DAVIS PICKERING & CO., INC. v. WORLEY FIELD SERVICES, INC.

CourtDistrict Court, E.D. Pennsylvania
DecidedFebruary 22, 2023
Docket2:22-cv-01837
StatusUnknown

This text of DAVIS PICKERING & CO., INC. v. WORLEY FIELD SERVICES, INC. (DAVIS PICKERING & CO., INC. v. WORLEY FIELD SERVICES, INC.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DAVIS PICKERING & CO., INC. v. WORLEY FIELD SERVICES, INC., (E.D. Pa. 2023).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA

DAVIS PICKERING & CO., INC., : Plaintiff, : CIVIL ACTION : No. 22-1837 v. : : WORLEY FIELD SERVICES, INC. : Defendant and Third-Party Plaintiff, : : v. : : BRASKEM AMERICA, INC. : Third-Party Defendant. :

MEMORANDUM

Schiller, J. February 22, 2023

Plaintiff Davis Pickering & Co., Inc. (“DPC”) was a subcontractor to Defendant/Third- Party Plaintiff Worley Field Services, Inc. on an electrical project for Third-Party Defendant Braskem America, Inc. When the project was completed, DPC asserted a claim against Worley, seeking to recover over $1 million in additional labor costs it allegedly incurred on the project due to COVID-19-related delays. Worley denied DPC’s claim pursuant to a “no damage for delay” clause in its subcontract with DPC, leading DPC to sue Worley for breach of contract and unjust enrichment. Worley then filed a Third-Party Complaint against Braskem for breach of contract and a declaratory judgment, seeking defense, indemnification, and reimbursement of Worley’s legal fees and the costs incurred in defending against DPC’s claims. Braskem now moves to dismiss Worley’s Third-Party Complaint against it pursuant to Federal Rule of Civil Procedure 12(b)(1) or 12(b)(6). It argues there is no case or controversy between Braskem and Worley because Worley’s claims are not ripe. Even if they are, Braskem contends Worley fails to state a claim against it because the contract between Braskem and Worley does not require Braskem to defend, indemnify, or reimburse Worley for DPC’s claims. For the reasons that follow, the Court denies Braskem’s motion. I. BACKGROUND Braskem owns and operates a manufacturing facility in Kenova, West Virginia. (Third-

Party Compl., ECF 12, ¶ 9.) On January 15, 2019, it entered into a Master Contract for Engineering, Procurement, Construction Management and Construction Services (“Master Contract”) with Worley1for services related to the design and installation of new electrical infrastructure at the facility (the “Project”). (Id. ¶ 10.) The Master Contract between Braskem and Worley itemizes “Other Reimbursable Costs” that Braskem must pay to Worley, including “Contractor and third party lawyers’ fees, court costs and related litigation expenses when incurred on behalf of or for the benefit of [Braskem]” and “[l]osses, expenses and deductibles in connection with the Project and not paid by insurance or otherwise reimbursed.” (Id. ¶ 13; see also id., Ex. C (Master Contract), Schedule D-1 at ECF p. 189-90.) Section 12.9 of the Master Contract also provides that if Braskem ever directed Worley

“to complete after a Force Majeure event, [Worley] shall be entitled to all reasonable and documented expenses it incurs in minimizing or mitigating the effects of the Majeure Event as set forth [t]herein, together with its demobilization, stand-by and remobilization costs, if any.” (DPC Compl., ECF 1, ¶ 27.) Those costs and any adjustments to the project schedule were required to be identified in a change order. (Id.)2

1 Jacobs Field Services North America, Inc., is identified as the “Contractor” on the Master Contract, but Jacobs was renamed as Worley after a legal entity name change effective June 20, 2019. (Third Party Compl. ¶ 11.)

