De Luxe Glass Co. v. Martin

208 P.2d 1127, 116 Utah 144, 1949 Utah LEXIS 178
CourtUtah Supreme Court
DecidedAugust 2, 1949
DocketNo. 7281.
StatusPublished
Cited by6 cases

This text of 208 P.2d 1127 (De Luxe Glass Co. v. Martin) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
De Luxe Glass Co. v. Martin, 208 P.2d 1127, 116 Utah 144, 1949 Utah LEXIS 178 (Utah 1949).

Opinion

*146 McDonough, justice.

Plaintiff as material supplier sued defendant Martin as general contractor, defendant Capson-Bowman, Inc., as owner of the land, and defendant General Casualty Company of America, as surety in the contractor’s performance bond, to recover the unpaid balance owing for certain materials purchased by defendant contractor in the construction of a store. The interveners were other materialmen who sought the same relief as plaintiff. From a judgment against the general contractor and against the surety, the latter only appeals.

The principal question raised by the appeal is the right of the materialmen to maintain the action against the surety.

On September 26, 1945, defendant George V. Martin, as general contractor entered into a written construction contract with defendant Capson-Bowman, Inc., by the terms of which contract the contractor agreed to construct a store building in Salt Lake City, in accordance with plans and specifications, for the sum of $30,000. Certain additions were subsequently made which increased the contract price to $32,406. The contract provided for payment of 90% of the contract price upon substantial completion of the entire work. Payment of the balance was due 15 days after substantial completion, provided the contract were then fully performed. Said contract also provided that

“Before issuance of final certificate the Contractor shall submit evidence satisfactory to the architect that all payrolls, material bills, and other indebtedness connected with the work have been paid.”

Included in the “General Conditions,” appeared the following :

“Unless otherwise stipulated, the Contractor shall provide and pay for all materials, labor, water, tools, equipment, light, power, transportation and other facilities necessary for the execution and completion of the work.”

*147 The owner required the execution of a performance bond, which was executed by the general contractor as principal and by defendant casualty company as surety, in the penal sum of $30,000 in favor of Capson-Bowman, Inc. The construction contract specifically provided that the owner should have the right to require the contractor to furnish a bond covering

“the faithful performance of the contract and the payment of all obligations arising thereunder.”

The principal portions of the bond furnished are as follows :

“The condition of this obligation is such, that whereas the Principal entered into a certain contract, hereto attached, with the Obligee, dated September 26, 1945, for construction of grocery store and drug store complete with fixtures, per plans and specifications. Located at 3000 South Highland Drive, Salt Lake City, Utah.
“Now, therefore, if the Principal shall well and truly perform and. fulfill all the undertakings, covenants, terms, conditions and agreements of said contract during the original term of said contract and any extensions thereof that may be granted by the Obligee, with or without notice to the Surety, and during the life of any guaranty required under the contract, and shall also well and truly perform and fulfill all the undertakings, covenants, terms, conditions and agreements of any and all duly authorized modifications of said contract that may hereafter be made, notice of such modifications to the Surety being hereby waived, then, this obligation to be void; otherwise to remain in full force and virtue.”

No liens were filed by any of the subcontractors or mater-ialmen ; but it was stipulated that certain bills and charges were justly due and owing to them, including plaintiff and all of the interveners. There was no question as to the liability of the general contractor. The materialmen asserted that if the owner, Capson-Bowman, Inc., failed to secure a good and sufficient bond, then in that event the owner was liable to them under the statutes, secs. 17-2-1, and 2, U. C. A. 1943, and in the event the owner was protected by a good and sufficient bond, then the surety as well as the contractor was liable to them. The trial court *148 held that the bond sufficiently complied with the statute to exempt the owner from liability and held that the contractor and his surety were liable.

On this appeal the surety company contends that it was not liable to any of the materialmen because: (1) The “performance bond” does not by its terms cover the material-men and subcontractors, and protects only the owner and not plaintiffs and interveners. (2) That it was released from any liability to the owner by reason of the fact that the owner made payments in excess of the amounts specified in the contract.

The second contention merits only brief mention. By the terms of the contract, the owner was obligated to make payments only up to 90% of the work completed, and only on presentation of lien waivers. It was stipulated that payments were made in excess of 90%, and that lien waivers were not obtained. The owner held back somewhat less than 10% of the contract price, which it paid into court. Although the surety claimed that it was prejudiced as a matter of law, it offered no evidence of prejudice. Prejudice cannot be presumed. So far as appears from the record, the payments made to the contractor in excess of 90 % of the contract price may have been applied on obligations owing to materialmen. The retention of such excess might well have resulted in increasing the materialmen’s claims by an amount equal thereto. It was admitted that no liens were filed. The failure to obtain lien waivers could not, therefore, have resulted in any prejudice. The contention that the surety was released by reason of being prejudiced by the conduct of the owner, must be overruled.

The remaining question is whether the bond was given in substantial compliance with the requirements of the statutes, so as to relieve the owner from liability and enable the claimants against the contractor to recover against appellant as surety on that bond. Appellant, as *149 stated, contends that the bond by its terms was not designed to protect the materialmen and subcontractors who sued herein as plaintiff and as interveners. It also argues that the statute requires the bond to contain certain terms, which this bond does not contain. The statute in question is quoted below. The portions thereof emphasized in the argument of appellant, are italicized:

“17-2-1. Bond to Protect Mechanics and Materialmen.
“The owner of any interest in land entering into a contract, involving $500 or more, for the construction, addition to, or alteration or repair of, any building, structure or improvement upon land shall, before any such work is commenced, obtain from the contractor a bond in a sum equal to the contract price, with good and sufficient sureties, conditioned for the faithful performance of the contract and prompt payment for material furnished and labor performed under the contract. Such bond shall run to the owner and to all other persons as their interest may appear;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Senor T's Restaurant v. Industrial Commission
641 P.2d 877 (Court of Appeals of Arizona, 1981)
Lignell v. Berg
593 P.2d 800 (Utah Supreme Court, 1979)
Utah State Building Board v. Walsh Plumbing Company
399 P.2d 141 (Utah Supreme Court, 1965)
Boise-Payette Lumber Co. v. Phoenix Indemnity Co.
280 P.2d 448 (Utah Supreme Court, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
208 P.2d 1127, 116 Utah 144, 1949 Utah LEXIS 178, Counsel Stack Legal Research, https://law.counselstack.com/opinion/de-luxe-glass-co-v-martin-utah-1949.