Davies v. Rascon Manufacturing & Development Co.

7 Teiss. 73, 1909 La. App. LEXIS 20
CourtLouisiana Court of Appeal
DecidedDecember 13, 1909
DocketNo. 4795
StatusPublished

This text of 7 Teiss. 73 (Davies v. Rascon Manufacturing & Development Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davies v. Rascon Manufacturing & Development Co., 7 Teiss. 73, 1909 La. App. LEXIS 20 (La. Ct. App. 1909).

Opinion

Statement of Case.

ST. PAUL, J.

Plaintiff sues on a promissory note for [74]*74$1,722.50 with interest at 7 per cent, from October 8, Í907; and 10 per cent, attorney’s fees.-

Defendant pleads failure of consideration, averring that the note was given in part payment for a locomotive manufactured by plaintiff, which by reason of plaintiffs failure to comply with specifications, is not worth more than $3,445.00, the amount already paid thereon by defendant. Eleven instances of failure to comply with specifications are given.

Defendant also claims in reconvention the following items of damage, in all $5500.00, viz:

1. $2,000.00 for cost of repairing curves and .changing the radius thereof made necessary by reason of the wheel base of said locomotive having been made 8 feet instead of 7 as called for by the specifications.

2. $1,000.00 for cost of raising bridges made necessary by reason of the top of the smoke staok being 11 feet 2% inches above top of rails instead of 11 feet even, as called for by the specifications.

3. $1,000.00 for damages done to a track by reason of said locomotive weighing 46,640 lbs. in working order and 39,644 lbs. on the drivers, instead, of 36,000 lbs. in working order and 30,000 lbs. on the drivers, as guaranteed in the specifications.

4. $1,000.00 for annoyance and inconvenience of having a defective locomotive delivered, and for injury to defendant’s credit and standing by the filing of this suit.

5. By supplemental answer, $500.00 for delay in delivering locomotive on October 8,1907, instead of in eight weeks from July 12, 1907.

The District Court gave judgment for plaintiff as prayed for and allowed defendant a credit of $101.00.

Opinion.

The facts in this case so far as they are undisputed are as follows:

[75]*75Defendant owns a tract of 1,000,000 acres of land situated near Rascón Station in the State of San Louis Potosi, Republic of Mexico, part of which is under cultivation as a sugar plantation.

Some time in 1905, and subsequently thereto, plaintiff sold defendant a small locomotive and 18 kilometers of 20-lb. steel rails. In 1907, defendant through its president Dr. Geo. H. Lee, authorized one Freeman, the secretary and general manager, to purchase a large locomotive and the latter, after investigation, purchased the locomotive which gives rise to this controversy. The price was to be $5,167.50, payable one-third in cash on receipt of bill of lading, one-third November 1, 1907, and one-third February 1, 1908. By mutual consent the last two payments were deferred to January 1st and March 1st, respectively, and notes were given therefor. The locomotive was to be delivered F. O. B. cars at Wilkesbarre, Pa., eight weeks from July 12, 1907, and was actually loaded on cars October 4, 1907.

Tne locomotive reached the Rascón Station some time in November, 1907, and was taken to the plantation some days later. It was not then weighed or measured, but one ¥m. Stites, an assistant engineer, made an examination thereof and reported the following variations from specifications, five in number, viz:

1. Boiler provided with only two hand-hole plates instead of four.

2. Side-rods solid instead of jointed.

3. Tender equipped with hand brakes instead of steam brakes.

4. Only one headlight instead of two.

5. No ventilator in top of cab.

This report was reduced to writing February 1, 1908. (See Davies 2.)

[76]*76The cash payment of $1,722.50 was promptly .made on receipt of the hill of lading. On January 2, 1908, the first note being then due, Thomas H. Eoyer, treasurer, and Ernest Eager, Jr., secretary of the defendant company-called on plaintiff and endeavored to have the payment thereof deferrred, informing plaintiff orally that the locomotive did not conform to the specifications, but they made no mention of details as they themselves did not have the particulars. Plaintiff, however, insisted on immediate payment and agreed to make good any deficiencies. (Testimony Thos. Roger, p., 64; R. Rogers, Jr., p. 68.)

On February 13, 1908 (see Doc. PIff. 3), Stites’ report of February 1st, (Doc. Davies, 2), was transmitted to plaintiff and he was informed by letter that the deficiencies must be supplied before final settlement. Plaintiff acknowledged this letter at once, expressed his willingness to supply the deficiencies and stated that he was taking up the matter with the works that very day. He further invited attention to the fact that although the locomotive had been delivered at the plantation since November, 1907, this was the first official notice of the deficiencies therein which matter he mentioned simply in connection with the last clause of the defendant’s communication and for the purpose of reminding defendant that the matter had no bearing on the obligation due March 1st-coming. (See Doc. Pltff. 4.)

On February 24, 1908, plaintiff again wrote defendant (after hearing from the works), explaining how the deficiencies had occurred, and offered to supply, same at once without cost to defendant, or if defendant preferred to allow $100.00 as an offset. He asked for prompt answer (see Doc. Pltff 5). This letter was addressed to the local office and was transmitted to the president then at Ea'scon (see Document Plaintiff 6) from whom, how[77]*77ever, no. answer or acknowledgment was ever received (testimony Davies, p, 36).

The obligation dne March 1, 1908, was not paid at maturity. On March 3d plaintiff, through counsel, threatened suit (see letter Clegg & Quintero, March 3, 1908). On March 6th suit was filed.

On March 11th, defendant’s president, then at Rascón, caused the locomotive to be weighed, measured and reexamined, for the avowed purpose of finding objections to be urged against same. (Testimony Dr. Lee, pp. 39-40.) On this occasion the following additional variations from specifications were discovered; six in number, viz.:

1. Wheel base 8 feet instead- of 7.

2. Height to top of stack 11 feet 2% inches instead of 11 feet even.

3. Length of locomotive over all 40 feet 6 inches instead of 41 feet 4 inches.

4. Weight of locomotive in working order (three gauges of water) 46,640 lbs. (?), of which 39,644 lbs. on drivers; instead of 36,000 lbs. in working order, of which 30,000 lbs. on drivers.

5. Only 83 boiler tubes instead of 85.

6. Locomotive has an ordinary whistle instead of a Chime Whistle.

On March 8th the answer herein was filed, followed by the supplemental answer April 1, 1908.

The several matters complained of herein will be considered separately, as follows:

I.

The damages claimed, for delay in the delivery of the locomotive cannot be allowed. There is no evidence that [78]*78defendant suffered any damage thereby (Vincent, p. 10; Stites, pp. 4-5), nor was the delay ever complained of until the filing of this suit. (C. C., Art. 1933.) Moreover, whilst the locomotive was to be delivered F. O. JB. at Wilkesbarre, eight weeks from July 12, 1907 (i. e., Sept. 10, 1907), it was actually ready for shipment on Sept.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
7 Teiss. 73, 1909 La. App. LEXIS 20, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davies-v-rascon-manufacturing-development-co-lactapp-1909.