Dawon and Company USA, LLC v. Joonwoo Solutions, LLC

CourtCourt of Appeals of Georgia
DecidedMay 1, 2026
DocketA26A0694
StatusPublished

This text of Dawon and Company USA, LLC v. Joonwoo Solutions, LLC (Dawon and Company USA, LLC v. Joonwoo Solutions, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dawon and Company USA, LLC v. Joonwoo Solutions, LLC, (Ga. Ct. App. 2026).

Opinion

FIRST DIVISION BARNES, P. J., MARKLE and HODGES, JJ.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. https://www.gaappeals.us/rules

May 1, 2026

In the Court of Appeals of Georgia A26A0694. DAWON AND COMPANY USA, LLC v. JOONWOO SOLUTIONS, LLC.

BARNES, Presiding Judge.

We granted this interlocutory appeal to consider whether the trial court erred

when it denied defendant Dawon and Company USA, LLC (“Dawon”)’s motion to

dismiss and to compel arbitration in this dispute arising from the construction of an

electric vehicle battery facility in Bartow County. On appeal, Dawon argues that the

trial court erred because the parties’ so-called “second contract” was not separate

from and did not supersede their first, which contained an arbitration provision. We

agree and reverse.

As the Georgia Supreme Court has noted, and “because . . . an incorrect

determination that a dispute is not subject to arbitration may cause the parties unnecessary expense and delay,” trial courts should, “except in the clearest cases, .

. . certify orders denying a motion to compel arbitration.” Am Gen. Financial Svcs. v.

Jape, 291 Ga. 637, 644 n. 3 (732 SE2d 746) (2012) (citation modified). “[W]e review

de novo a trial court’s order granting or denying a motion to compel arbitration,” but

“the factual findings on which the ruling is based . . . will not be overturned unless

clearly erroneous.” C. R. of Thomasville, LLC v. Hannaford, 363 Ga. App. 581, 582

(871 SE2d 679) (2022) (citation modified).”The party seeking arbitration bears the

burden of proving the existence of a valid and enforceable agreement to arbitrate[,]”

and the question whether there is a valid agreement to arbitrate is “a matter of

contract . . . generally governed by state law principles of contract formation[.]” Id.

The record shows that in January 2024, plaintiff Joonwoo Solutions, LLC and

Dawon entered into a written “service agreement” by which Joonwoo would perform

certain construction work on the battery facility for $6.8 million. This first agreement

contained the following provision:

With the exception of any third party claim (impleader) asserted by Dawon against the SUBSUBCONTRACTOR [Joonwoo], if at any time any dispute, claim or controversy should arise between Dawon and [Joonwoo] with respect to any matter or thing arising out of or related to, or involved in any matter with this Agreement or with the construction project,

2 which dispute, claim or controversy is not controlled or determined by the dispute resolution procedures of the Subcontract, then such dispute, controversy of claim shall be settled by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association (“AAA”) and the Federal Arbitration Act. . . . This obligation to arbitrate survives any termination of this Agreement under other provisions thereof.

(Emphasis supplied.) The agreement also provided that in the event of Joonwoo’s

default, it “agree[d] to pay Dawon such reasonable attorney’s fees and related costs

as [it] may expend therein.” In a section entitled “Changes,” the agreement stated

that the parties would not change the terms of the contract without a written order.

That portion of the agreement further stated that the “Parties acknowledge that no

course of conduct or dealing between the Parties shall serve as a basis for any variation

of the requirements of the Agreement[.]”

On August 26, 2024, the parties entered into a so-called “second agreement”

clarifying that Dawon would pay $1.4 million of the agreed amount by September 4,

2024. The second agreement, which was executed in Korean, also stated that Joonwoo

would “adhere to the schedule for the designated section works by August 31” and

3 and would “make every effort to complete any defective or unfinished works by the

project’s conclusion.” Both parties signed this document.

In February 2025, however, after conflicts arose over the work and payment,

Joonwoo filed this action against Dawon and other defendants, alleging that the

project had run into significant delays and that Dawon was indebted to it for more

than $2 million. Joonwoo alleged that under the August 26 agreement, Dawon was

required to pay Joonwoo $1.4 million and that this agreement, which amounted to a

change order, concerned work that was outside the scope of the original agreement.

Joonwoo conceded that the “full terms of repayment for that work were to be agreed

upon later.” Joonwoo set out counts for breach of contract based on the agreements,

along with unjust enrichment and quantum meruit.

In May 2025, Dawon filed a motion to dismiss and to compel arbitration,

attaching the January 2024 service agreement and arguing that it contained a

mandatory arbitration clause which covered all disputes between it and Joonwoo

arising from the project. According to Dawon, although it had terminated the

agreement in December 2025 due to Joonwoo’s material breaches, the obligation to

arbitrate survived that termination. Thus, Dawon reasoned, dismissal of the lawsuit

4 was appropriate, along with recovery of the attorney fees expended in enforcing the

arbitration provisions of the agreement.

Joonwoo responded to the dismissal motion, arguing that the dispute between

it and Dawon stemmed from three separate agreements. Joonwoo claimed that after

executing the first agreement, the parties entered into the second agreement, which

did not reference the original agreement and was therefore independent of it.

Furthermore, Joonwoo argued, the parties then entered a third agreement, which was

not reduced to writing and concerned custodial services. Joonwoo claimed that the

arbitration agreement did not apply to it because it was a “subsubcontractor” under

the original agreement.

The trial court held a hearing, after which it found that Joonwoo’s claims

related solely to the August 2024 second agreement. The trial court stated that on the

hearing date, Joonwoo filed a Second Amended Complaint, which removed portions

of the complaint which had been based on the parties’ original January 2024

agreement. The court then found that the second agreement did not contain an

arbitration clause and did not incorporate by reference the original agreement.

Therefore, the trial court denied Dawon’s motion to dismiss, noting, however, that

5 it was not ruling on whether claims in the First Amended Complaint made under the

original agreement were subject to arbitration. The court explicitly limited its ruling

to Joonwoo’s claims under the second agreement. The trial court then certified its

ruling for review, and we granted Dawon’s timely application.

On appeal, Dawon repeats its argument that the parties’ dispute is subject to

arbitration.1

The parties’ first agreement was a six-page agreement accompanied by

seventeen appendices, which addressed the scope and quality of the work, insurance

coverage, the construction time schedule, and the timing and manner of payment. The

parties’ second agreement, executed in August 2025, consisted of a one-page

document written in Korean. Though the parties’ translations of this document differ

slightly, both versions of the second agreement are entitled “Agreement on Additional

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Atlanta Integrity Mortgage, Inc. v. Ben Hill United Methodist Church, Inc.
650 S.E.2d 359 (Court of Appeals of Georgia, 2007)
Simmons Co. v. Deutsche Financial Services Corp.
532 S.E.2d 436 (Court of Appeals of Georgia, 2000)
Samaca, LLC. v. Cellairis Franchise, Inc.
813 S.E.2d 416 (Court of Appeals of Georgia, 2018)
American General Financial Services v. Jape
732 S.E.2d 746 (Supreme Court of Georgia, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Dawon and Company USA, LLC v. Joonwoo Solutions, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dawon-and-company-usa-llc-v-joonwoo-solutions-llc-gactapp-2026.