Davis v. Bertschinger

241 P. 53, 116 Or. 127, 1925 Ore. LEXIS 126
CourtOregon Supreme Court
DecidedOctober 5, 1925
StatusPublished
Cited by4 cases

This text of 241 P. 53 (Davis v. Bertschinger) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davis v. Bertschinger, 241 P. 53, 116 Or. 127, 1925 Ore. LEXIS 126 (Or. 1925).

Opinion

BAND, J.

The defendant, A. Bertschinger, hereinafter referred to as the owner, appeals from a decree foreclosing a mechanic’s lien for labor performed by plaintiffs on a dwelling-house and lot *129 of which he is the owner. The transaction ont of which the lien arose was as follows: Bertschinger entered into a written contract with the firm of Fancher-McLean Company whereby said firm contracted to furnish all material and labor and completely construct said dwelling-house according to certain plans and specifications for a fixed sum. Fancher-McLean Company, in turn, entered into a written contract with the plaintiff Davis whereby he undertook to perform the carpenter work of constructing said dwelling-house in accordance with said plans and specifications for the sum of $725, and they undertook to furnish all material for the construction of the building. Davis also, in express terms, undertook to do the work in a workmanlike and satisfactory manner and to commence work at once and proceed with all possible speed to its final completion and to employ sufficient labor to continuously carry' on the work without interruption or delay on his part. Thereupon, Davis entered into an agreement with the plaintiff Sears whereby they mutually undertook to jointly perform the contract between Davis and Fancher-McLean Company, and pursuant thereto they jointly performed the labor for which the lien was claimed. They have been paid the sum of $600 only.

In the performance of the work plaintiffs were required, in addition to doing the work called for in the plans and specifications, to do other work and to make changes and modifications not included in said plans and specifications. While the said building was being constructed Fancher-McLean Company transferred and assigned their rights and interest under said contracts to the defendant Portland Construction Company, a corporation, and *130 • said corporation assumed all of the obligations of its assignor thereunder. After plaintiffs had substantially but not completely performed the contract between Davis and Fancher-McLean Company, Fancher-McLean Company and Portland Construction Company each became insolvent and were unable to proceed further in the performance of said contracts, and plaintiffs were unable to obtain the remainder of the material necessary for the complete performance of their contract from the Portland Construction Company because of its said insolvency. Plaintiffs notified the owner of their inability to get the material to complete the Davis contract and offered to perform upon tiieir part if he would furnish the required material. The owner failed to furnish such material, and thereupon Davis, in behalf of himself and Sears, filed a claim of lien upon said building together with the lot on winch it was situate, claiming the right to a lien for the sum of $545 and stated his demand as follows: “Sept. 27, 1921. To labor performed upon said building and used in the construction thereof, $1,145. Credits and offsets, $600. Balance due, $545.” The decree appealed from awards a lien to plaintiffs upon said building and lot for the sum of $209.50, costs and attorney’s fees.

Among other things, the answer of the defendant sets forth the contract between Davis and FancherMcLean Company and avers that plaintiffs, before the complete performance thereof, abandoned the contract and failed to completely perform the same; that plaintiffs failed to do the work in a workmanlike manner and failed to do the work with reasonable dispatch as required by the terms of their contract, and that by reason thereof the owner sus *131 tained damage in excess of the amount for which the lien was claimed. The evidence discloses that plaintiffs, at the time they ceased work on said building, had substantially but not completely performed the Davis contract; that some of the hardware provided for in the plans and specifications had not been affixed or attached to parts of the building, and that the same had not been furnished to plaintiffs; that they gave notice thereof to the owner of the building and requested him to furnish the same so that they could complete said contract and offered to perform if the same was furnished, but that the owner failed to furnish the same, and that for that reason alone plaintiffs discontinued work on the building after their work had been almost completely performed.

It also appears from the evidence that the Davis contract was made on May 6, 1921, and that the last work performed under it was on August 15, 1921; that Davis worked on the building 96 days, Sears 89 days, and that they hired a helper for 14 days and a shingler for 6 days; that the Portland Construction Company, at its own expense but without any cost or expense to the owner, employed other carpenters to assist plaintiffs in doing the work and paid for such labor the sum of $229.25. There is no evidence that any other part of the work of erecting the building was delayed by any failure of plaintiffs to keep the carpenter work sufficiently advanced to permit other work to be done. Under the Davis contract plaintiffs could only proceed as the material to be used was furnished, and there is no proof of any damage to the owner caused by any unnecessary or unreasonable delay of plaintiffs in doing the work contracted for.

*132 The contention that the work was not done in a workmanlike manner stands upon no better foundation, so far as can be gathered from anything contained in the record. In respect to the manner in which the work was performed, plaintiffs offered the testimony of many witnesses who testified that the carpenter work upon the building had been done in a good and workmanlike manner. Among these witnesses who so testified was a well-known architect who seems to have been entirely disinterested. He testified that he made an examination of the building, and found that the carpenter work in the building had been done in a good and workmanlike manner. There was much other evidence of the same import offered by the plaintiffs. There was, however, some evidence tending to show that some of the material furnished by the contractor and used by plaintiffs in the performance of the work did not conform to the requirements of the plans and specifications. In one instance, 2x8 timbers were used where 2x10 timbers were called for in the specifications. Because of this there is a slight sag or settlement in one part of the house.

There was also some evidence tending to show that because of defective plans and specifications some other slight defects existed, but as to both of these matters, plaintiffs had no control over them and were not responsible for the defects caused thereby. “The right of a subcontractor to a lien will not be defeated by defects in the work arising from the architecture.” 27 Cyc., p. 106, Point 47. The material used by plaintiffs was the material which the contractors had furnished and which, under their contract, plaintiffs were required to use. In *133 fact, they could use none other, for the evidence shows that plaintiffs objected to using the 2x8’s and were directed by the contractor to use the .same.

One of the defenses urged is that the lien is invalid because it does not contain “a true statement of plaintiffs’ demand after deducting all just credits and offsets” as required by Section 10195, Or. L.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boyer v. DAWSON ET UX
295 P.2d 159 (Oregon Supreme Court, 1956)
Drake Lumber Co. v. Paget Mortgage Co.
274 P.2d 804 (Oregon Supreme Court, 1954)
Warrenton Lumber Co. v. Smith
245 P. 313 (Oregon Supreme Court, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
241 P. 53, 116 Or. 127, 1925 Ore. LEXIS 126, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davis-v-bertschinger-or-1925.