2 Section 12.4.1 of the Master Contract also obligates Braskem to “defend, indemnify and hold harmless [Worley] from and against Losses arising out of Third-Party Claims for death, personal injury or property damage to the extent caused by the deliberate, reckless or negligent On February 28, 2019, Worley, acting as Braskem’s authorized representative, entered into an Agreement for Construction Subcontractor (“Subcontract”) with DPC. (Third-Party Compl., ¶ 14.) It alleges it did so “on behalf of or for the benefit of Braskem pursuant to Braskem’s agreement in the Master Contract to reimburse [Worley] for all amounts owed to DPC under the

Subcontract.” (Id. ¶ 15.) Section 8(C) of the Subcontract provides, in relevant part, that in the event DPC was delayed in performing its obligations, and such delay is caused by a[ ] . . . Force Majeure . . . [or] acts of civil . . . authority, and which are beyond the reasonable control of, and without any fault or responsibility on the part of [DPC], such delay shall be excused (an “Excusable Delay”), and the period of such delay shall be added to the Subcontract Schedule.

(Worley Answer to DPC Compl., Ex. A (DPC Subcontract), ECF 11 at ECF p. 26-27.) Section 8(E) of the Subcontract provides that no delay in the progress of the “Work under th[e] Subcontract, from any cause whatsoever . . . shall . . . give rise to any right to damages of any kind or nature from [Worley].” (Id. at ECF p. 27.) DPC “expressly acknowledge[d] and agree[d] that it shall receive no damage for delay.” (Id.) As stated in the Subcontract, DPC’s sole remedy against Worley for a delay was “the right to seek an extension in the Subcontract Schedule.” (Id.) Pursuant to the $14,245,754 Subcontract, DPC agreed to fabricate and install concrete, structural steel, equipment, and electrical components at the Project as the prime electrical contractor. (Third-Party Compl. ¶ 14.) DPC prepared and attached a Project schedule to the Subcontract. (Id. ¶ 16.) According to the schedule, DPC was to begin its work in February 2019

acts or omissions of [Braskem], its employees, or agents in connection with the Project.” (Id., Ex. C (Master Contract), § 12.4.1 at ECF p. 116; see also Third Party Compl., ¶ 12.) However, DPC alleges its losses were caused by COVID-19, not by death, personal injury, or property damage. (See DPC Compl., ¶¶ 13-22.) and complete electrical commissioning work on or before April 23, 2020. (Id.) However, on March 23, 2020, Braskem halted the Project for thirty-six working days due to the COVID-19 pandemic.3 (Id. ¶ 17.) DPC resumed its work on the Project on May 18, 2020. (Id. ¶ 18.) When it did, DPC “was not able to make nearly the same level of progress that it had pre-COVID” because of

circumstances including the need to implement COVID-19 mitigation efforts. (Id. ¶ 17.) Once DPC resumed work, DPC asked Braskem to pay for certain direct costs DPC incurred as a result of the pandemic. (Third-Party Compl., ¶¶ 19-20.) Braskem paid for costs including the purchase of face masks and cleaning supplies, an additional break trailer, idle equipment time, Saturday premium time, and additional management support. (Id. ¶¶ 19-20.) Braskem also implemented and executed a $37,000 craft retainage and $222,000 completion bonus program with those funds passing directly to DPC employees. (Id. ¶ 21.) On September 29, 2020, DPC submitted a Request for Equitable Adjustment to Worley. seeking $1,110,693.25 in labor costs for 16,214.5 hours of time spent “over and above what it planned to expend on the Project” because of the COVID-19 “mandated shutdown of the Project

site and the resultant need to later accelerate to recover the time lost to achieve [Braskem’s] desired pre-outage completion date.” (Id. ¶¶ 22-24.) DPC alleges Worley “summarily rejected” its claim “claiming DPC’s sole remedy for the impacts due to COVID-19 was a time extension.” (DPC Compl. ¶ 24.) Worley then submitted DPC’s Request for Equitable Adjustment to Braskem “[i]n accordance with terms of the Master Contract . . . .” (Third-Party Compl. ¶ 27.) Braskem denied DPC’s Request for Equitable Adjustment on February 9, 2021, “explaining that it was based entirely upon a non-compensable Force Majeure delay” consistent with the DPC Subcontract. (Id.

