Dean v. Mayor of New York

45 A.D. 605, 61 N.Y.S. 374
Appellate Division of the Supreme Court of the State of New York·Decided December 15, 1899·Published·Cited by 2 cases

Opinions

Ingraham, J.:

This action was brought to recover upon three separate causes of action. The first was to recover the balance alleged to be due for [606] work and services performed under a contract between the plaintiff and the defendant. The second was to recover for the Value of extra work done by the plaintiff, and the third was for damages caused by the defendant’s preventing the plaintiff from performing the entire work under the contract. The contract was for regulating and, grading Dyckman street, in' the city of New York.The second cause of action was dismissed upon the trial, no exception being taken by the plaintiff. The answer of the defendant denied that the plaintiff had earned the balance claimed to be due under the first cause of action and alleged that a certain certificate given' by the officers of the defendant as to the amount of the work performed under the contract was false, fraudulent, untrue and •made in bad faith;, in that it did not state the true and correct amount and character of the work actually, done and materials actually furnished' by the plaintiff under the said contract; that the defendant had paid to the plaintiff, relying upon such certificate, the sum of $26,-514.99 over an.d above the true value, at the contract prices, of the work and materials actually done and furnished by the plaintiff under the contract, and demanded by way of counterclaim a judgment against the plaintiff for that sum; and in answer to the third- cause of action alleged that, under the contract and the plan and specifications therein referred to, the plaintiff was not entitled to do any work except that which he actually did in the said street, and denied that the defendant -wrongfully and unreasonably and in violation of the said agreement neglected to permit the plaintiff to furnish and provide all the materials and , labor for the purpose of the performance of the work to be done under the contract.

Upon the 'trial the third cause of action was dismissed by the court and the plaintiff excepted, and the question as to the amount of work performed by the plaintiff under the first cause of action was submitted to the jury who found a verdict for the defendant against the plaintiff, upon the defendant’s counterclaim,- for $20,694, and upon that counterclaim judgment was entered for the defendant against the plaintiff, from which judgment the'plaintiff appeals.

The contract upon which this action -was brought was executed on September 21, 1891. There was annexed to this contract a proposal for estimates for regulating and grading Dyckman street from [607] Hudson river to Exterior street and setting curbstones and flagging-sidewalks therein. These proposals recited an ordinance by the defendant which provided that “ Dyckman street, from Hudson river to Exterior street, be regulated and graded, the curbstones set and sidewalks flagged a space four feet wide through the center thereof, under the direction of the commissioner of public works,” and sealed estimates for this work were to be presented to the department of public works. Such proposals contained the survey- or’s estimate of the nature and extent of the work to be done and materials to be furnished, and the bidders were to state in their estimates the price for excavating earth per cubic yard, the price for excavating rock per cubic yard, the price for furnishing filling per cubic yard and the price for furnishing and setting the curbstones,, new flagging and new culvert per square or lineal foot. In pursuance of these proposals estimates for the work were furnished by the plaintiff and others. That furnished by the plaintiff was accepted and the contract executed. By the contract the party of the second part (the plaintiff) agreed to furnish and provide all the materials and labor for the purpose of regulating and grading Dyckman street from Hudson river to Exterior street and setting curbstones and flagging sidewalks therein, and to strictly conform to the specifications contained and set forth in said contract. It was further agreed that the plaintiff would complete the entire work to the satisfaction of the commissioner of public works and in substantial accordance with the said specifications and the plan therein mentioned.

Free access — add to your briefcase to read the full text and ask questions with AI

Dean v. Mayor of New York, 45 A.D. 605, 61 N.Y.S. 374 (N.Y. Ct. App. 1899).

45 A.D. 605 (Dean v. Mayor of New York) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Kehler Estate
4 Pa. D. & C.3d 542 (Northumberland County Court of Common Pleas, 1978)
Haven v. The Mayor
67 A.D. 90 (Appellate Division of the Supreme Court of New York, 1901)