DCI Properties-DKY, LLC v. Coppage Construction Co.

465 S.W.3d 886
CourtCourt of Appeals of Kentucky
DecidedJuly 14, 2015
DocketNO. 2013-CA-001932-MR
StatusPublished
Cited by1 cases

This text of 465 S.W.3d 886 (DCI Properties-DKY, LLC v. Coppage Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DCI Properties-DKY, LLC v. Coppage Construction Co., 465 S.W.3d 886 (Ky. Ct. App. 2015).

Opinion

OPINION

STUMBO, JUDGE:

DCI Properties appeals from an order granting Coppage Construction’s motion to dismiss. The issues involved are matters of first impression. We find that the trial court erred in dismissing DCI’s cause of action; therefore, we reverse and remand for further proceedings.

This case arises out of DCI’s construction of a sewer line funded in part with public funds. In 2007, Sanitation District No. 1 of Northern Kentucky (SD1), a public entity, contracted with DCI to design, construct, and manage the project. DCI then subcontracted with Coppage for the actual construction of the sewer line. The project experienced delays and DCI ultimately terminated its contract with Cop-page. On September 25, 2008, Coppage filed a lien pursuant to Kentucky Revised Statutes (KRS) 376.210 in the amount of [888]*888$3,758,784.31. Pursuant to that statute, because the sewer line was being built by a public entity, Coppage could only put a lien on the funds due to the contractor, DCI.

DCI filed a notice of protest to the lien pursuant to KRS 376.250. Also pursuant to this statute, when DCI protested the lien, SD1 was required to set aside the lien amount from the funds to be paid to DCI under the SD1 contract. Fortunately, Coppage’s lien did not result in an immediate cessation of payments by SD1 to DCI because there were sufficient funds available under the contract for SD1 to continue paying DCI until October of 2009. At that point, DCI received no further payment from SD1.

In November of 2008, Coppage filed an action in Campbell Circuit Court to enforce its hen. DCI 'filed its answer on December 15, 2008, in which it. alleged the lien amount was excessive. DCI did not file any kind of counterclaim at this time. On January 4, 2010, the trial court entered an order finding that Coppage’s lien was excessive in the amount of $2,977,245.02. On January 28, 2010, the parties agreed to the entry of an order which called for SD1 to set aside $935,041.09 to pay Coppage, released the lien as to $2,823,743.22, and dismissed the action.

On April 14, 2010, DCI filed the underlying complaint pursuant to KRS 376.220(3) seeking damages caused by Coppage’s excessive lien. KRS 376.220(3) states:

If any person files a statement asserting a lien against any contractor on any fund due the contractor, for an amount in excess of the amount actually due, the person filing the hen shall be liable to any person damaged thereby to the extent of such damage, including reasonable court costs and attorney’s fees incurred by the injured parties. Any such claim for damages may be asserted and prosecuted in the county in which the hen statement was filed.

On May 25, 2010, Coppage filed a motion to dismiss arguing that the claim was barred by Kentucky Rules of Civil Procedure (CR) 13.01 as a compulsory counterclaim to the prior htigation and under general principles of res judicata. CR 13.01 states in pertinent part:

A pleading shall state as a counterclaim any claim which at the time of serving the pleading the pleader has against any opposing party, if it arises out of the transaction or occurrence that is the subject matter of the opposing party’s claim and does not require for its adjudication the presence of third parties of whom the court cannot acquire jurisdiction.

In essence, Coppage argued that the KRS 376.220(3) excessive hen claim should have been raised in the enforcement action.

On June 15, 2010, DCI filed a reply to Coppage’s motion to dismiss. DCI argued that its claim under KRS 376.220(3)" did not accrue until after the enforcement action was terminated and it was determined the hen was excessive. In the alternative, DCI argued that the claim did not accrue until DCI stopped being paid by SD1, which was approximately 10 months after it filed its answer. This would take it out of the province of CR 13.01 because the claim was not ripe “at the time of serving the pleading,” said pleading being the answer.

A hearing was held in this matter on August 15, 2013.1 On October 25, 2013, the trial court entered an order dismissing DCI’s case with prejudice. The trial court stated that if “DCI had a proper [889]*889counterclaim at the time Coppage brought the 08 Case, then it had to bring it as part of that case and nothing in KRS § 376.220(3) can compel to the contrary.” The court went on to say that “[i]f a counterclaim is compulsory, failure to bring it bars a later suit under the principles of res judicata.” The court ultimately found that “once SD1 was prohibited from paying contested monies ... the money was restrained by law; therefore, the injury was mature.” The court stated:

the Court finds DCI should have brought the claim it asserts in this action in the 08 Case. This is true even though, at the time it answered, DCI did not know whether ultimately the hen would be enforced or the specific dollar amount of its damage. DCI had been injured, and to impose a requirement that its damages had to be fixed or liquidated to constitute a cognizable claim imposes an additional requirement that is not supported in the law governing public liens.

The trial court then dismissed DCFs claim with prejudice and this appeal followed.

A motion to dismiss is governed by Kentucky Rules of Civil Procedure (CR) 12.02. “Under CR 12.02 a court should not dismiss for failure to state a claim unless the pleading party appears not to be entitled to relief under any state of facts which could be proved in support of his claim.” “In making this decision, the circuit court is not required to make any factual determination; rather, the question is purely a matter of law.” Accordingly, our review of orders of dismissal is de novo.

Certain Underwriters at Lloyd’s, London v. Abundance Coal, Inc., 352 S.W.3d 594, 596 (Ky.App.2011) (citations omitted).

The primary issue on appeal is whether or not DCI was required to assert its claim as a counterclaim during the enforcement action. Because the enforcement action and the excessive hen action both involved the same parties and subject matter, this issue can be determined by answering the following question: When did DCFs claim accrue?

If it accrued before DCI filed its answer in the enforcement action, then the excessive hen claim should have been brought as a counterclaim pursuant to CR 13.01. By not bringing the claim at that time, DCI would be barred from bringing it in a subsequent action due to thé civil rule and res judicata. Causes of action “may not be spht and tried piecemeal.” Egbert v. Curtis, 695 S.W.2d 123, 124 (Ky.App.1985).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
465 S.W.3d 886, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dci-properties-dky-llc-v-coppage-construction-co-kyctapp-2015.