Day v. Abernathy

133 S.E.2d 299, 204 Va. 723, 1963 Va. LEXIS 206
CourtSupreme Court of Virginia
DecidedDecember 2, 1963
DocketRecord No. 5644
StatusPublished
Cited by5 cases

This text of 133 S.E.2d 299 (Day v. Abernathy) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Day v. Abernathy, 133 S.E.2d 299, 204 Va. 723, 1963 Va. LEXIS 206 (Va. 1963).

Opinion

Snead, J.,

delivered the opinion of the court.

R. F. Abernathy and L. S. Abernathy, partners, trading as L. S. Abernathy & Co. instituted this proceeding1 against Sidney C. Day, Jr., Comptroller of Virginia; Department of Highways, Commonwealth of Virginia, and Howard Hugh Harris, State Highway Commissioner, defendants, seeking a judgment for the balance due on a contract between the plaintiff and the Highway Department, whereby the plaintiff was to construct a bridge and approaches to it for the Highway Department.

The partnership will be referred to as plaintiff.

The plaintiff’s claim was based on the theory that materials were purchased in accordance with the terms of the contract between the parties but were not used because the Highway Department eliminated them from the contract and substituted the use of other materials therefor. The plaintiff alleged that by reason of the change in specifications it was entitled to be reimbursed for the materials purchased and not used, the transportation costs incurred with respect to these materials, and expenses incidental thereto such as rental of special equipment beyond that required by the original contract.

[725]*725In their answer, the defendants denied certain allegations of fact set forth in plaintiff’s petition. They asserted that the change in the specifications was at the instance of the plaintiff, and that the plaintiff had been fully paid for the installation of piles under the terms of the contract. In its reply to the answer, plaintiff denied that the change was made at its instance, and again alleged that the change was made at the instance of the Highway Department. The plaintiff admitted that it had been paid the sum specified in the contract for the installation of the piles, but contended that its claim was for losses resulting from the change in the specifications.

The defendants moved for summary judgment and the motion was overruled. At the conclusion of plaintiff’s evidence and also at the conclusion of all the evidence the court overruled the defendants’ motions to strike plaintiff’s evidence. The jury returned a verdict for plaintiff in the sum of $15,403.07, and defendants’ motion to set it aside was overruled. Judgment was entered on the verdict, and we granted the defendants a writ of error.

The plaintiff is before us as a successful litigant, armed with a jury verdict that has been approved by the trial judge. All conflicts in the evidence have been resolved in its favor. Thus, under familiar principles, the evidence will be stated in the light most favorable to the plaintiff.

On March 2, 1960, the plaintiff entered into a written contract with the Highway Department to construct .607 miles of roadway, including a bridge across the Pamunltey river on Highway No. 360. The work was to be performed in accordance with the plans, Virginia Department of Highways Road and Bridge Specifications, dated April 1, 1958, supplemental specifications, and certain special provisions. They were incorporated as a part of the contract.

The plans provided for an abutment at each end of the bridge and seven piers between the two abutments. In each abutment and pier the plaintiff was required to drive a specified number of cast-in-place concrete piles. These piles are installed by driving steel tubes into the ground, after which they are filled with concrete. The specifications required that the thickness of the “wall metal” of these tubes be not less than 11 gauge. Lower gauge numbers denote a thicker shell. Compensation for the placement of cast-in-place concrete piles was fixed at $7.50 per linear foot.

Under the specifications, the use of several types of steel tubes was permitted. The plaintiff elected to use 7 gauge Canton mono-[726]*726tubes, which were fluted piles and thicker than the minimum gauge specified and “about the heaviest” gauge used “in this part of the country”.

The first piles were successfully driven at abutment B, which is on the King William county side of the river. The plaintiff then commenced driving the piles at pier 7, the first pier at the water edge next to abutment B. All save one of these tubes collapsed from pressure, which prevented the plaintiff from filling them with concrete as it was required to do. The plaintiff then proceeded to drive piles at pier 3, which was in the low ground of the opposite or Hanover county side of the river. Here again the same difficulty was encountered. The tubes collapsed from pressure. These conditions were brought to the attention of the Highway Department and conferences were had during which various alternate methods and devices were suggested by Highway officials for a successful accomplishment of the work. One suggestion was that holes be bored into which the tubes could be inserted. A drill and motor were procured for this purpose, but the drilled holes caved in before the tubes could be installed. The plaintiff then ordered and drove another type tube, which was permitted under the specifications and is known as a “Taylor Forge pile”. Since this tube did not collapse at the time, the plaintiff ordered and had delivered at the job site a sufficient quantity to complete the work. However, these tubes caved in, causing the test tube to collapse. With permission of the Highway Department the plaintiff opened the collapsed tubes at pier 7 sufficiently by means of a spud so that they could be filled with concrete.

After the installation of the “Taylor Forge piles” proved to be unsuccessful, another conference was had between the plaintiff and officials of the Highway Department. It was decided to substitute prestressed concrete piles for the cast-in-place concrete piles. Prestressed concrete piles are manufactured away from the project and the cost is approximately the same as cast-in-place piles, but they are more expensive to install. No increase in compensation was allowed for the substitution, because the U. S. Bureau of Public Roads, which contributed to the project would not approve an increase. According to L. S. Abernathy, the Highway Department decided to make the change.

Under the specifications, a work order is defined as “A written modification of the contract increasing, decreasing, deleting or adding [727]*727items at prices mutually agreed to by both parties and which, when duly executed by them, becomes a supplement to the contract.”

Work Order No. 1. was prepared by the Highway Department covering the modification. It reads in part:

“ENGINEER’S EXPLANATION OF NECESSITY FOR PROPOSED WORK:
“After observing failure of steel monotubes as being driven, it is evident that this type of pile cannot be satisfactorily driven in the type of material encountered.
“It is proposed to substitute 12" square prestressed concrete piles, Std. PSP-1 and special provision for prestressed concrete revised 2-24-60, in lieu of cast in place piles. It is believed that the prestressed concrete piles will be more suited to the conditions encountered.”

J. N. Clary, State bridge engineer, testified that the above was the determination of the engineers.

The work order was signed by all proper parties in June, 1960. However, L. S. Abernathy, prior to the time he affixed his signature and while the work order was being discussed, inquired of an official of the Highway Department “what I could do about collecting for these piles I had on hand”.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kathryn M. Saffert v. Fairfax County School Board
720 S.E.2d 139 (Court of Appeals of Virginia, 2012)
Wallace v. Dramberger
58 Va. Cir. 454 (Virginia Circuit Court, 2002)
Hargrave v. Tignor
24 Va. Cir. 353 (Stafford County Circuit Court, 1991)
Prospect Enterprises, Inc. v. Pennsylvania Manufacturers Ass'n
23 Va. Cir. 60 (Virginia Circuit Court, 1991)
City of Ballwin v. Hardcastle
765 S.W.2d 324 (Missouri Court of Appeals, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
133 S.E.2d 299, 204 Va. 723, 1963 Va. LEXIS 206, Counsel Stack Legal Research, https://law.counselstack.com/opinion/day-v-abernathy-va-1963.