Dawson Construction Co. v. Georgia State Financing & Investment Commission

417 S.E.2d 190, 203 Ga. App. 625, 1992 Ga. App. LEXIS 556
CourtCourt of Appeals of Georgia
DecidedMarch 10, 1992
DocketA91A1885
StatusPublished
Cited by2 cases

This text of 417 S.E.2d 190 (Dawson Construction Co. v. Georgia State Financing & Investment Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dawson Construction Co. v. Georgia State Financing & Investment Commission, 417 S.E.2d 190, 203 Ga. App. 625, 1992 Ga. App. LEXIS 556 (Ga. Ct. App. 1992).

Opinion

Pope, Judge.

In June 1985, plaintiff/appellant Dawson Construction Company, Inc. (“Dawson”) entered into a construction contract (the “Contract”) with defendant/appellee Georgia State Financing and Investment Commission (“GSFIC”) to renovate the Old State Office Building owned by GSFIC (the “Project”). On March 2, 1988, Dawson submitted Periodical Estimate No. 29 seeking to be paid $1,065,057.16 for work performed at the Project and retainage.

On March 4, 1988, Tom Dawson, president of the construction company, met with Bill Roberts of the GSFIC to review various claims filed by Dawson and its subcontractors seeking damages for a series of delays at the Project allegedly caused by defective plans and specifications prepared by GSFIC’s architect. Two of the subcontractors who had claims pending at this time were Hays Heating & Plumbing Company (“Hays”) and Ralph A. Davis Construction Company, Inc. (“Davis”). Another subcontractor, Centin Corporation, had not yet filed a claim but did so later. During this meeting, GSFIC apparently asserted claims against Dawson in the amount of $593,126 [626]*626allegedly caused by Dawson’s defective or unfinished work on the Project. At the end of the meeting, both parties agreed to defer negotiation of their respective claims until a later date. Tom Dawson claims that at no time during the meeting did Bill Roberts dispute the amount of money claimed by Dawson in Periodical Estimate No. 29.

On March 9, 1988, GSFIC sent Dawson a check in the amount of $863,599.06 made payable to Dawson and its surety. The back of the check contained an endorsement which read: “NEGOTIATION OF THIS CHECK CONSTITUTES PAYMENT IN FULL OF ITEMS LISTED ON THE VOUCHER.” The accompanying voucher provided: “FINAL PAYMENT EXCEPT FOR THE SUM OF $200,000.00 WITHHELD FOR INCOMPLETE WORK.” An accompanying memorandum quoted from Article E-25 (b) of the Contract as follows: “Acceptance of the final payment shall operate as and shall be a release to the owner from all claims of any kind or character under the contract except for such specific amount or amounts as may have been withheld to cover the fair value of any incomplete work, which has been certified by the architect under the provision of Paragraph (d) of Article 5 of the Form of Agreement as incomplete through no fault on the part of the contractor.” The bottom of the memorandum also noted that $200,000 was being withheld for incomplete work.

On March 11, 1988, Dawson wrote Bill Roberts a letter seeking confirmation of the agreement reached during the March 4 meeting to defer review of outstanding subcontractor claims. Dawson also noted that despite the conditional language on the voucher and memorandum providing that the check represented final payment except for $200,000 withheld for incomplete work. Dawson was not, by accepting the check, waiving its right to assert the various claims for damages by Dawson and its subcontractors.

On March 15, 1988, Mr. Roberts wrote to Dawson stating that during the March 4 meeting, Dawson agreed to give up one of its claims, referred to as the “granite claim,” if GSFIC paid a substantial portion of the retainage being held by GSFIC. According to the letter, it was in reliance on this agreement that GSFIC paid Dawson $863,599.06 as final payment less the sum of $200,000 withheld for incomplete work. GSFIC went on to deny certain of the pending subcontractor claims, but specifically noted that the claims made by Hays and Davis were considered still pending. After reminding Dawson that GSFIC also had unresolved claims against the construction company in the amount of $595,126 for defective or unfinished work on the Project, GSFIC offered to execute a mutual release or covenant not to sue if the parties agreed to settle their claims against each other. In such case, GSFIC would issue Dawson a check for the re[627]*627maining $200,000 of retainage. Neither party acted on this proposal.

