Dawson-Alamo1 JV, LLC

CourtArmed Services Board of Contract Appeals
DecidedMay 30, 2019
DocketASBCA No. 60590
StatusPublished

This text of Dawson-Alamo1 JV, LLC (Dawson-Alamo1 JV, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dawson-Alamo1 JV, LLC, (asbca 2019).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Dawson-Alamo 1 JV, LLC ) ASBCA No. 60590 ) Under Contract No. FA3047-10-D-OOI2 )

APPEARANCES FOR THE APPELLANT: Johnathan M. Bailey, Esq. Kristin E. Zachman, Esq. Bailey and Bailey, P.C. San Antonio, TX

APPEARANCES FOR THE GOVERNMENT: Jeffrey P. Hildebrant, Esq. Air Force Deputy Chief Trial Attorney Erika L. Whalen Retta, Esq. Justin D. Haselden, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE WILSON ON THE GOVERNMENT'S MOTION TO DISMISS COUNT TWO OF APPELLANT'S AMENDED COMPLAINT

Dawson-Alamo I JV, LLC (DAI or appellant) has appealed the contracting officer's (CO's) deemed denial of its certified claim for work performed, allegedly outside the statement of work (SOW). The Air Force (AF or government) has moved to dismiss count two of appellant's amended complaint, in which appellant raised the allegation of mutual mistake for the first time.

ST A TEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On July 12, 2010, the AF awarded Contract No. FA3047-10-D-OOI2 to DAI for miscellaneous construction projects on Lackland Air Force Base, San Antonio, Texas, and related installations. This was a fixed-price, indefinite-delivery, indefinite-quantity requirements contract. (R4, tab 3 at 2, 5-10)

2. On September 22, 2011, DAI was awarded Delivery Order (D035) for repair of the interior rooms at Lackland Air Force Base Building 150, valued at $2,500.000 (R4, tab 10 at 1-2).

3. The parties executed Modification No. 01, effective September 30, 2011, adding repairs and increasing the price of D035 by $500,000 to $3,000,000 (R4, tab 12 at 1-3). Bilateral Modification No. 03, effective March 25, 2013, incorporated a revised comprehensive SOW and estimate. This revised SOW added repairs to the understructure of Building 150 and increased the price ofD035 by $347,335.14 to $3,347,335.14. (R4, tab 15 at 1-4)

4. Appellant submitted a letter, dated October 29, 2012, to the CO outlining costs related to "the extensive changes to this project that has [sic] been established by [the government] and DAI JV. All items and tasks are needed to give the end user a useable/workable facility." (Supp. R4, tab 53 at 1) The government, by memorandum dated January 11, 2013, stated "your request is being returned without action. [The Civilian Engineering Center] feels that your letter does not state the facts clearly." (App. supp. R4, tab 145)

5. Appellant submitted a request for equitable adjustment (REA) to the AF, dated January 16, 2013, requesting payment of $465,521.98 for extra materials and work performed under the contract as well as a contract time extension of 210 days (R4, tab 21 at 1). Appellant's REA stated:

As you review the E4-Clicksf*l cost estimate and compare to the original SOW, you will find that all of the additional work was not included in the original scope of work or awarded task order, but all was coordinated and performed per [the government]'s direction .... Per [two government offices], all items were deemed necessary .... Additional items include, but are not limited to, electrical infrastructure, bracing for the TV's [sic], emergency exit corridor, and communications infrastructure, all of which were not part of the original SOW and E4Clicks cost estimate. Unfortunately several needed items were overlooked in the mechanical portion of the project as well. The original SOW and MOD#l called for 10 RTU's when the true requirement was for 12 units in this area of the construction including all necessary components.

(Id. at 1-2) Appellant then submitted a certified claim, dated August 8, 2013, to the CO requesting the same amount, arguing its performance of "additional work outside the scope of the awarded task order is a binding change under the Changes clause" (R4, tab 24 at 4). Appellant further noted:

During the performance of the Project the Government directed DA 1 to perform additional work that was beyond the scope of the agreed E4click [sic] estimate presented by

• E4Clicks appears to be a system for producing estimates of project costs.

2 the Government and accepted by DAI as the scope of the work for the project at the beginning of the project...the Government directed work amounted to $462,521.98.

(Id.) DA I attached its REA to its claim (R4, tab 24 at 65-80).

6. By email dated May 17, 2016, appellant appealed the deemed denial of its claim to the Board.

7. Appellant asserted in its June 28, 2016 complaint that the government directed it to perform work beyond the scope of the SOW. causing it to incur the extra mat~rials and work expenses, and argues that such changes were pursuant to the Changes clause (com pl. , 13 ). However, appellant later amended its complaint to include count two, alleging in the alternative mutual mistake (amended compl., 16). This legal argument was developed further in appellant's pre-hearing brief, in which appellant requested reformation of D03 5 on the basis of mutual mistake, though no longer in the alternative (app. pre-hearing br. at 53-59).

DECISION

The AF moves to dismiss appellant's mutual mistake allegation, asserting it is a new claim not submitted to the CO, and thus not within the Board's jurisdiction. In its motion, the AF argues mutual mistake requires proof of different elements and requests different relief than the constructive change theory, and that both of these issues indicate the mutual mistake count is a separate claim. As this separate claim was not submitted to the CO for a final decision, the AF posits that the Board lacks jurisdiction over it, and it must be dismissed.

In its response, appellant argues that the operative facts of its original claim provided for mutual mistake and the addition of this new legal theory does not alter the nature of the claim. Thus, it is not a new claim and the Board retains jurisdiction.

The Contract Disputes Act requires all claims by a contractor be submitted to the CO for decision. 41 U.S.C. § 7103(a)(l ). "We lack jurisdiction over claims raised for the first time on appeal, in a complaint or otherwise." Optimum Servs., Inc., ASBCA No. 57575, 13 BCA, 35,412 at 173,726 (citing Versar, Inc., ASBCA No. 56857, 10-1 BCA, 34,437 at 169,957). However, the Board possesses jurisdiction to entertain claims that arise from the same operative facts as those presented to the CO, seek essentially the same relief, and merely assert differing legal theories for that recovery. ABC Data Entry Sys., Inc., ASBCA No. 59865, 16-1 BCA , 36,557 at 178,048 (citing King Aerospace, Inc., ASBCA No. 57057, 16-1 BCA , 36,451 at 177,651). "Matching the elements of [the original legal theory] against the elements of the new legal theories [appellant] posed does not resolve the question

3 whether the claim before us in the amended complaint is the same one presented to the CO.'" Public Warehousing Co., ASBCA No. 56022, 11-2 BCA, 34,788 at 171,228 (citing URN Indus., Inc. v. United States, 962 F.2d 1013, 1024 (Fed. Cir. 1992)). "The introduction of additional facts which do not alter the nature of the original claim ... or the assertion of a new legal theory of recovery, when based upon the same operative facts as included in the original claim, do not constitute new claims." Trepte Constr. Co., ASBCA No. 38555, 90-1 BCA, 22,595 at 113,385-86. "In determining a claim's scope, we are not limited to the claim document but can examine the totality of the circumstances.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Dawson-Alamo1 JV, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dawson-alamo1-jv-llc-asbca-2019.