De Avila v. Espinoza Metal Bldg. & Roofing Contractors

564 S.W.3d 150
CourtCourt of Appeals of Texas
DecidedAugust 29, 2018
DocketNo. 08-15-00283-CV
StatusPublished
Cited by2 cases

This text of 564 S.W.3d 150 (De Avila v. Espinoza Metal Bldg. & Roofing Contractors) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
De Avila v. Espinoza Metal Bldg. & Roofing Contractors, 564 S.W.3d 150 (Tex. Ct. App. 2018).

Opinion

YVONNE T. RODRIGUEZ, Justice

Appellant appeals the trial court's judgment against him in the amount of $12,594.03 for breach of contract. In a single issue, Appellant claims there was legally and factually insufficient evidence to support the trial court's finding that he was in breach of contract when he evicted Appellee from the job site before the contract was fulfilled because he was free to terminate the agreement at his convenience. Alternatively, he asserts that the evidence clearly established the Appellee breached the contract before Appellant's alleged breach. We affirm.

*153BACKGROUND

Eduardo De Avila, as sole proprietor of Avilart MDA Construction, entered into a contract with Espinoza Metal Building & Roofing Contractor in February 2011 to preform roofing repairs at the Tigua Business Center in El Paso, Texas. Juan Espinoza headed the building and roofing company and was one of a number of subcontractors working on the project for De Avila. The contract required Espinoza to install a type of energy-efficient roofing-system, known as Thermoplastic Polyolefin TPO Roofing, which Espinoza had been specially certified to install by the manufacturer. The contract provided Espinoza would be paid $87,475 for the job. No timetable or date of completion was specified for the installation, but the contract provided that "Time is of the essence of the Subcontract." A provision of the contract also allowed De Avila to terminate the contract with or without cause by providing forty-eight hours' notice of termination in writing. The contract further required that any modifications to the agreement be made in a writing signed by both parties.

Espinoza began working on the roofing system in August 2011. The trouble began in October. Demolition by other subcontractors was ongoing, and at some point a decision was made to move HVAC units from the interior of the building-as provided for in the original contract-to the roof, which required holes to be drilled in the roof for installation. The roofing system was almost complete when the other contractors began drilling the holes in the roof for the HVAC installation. With the holes now drilled, Espinoza would need to install new insulation, bonding adhesive, roofing material, and counter flashing all at additional cost in order to maintain the 20-year manufacturer's warranty for the TPO roof system. Espinoza prepared a change order-a written proposal for modification to the original contract-quoting a $650 estimate per unit for labor and parts for the eight HVAC units. The change order also quoted $50 per TPO boot-a device for the HVAC roof penetrations that was provided by the TPO manufacturer-and estimated four boots per HVAC unit would be needed. Espinoza sent the change order to De Avila on October 25, 2011.

Initially, there was no response from De Avila to the change order; instead, a quarrel began regarding Espinoza's performance to date. On November 22, De Avila sent an email to Espinoza requesting he fix alleged roof leaks and make the penetrations for the HVAC units water tight. Espinoza claimed he went to the job site to inspect the leaks but did not find any. De Avila then sent a written letter to Espinoza on November 29, asserting Espinoza had failed to complete the roofing work in a timely fashion and demanding it be completed no later than December 10, but not mentioning the HVAC issue. On December 1, Espinoza arrived at the job site to find all of his remaining material and work supplies missing. Believing the items had been stolen, Espinoza called the police and was in the process of filing a report when De Avila arrived. De Avila stated that he had removed all of Espinoza's materials and supplies from the job site. Sometime in late December, while working on the roof, De Avila ordered the Espinoza crew off of the job site. They did not return.

On January 4, 2012, De Avila finally responded to the change order, sending a copy of the order back to Espinoza with the line for the TPO boots at $50 per boot crossed out and noting the approved price for the change order as $4,550. In an undated response, Espinoza sent the change order back approving the new price but stating that unless a payment of $2,335-representing *154about half of the additional cost-was received by January 6, no work would be completed. No response was given, and Espinoza did no further work on the project. De Avila hired a new subcontractor in mid-January to complete the roof installation.

Espinoza sued De Avila in March 2013, stating claims for breach of contract and quantum meruit, and seeking the outstanding balance due on the contract of $12,594.03 and attorney's fees. In a counter claim, De Avila sought damages for having to hire a subcontractor to complete the work. During the bench trial, Espinoza testified his company's roofing work was 95 percent complete when De Avila removed the supplies and building materials from the job site. Espinoza's brother, who had worked on the job with Espinoza, also testified at trial and stated they had completed between 95 and 98 percent of the work at the time De Avila forced them off the job site. De Avila in turn testified that he had been dissatisfied with Espinoza's job performance since October 2011, stating that Espinoza had been difficult to reach and had not been attending the weekly contractors' meetings with any regularity. He further testified that Espinoza had never repaired the leaks De Avila complained of in his November 22 email. The trial court found for Espinoza, awarding him $12,594.03 for his breach of contract claim and $10,500 in attorney's fees. This appeal followed.

DISCUSSION

In a single issue, De Avila claims the trial court erred in finding he was in breach of contract, claiming there was legally and factually insufficient evidence to support the finding. Specifically, De Avila asserts the evidence demonstrated Espinoza breached the contract first by refusing to complete the work provided for in the original agreement. Alternatively, he asserts he was free to terminate the contract at his convenience and therefore could not have been in breach of contract for removing Espinoza's materials or forcing his workers off the job site.

Legal Sufficiency of the Evidence

Standard of Review

When reviewing a claim that the evidence is legally insufficient to support a finding, we only consider the evidence and inferences that to tend support the finding and disregard all evidence and inferences to the contrary. City of Keller v. Wilson , 168 S.W.3d 802, 827 (Tex. 2005) ; Trammell v. Trammell , 485 S.W.3d 571, 575 (Tex.App.--Houston [1st Dist.] 2016, no pet.). Findings of fact entered in a bench trial have the same force and dignity as that of a jury's verdict upon questions. Hernandez v. Hernandez , 547 S.W.3d 898, 900 (Tex.App.--El Paso 2018, pet.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DBR Custom Builders, LLC v. Hector Marrufo
Court of Appeals of Texas, 2025
Onyd, LLC v. Chandra a Williams
Court of Appeals of Texas, 2020

Cite This Page — Counsel Stack

Bluebook (online)
564 S.W.3d 150, Counsel Stack Legal Research, https://law.counselstack.com/opinion/de-avila-v-espinoza-metal-bldg-roofing-contractors-texapp-2018.