Davis v. Utah Const. Co.

231 P. 816, 64 Utah 460, 1924 Utah LEXIS 58
CourtUtah Supreme Court
DecidedDecember 16, 1924
DocketNo. 4147.
StatusPublished
Cited by1 cases

This text of 231 P. 816 (Davis v. Utah Const. Co.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davis v. Utah Const. Co., 231 P. 816, 64 Utah 460, 1924 Utah LEXIS 58 (Utah 1924).

Opinion

FRICK, J.

The transactions involved in this action took place at a time when the Oregon Short Line Railroad was operated by the federal government through James C. Davis as director general of railroads, or by his predecessor, and hence Davis was made the nominal plaintiff, although the Oregon Short Line Railroad Company is the real party in interest.

The action was commenced by the director general, hereinafter called plaintiff, against both of the defendants to recover judgment for material sold and delivered as alleged in the complaint. The complaint states two causes of action. In the first cause of action, omitting all matters of inducement, it is in substance alleged that in October, 1919, and in February, 1920, the plaintiff “sold and delivered to the said defendants goods, wares, and material, ’ ’ describing them, ‘ ‘ of the reasonable value of” $7,632.32, no part of which has been paid. In the second cause of action the same material is described, and it is alleged that the same was “sold and delivered” to the defendants, and that they “promised to pay therefor” the said sum of $7,632.32. The plaintiff prayed judgment for said sum, with interest.

The defendants filed separate answers in which each denied that the material described in the complaint was sold and delivered to the answering defendant, and each denied all liability therefor.

Upon the foregoing issues the case was tried to the court without a jury. Omitting the matters of inducement, the court found that on the dates alleged in the complaint ‘ ‘ plaintiff sold and delivered to the defendants above named goods, Wares, and material,” describing the same of the value of $7,632.32. The court further found that “the said defendants promised and agreed with the plaintiff to pay it for said material” the sum of $7,632.32. As a conclusion of law the court found that the plaintiff was entitled to judgment *463 against the defendants jointly for said amount, and entered judgment accordingly.

Just before proceeding to the trial the respective parties stipulated in open court that the amount asked by plaintiff for the material is correct; that the material described in the complaint was all delivered either to one or to the other of the defendants; that the same was used in the construction of a railroad which is owned by the defendant J. A. Mcllwee & Son, and was constructed by the defendant Utah Construction Compay as contractor for said J. A. Mcllwee & Son; that one or the other of the two defendants is liable for said material; and that the only issue to be tried was which one of them is liable, each one denying liability. . The plaintiff, however, contended that the material was sold and delivered to both of the defendants, and that they are both liable therefor.

The defendant Utah Construction Company will hereinafter be called company.

The plaintiff then produced his evidence, which, in substance, is to the effect that in the late summer or fall of 1919 the defendant J. A. Mcllwee & Son desired to construct a railroad spur of a little over three miles in length to connect with the main line of the Oregon Short Line Railroad for the purpose of developing some phosphate deposits in Idaho; that J. A. Mcllwee took up the matter of constructing the railroad with the assistant engineer of the Oregon Short Line Railroad Company, and asked the engineer to make a preliminary survey; that the engineer caused a preliminary survey to be made, the expense of which was paid by J. A. Mcllwee & Son; that J. A. Mcllwee & Son intended to construct the railroad themselves, and with that end in view sought information from the engineer aforesaid regarding material and prices; that the engineer promised J. A. Mcllwee that he would take up the matter of obtaining the material from the Oregon Short Line Railroad Company with his superiors, and that he would later report to Mr. Mcllwee regarding the matter; that the engineer accordingly took up the matter with his superiors, and obtained consent from them *464 to furnish the material that Mr. Mcllwee wanted for the construction of the railroad from the railroad officials, and reported that fact to Mr. Mcllwee, and also quoted the prices for the several kinds of material that Mcllwee wanted, all of which was satisfactory to Mr. Mcllwee; that at that stage of the matter the engineer advised Mr. Mcllwee that it would be better for him to have an experienced contractor construct the contemplated railroad, recommending the company as being a competent and reliable contractor to do the work; that Mr. Mcllwee then presented a proposed contract to construct the railroad to the engineer for inspection; that afterwards J. A. Mcllwee & Son and the company executed the proposed contract, and the company agreed to furnish the material and labor, and to construct and complete the railroad for a specified sum; that it was stipulated in the contract that the company should have the benefit of any material that J. A. Mcllwee & Son had obtained at the same prices that they were to pay therefor; that Mr. J. A. Mcllwee, together with a representative of the company, then went to the Oregon Short Line Railroad Company’s offices at Salt Lake City and completed the arrangement for the material and the shipment and delivery thereof; that it was expressly agreed that the material should be billed against the company, and should be delivered as directed by J. A. Mcllwee & Son and the representative of the company, which was accordingly done; that all the material was delivered by the plaintiff as directed by J. A. Mcllwee & Son and by the company, and that all of it was received and receipted for by the company, and used in the construction of the railroad; that the company paid for about $30,000 worth of the material, but refused to pay for the material involved in this action; that the material in question was billed against both the company and J. A. Mcllwee & Son, and payment was demanded from both of them; that after the controversy arose respecting the payment for the material the president of the company wrote to the plaintiff under date of July 4, 1920, as follows:

"I am in receipt of yours of June 30th, relative to some little hills you have against our company, and note what you say about your efforts to get this account settled up. We are sorry for the *465 trouble they have caused you and the delay in payment of this account. The reason for the delay has been that there was some question about who was to pay for these bills, as to whether we were to pay them or the company for whom We were doing this wort. Of course there is no question about our responsibility to your company, and you can depend upon it that they will be straightened out this weeh.”

There is much other evidence which no doubt would be material in settling the accounts as between the defendants, but it is not of controlling influence respecting the rights of the plaintiff, and hence we shall not refer to the same.

At the time of the trial the district court informed the defendants that it would not attempt to determine the liability of the defendants as between themselves, but would merely determine whether the defendants were jointly liable to the plaintiff, and the court disposed of the matter upon that theory, and made its findings and conclusions accordingly.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sorenson v. Korsgaard Et Ux.
27 P.2d 439 (Utah Supreme Court, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
231 P. 816, 64 Utah 460, 1924 Utah LEXIS 58, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davis-v-utah-const-co-utah-1924.