3 DPC alleges it “was forced to shut down as a result of a government mandate concerning the Coronavirus pandemic” on or around March 26, 2020.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maryland Casualty Co. v. Pacific Coal & Oil Co.
312 U.S. 270 (Supreme Court, 1941)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Federal Deposit Insurance Corporation, as Receiver for the First National Bank of Toms River, New Jersey v. Lawrence E. Bathgate, II Novasau Associates, a New Jersey Limited Partnership New Nas, Inc. T. Pamela Bathgate 54 Buena Vista Associates, a New Jersey Limited Partnership Tuscol Development, Inc., a New Jersey Corporation Old Monmouth Associates, a New Jersey Partnership Airport Associates, a New Jersey Partnership Gerald A. Gura the Club at West Deptford, a Limited Partnership, a New Jersey Limited Partnership State of New Jersey Columbia Savings and Loan Association Asset Recovery Management, Inc. William Bowman Associates, Inc. National Westminster Bank Nj, Successor to First Jersey National Bank/south. Lawrence E. Bathgate, II Novasau Associates New Nas, Inc. 54 Buena Vista Associates, a New Jersey Limited Partnership Tuscol Development, Inc., a New Jersey Corporation Old Monmouth Associates, a New Jersey Partnership, Third-Party v. William Barlow John C. Fellows, Jr. Ebert L. Hall Joseph P. Iaria David E. Johnson, Jr. Irene F. Kramer Jacqueline F. Pappas John F. Russo Leonard G. Lomell Office of the Comptroller of the Currency John McDougal Third-Party Federal Deposit Insurance Corporation, as Receiver for the First National Bank of Toms River v. Nla Associates Limited Partnership, a New Jersey Limited Partnership Lgp-I Limited Partnership, a New Jersey Limited Partnership Lgp-I Capital Corp., a New Jersey Corporation New Nas, Inc. Lawrence E. Bathgate, II Alan B. Landis Novasau Associates, a Limited Partnership, a New Jersey Limited Partnership. Lawrence Bathgate, II Novasau Associates, Limited Partnership New Nas, Inc. 54 Buena Vista Associates Tuscol Development, Inc. And Old Monmouth Associates (The Bathgate Defendants)
27 F.3d 850 (First Circuit, 1994)
Kelley Mala v. Crown Bay Marina
704 F.3d 239 (Third Circuit, 2013)
Guy M. Cooper, Inc. v. East Penn School District
903 A.2d 608 (Commonwealth Court of Pennsylvania, 2006)
Lichter v. Mellon-Stuart Company
193 F. Supp. 216 (W.D. Pennsylvania, 1961)
State College Area School District v. Royal Bank of Canada
825 F. Supp. 2d 573 (M.D. Pennsylvania, 2011)
Monarch Life Insurance v. Donahue
702 F. Supp. 1195 (E.D. Pennsylvania, 1989)
Save Ardmore Coalition v. Lower Merion Township
419 F. Supp. 2d 663 (E.D. Pennsylvania, 2005)
Quinn Construction, Inc. v. Skanska USA Building, Inc.
730 F. Supp. 2d 401 (E.D. Pennsylvania, 2010)
Sandra Connelly v. Lane Construction Corp
809 F.3d 780 (Third Circuit, 2016)
Schuchardt v. President of the United States
839 F.3d 336 (Third Circuit, 2016)
Davis v. Wells Fargo, U.S.
824 F.3d 333 (Third Circuit, 2016)
Judd v. General Motors Corp.
65 F.R.D. 612 (M.D. Pennsylvania, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
DAVIS PICKERING & CO., INC. v. WORLEY FIELD SERVICES, INC., Counsel Stack Legal Research, https://law.counselstack.com/opinion/davis-pickering-co-inc-v-worley-field-services-inc-paed-2023.