After Dawson received Robert’s March 15 letter, it deposited the March 9 check first marking out the language on the back. GSFIC argued in support of its motion for summary judgment that Dawson’s acceptance of the March 9 check constituted an accord and satisfaction of all claims by Dawson and its subcontractors, except the claims made by Hays and Davis. The alleged accord and satisfaction included Dawson’s claim for the balance of retainage requested in Periodical Estimate No. 29 in the amount of $200,000.

On August 8, 1988, Dawson wrote GSFIC requesting one-half of the $200,000 retainage being withheld for incomplete work. On August 18, 1988, GSFIC issued Check No. 4123 payable to Dawson and its surety in the amount of $100,000. The back of the check contained the same conditional language as on the March 9 check referencing the voucher. The accompanying voucher provided: “FINAL PAYMENT EXCEPT FOR THE SUM OF $100,000.00 WITHHELD FOR INCOMPLETE WORK.” The memorandum accompanying the check and voucher stated that the memorandum supplemented the March 9 memorandum, and that $100,000 was being withheld for incomplete work. GSFIC argued in support of its motion for summary judgment that Dawson’s acceptance of the August 18 check constituted an accord and satisfaction of Hays’ and Davis’ claims, the only remaining claims under the Contract. Thus, it is GSFIC’s contention that an accord and satisfaction occurred in two parts, each covering separate and independent claims which, taken as a whole, encompassed all of Dawson’s claims on behalf of itself and its subcontractors.

On October 5, 1988, Dawson wrote GSFIC requesting payment of the remainder of the retainage and asked GSFIC to make a decision about the pending claims of Dawson and its subcontractors. On November 18, 1988, Bill Roberts responded by letter, stating that he had reviewed the claims of Dawson’s mechanical and drywall subcontractors with GSFIC’s architect and was denying them. (Although the record is not clear, Hays appears to be the referenced mechanical subcontractor, and Davis, the referenced drywall subcontractor.) The letter further provided: “We are anxious to make final payment as soon as possible. Final payment will be made promptly after all requirements of the contract have been met.” One of the requirements for final payment set forth in the letter was the delivery of a final certificate from the architect. On June 26, 1989, Dawson provided GSFIC with a statutory affidavit, but GSFIC never paid any further money to Dawson. Thereafter, Dawson, for itself and on behalf of Hays, Davis and Centin Corporation, which by this time had filed a claim against GSFIC for delay damages, brought this action to recover damages against GSFIC. GSFIC answered the complaint and [628]*628raised as one of its defenses, accord and satisfaction. GSFIC also filed a counterclaim against Dawson for damages incurred by GSFIC as a result of Dawson’s incomplete and defective work on the Project.

On August 16, 1989, two days after GSFIC’s answer in this action was filed, GSFIC sent Dawson a third check in the amount of $90,770.73 made payable to Dawson and its surety. This time the accompanying voucher and memorandum contained the following language: “FINAL PAYMENT AND SETTLEMENT OF ALL CLAIMS AND SUITS EXCEPT FOR THE SUM OF $7,500.00 WITHHELD FOR INCOMPLETE WORK.” Thus, three checks were tendered by GSFIC containing the language “final payment.” The third check was never negotiated by Dawson and was eventually returned to GSFIC at the request of GSFIC’s attorney, after the attorney notice GSFIC’s counterclaim in the action exceeded the amount of the check.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Whitlock v. George
499 S.E.2d 138 (Court of Appeals of Georgia, 1998)
Emory Rent-All, Inc. v. LISLE ASSOCIATES GENERAL CONTRACTORS, INC.
441 S.E.2d 926 (Court of Appeals of Georgia, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
417 S.E.2d 190, 203 Ga. App. 625, 1992 Ga. App. LEXIS 556, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dawson-construction-co-v-georgia-state-financing-investment-commission-gactapp-1992.