paul Railway Company of Montana, during the years 1907 and 1908, and to foreclose a lien upon said property. The material issues of fact were the amount and value of the work done and whether the work was done under contract between the plaintiffs and Stewart & Welch, who were contractors under Winston Brothers, whose contract in turn was with the company. The issues were .referred to Daniel J. ITeyfron, Esq., an attorney and counselor at law of Missoula, Montana, who was directed to take the proof and report the same, together with his findings of fact and conclusions of law, to the district court. The referee proceeded, and as the result of the evidence presented to him, found, in substance, that Stewart & Welch did contract with the plaintiffs for the construction of the portion of the railway in question, agreeing to pay therefor as follows: 32% cents per cubic yard for moving common earth, 90 cents per cubic yard for solid rock, 1 cent per cubic yard for overhaul, and $1.25 per square rod for grubbing; that the plaintiffs moved 90,751 cubic [511]*511yards of common earth, 24,870 cubic yards of solid rock, 664,400 cubic yards of overhaul, and did 58 square rods of grubbing; that at the special instance of Stewart & Welch and the railway company, plaintiffs also did extra work in reconstructing a culvert of the reasonable value of $250; that in consequence of such operations plaintiffs became entitled to receive the sum of $58,843.57 and have received $48,843.95, leaving still due to them $9,999.62; that the work was completed on November 10, 1908, and' on December 16, 1908, plaintiffs filed their notice and claim of lien. As conclusions of law the referee reported that plaintiffs were entitled to judgment against the defendants Stewart & Welch for $9,999.62, with interest at eight per cent from December 18, 1908, and to a first lien upon 3,300 feet of said railroad lying between stations 1600 and 1633, in miles 46 and 47 near Rivulet, Missoula county, Montana.

This report of the referee, together with the evidence presented at the hearing before him, was submitted to the district court, upon plaintiffs’ motion for a judgment and decree accordingly, and upon defendants’ exceptions to the report, motion to reject the findings and to adopt certain other findings contrary thereto. The court overruled the motion to reject and adopted the findings, save as to an item of attorneys’ fees. On May'21, 1912, a judgment and decree was entered for the plaintiffs as of December 30,1911, in accordance with the findings as adopted. From that judgment and decree Stewart & Welch and the railway company have appealed.

Much discussion is devoted to the proposition that this court ought not to consider the voluminous record of the evidence; for certain reasons of procedure. We shall put them aside, because we prefer to dispose of the case upon the merits.

The questions then are: (1) Is the evidence sufficient to sustain (a) the finding of a contract between the plaintiffs and Stewart & Welch, and (b) the finding as to the amount of work done? (2) Is the notice of lien sufficient?

1. We shall assume without deciding, that this case — even as to Stewart & Welch — is in equity, and that the conclusions below [512]*512[1] may be reversed if the evidence decidedly preponderates against them; hut in determining whether the evidence does preponderate against the findings, we are not to forget that the trial court (in this case the referee) had the advantage of the personal presence of the witnesses, and “owing to this advantageous position this court will naturally hesitate to overturn findings' based upon substantially conflicting evidence which would justify an inference in favor of either side.” (Bordeaux v. Bordeaux, 32 Mont. 159, 80 Pac. 6; Boyd v. Huffine, 44 Mont. 306, 120 Pac. 228.) (a) The contention on the part of defendants was that plaintiffs were not in contractual privity with Stewart & Welch but with one John Hanson, a contractor under Stewart & Welch. Let it he granted that there is ample evidence to justify this conclusion; what is to be said against it? The plaintiff Dean testified that there had been negotiations between his firm and Hanson for the work at a certain price; these negotiations terminated without result'; thereafter he saw Mr. Shepard, who is admitted to have been the superintendent and authorized agent of Stewart & Welch, and who sought to have plaintiffs do the work; he was told by Dean that they would take the work from Stewart & Welch hut would have nothing to do with Mr. Hanson. Shepard told them to go ahead and a price was agreed upon. During the work plaintiffs took their instructions from Stewart & Welch. Mr. Elrod, the other plaintiff, testified to similar effect. Mr. Shepard testified for the defendants, that as superintendent for Stewart & Welch he had written to and discussed with the plaintiffs the matter of their doing the work, hut that he did so and actually procured the plaintiffs to do the work' for Planson, as it was within the range of Hanson’s contract. Certain letters, however, which were received in evidence, tend to support the plaintiffs rather than Mr. Shepard in this regard. Prior to September 23, 1907, plaintiffs had signified to Hanson their willingness to accept a contract from him, and on that date he wrote to them.that certain changes in the work directed by the engineers of the company precluded the successful use of a team outfit, “so we will have [513]*513to call the deal off.” On September 25, plaintiffs wrote Mr. Shepard inclosing Hanson’s letter of September 23, adding: “Will consider yonr letter a guaranty and will continue to make our arrangements to move over and take the work.” ■ In response plaintiffs received a letter signed “Stewart & Welch— J. C. Shepard,” stating: “You can have the cut and at prices named, and as I said before, I will see you get a square deal.” Plaintiffs answered: “Would like to have you make Hanson come through with a contract for the work after what has transpired ’’; and the rejoinder, signed “J. C. Shepard for Stewart & Welch,” says-: “It is not customary to forward contracts to sign before outfit is on the ground, but in this case it is entirely unnecessary as my letters are the agreement.” The foregoing, coupled with other details and circumstances presented in the record, forbid us to say that the finding upon this point was without substantial support.

(b) The same conclusion must be reached touching the amount of work that was done. The real controversy was as to the amount of rock removed, and upon this there was a sharp conflict between Dean, Elrod, Sibley and Mayo on the one side, and the company’s engineers — two in number — on the other. We cannot undertake to decide between these witnesses; but upon settled principles will uphold the finding of the referee as adopted by .the court. (O’Malley v. O’Malley, 46 Mont. 549, 558, Ann. Cas. 1914B, 662,129 Pac. 501.)

2. In the notice or claim of lien as filed by the plaintiffs, it is averred that the balance claimed is “for excavating and [2] building a certain piece of roadbed of the Chicago, Milwaukee & St.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gibbs v. Gardner
80 P.2d 370 (Montana Supreme Court, 1938)
Conner v. Helvik
73 P.2d 541 (Montana Supreme Court, 1937)
Continental Supply Co. v. White
12 P.2d 569 (Montana Supreme Court, 1932)
Mason v. Swee
198 P. 356 (Montana Supreme Court, 1921)
Johnson v. Erickson
185 P. 1116 (Montana Supreme Court, 1919)
Loud v. Hanson
164 P. 544 (Montana Supreme Court, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
143 P. 966, 49 Mont. 506, 1914 Mont. LEXIS 85, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dean-v-stewart-mont-1914.