David Lemieux & Co. v. Letourneau

154 A. 454, 130 Me. 201, 1931 Me. LEXIS 52
CourtSupreme Judicial Court of Maine
DecidedApril 21, 1931
StatusPublished
Cited by1 cases

This text of 154 A. 454 (David Lemieux & Co. v. Letourneau) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
David Lemieux & Co. v. Letourneau, 154 A. 454, 130 Me. 201, 1931 Me. LEXIS 52 (Me. 1931).

Opinion

Pattangall, C. J.

On motion. Action on account annexed for labor performed and material furnished in the erection of a hotel. Defendants plead the general issue and, as a matter of special defense, “That the several items in plaintiff’s writ are embraced in the provisions of a written contract entered into by plaintiff and defendant.”

Plaintiff admitted that such a contract was executed and that the building was partially constructed under it but claimed that, during the progress of the work, on account of certain controversies concerning changes in the plans, the written contract was abandoned and a new agreement made whereby it was to receive compensation on the basis of per diem charges for labor, actual cost of material and a reasonable charge for superintendence.

While specifically denying any abandonment of the contract, defendants admitted that in addition to the price stated therein, [203]*203plaintiff was entitled to some compensation on account of certain minor changes in the plans and specifications and, ton the other hand, contended that they were entitled to credit because of having paid substantial bills for materials in order to relieve the property from lien claims.

It was apparent that however the principal contentions might be decided, the services of an auditor would be required in the final adjustment of the controversy, and the parties therefore agreed that the jury should be required to do no more than answer the question: “Was the written contract, dated October 19, 1928, between the plaintiff and defendants, abandoned?”; to which the jury answered, “Yes.”

The conclusion thus reached is binding upon this court unless the evidence preponderates so strongly against it as to make it a moral certainty that the jury erred. Inhabitants of Enfield v. Buswell et al, 62 Me., 128; Smith v. Brunswick, 80 Me., 191.

There was no dispute as to certain facts. Defendants projected the building of a hotel. An architect was employed, plans were made and bids asked for. Plaintiff submitted a bid. The amount was very much larger than defendants desired to invest and the plans were materially changed with the idea of reducing the cost of the building. Plaintiff examined the new plans and specifications and reduced its bid to conform to the changed conditions. Its bid was accepted, a contract was executed, work was begun on the building in the latter part of October, 1928, and continued until December 15 following when it was suspended until February 4, 1929.

In February one man worked five days and one-half on the job. In March the labor bill amounted to $334.73. In April the work was resumed on a substantial scale and continued until June 6 when the building was completed.

Plaintiff’s contract called for payment to it of $13,660.00. Including a payment of $500.00 on May 17, it received from defendants $10,632.75 and an order for $646.00 which it credited, making an admitted total credit of $11,278.75. In addition to these payments, defendants were liable for material bills amounting to four or five thousand dollars, so that unless plaintiff was entitled to a very substantial allowance for work and material not covered [204]*204by the contract, it had received all that was due it, assuming that the original contract remained in force.

It was plaintiff’s contention that the contract was abandoned in April, 1929, by mutual agreement and the new arrangement heretofore referred to substituted.

Its account annexed totalled $18,026.02. In this was included contractor’s profit, $1,493.18; bill of Pineland Lumber Company, $272.69; bill of A. N. Parent, $1,321.25; and bill of F. R. Conant Co., $3,048.74. There were also included per diem charges for superintendence at the rate of $15.00 per day, amounting to $670.00. These bills totalled $6,805.86. The Lumber Company bill, Parent’s bill and Conant’s bill had already been paid by defendants. There was then nothing due plaintiff on its own theory excepting its bill for superintendence and contractor’s profit. On the other hand, on defendants’ theory, plaintiff owed them between one and two thousand dollars.

It was obviously impossible to reach a final adjustment without the assistance of an auditor. All that could be determined in a trial before a jury was to fix a basis on which the accounting should be made. The plaintiff assumed the burden of proving the abandonment of the original contract and the substitution therefor of the agreement upon which it based its claim.

The record is voluminous. Including the exhibits, it fills three hundred and thirty-five pages, but the evidence directly bearing upon the question submitted to the jury is singularly brief.

Plaintiff’s agent, Mr. Boucher, testified that defendant George E. Letourneau insisted on so many changes in the plans and interfered with the progress of the work to such an extent that he, Boucher, on behalf of the plaintiff, at some time in April informed Letourneau that plaintiff considered the contract breached by defendants and would go no farther on the job unless some satisfactory agreement was substituted for the original undertaking, which he says was done. Mr. Boucher was unable to fix the exact date when the new contract was made but from certain admitted facts, it must have been made on April 22,1929, if made at all.

The changes in the plans were not extensive. They related principally to the work done in February and March, which, as has been indicated, was unimportant. Plaintiff could easily have kept [205]*205an account of them as extras and have been compensated for them under that head. They were not sufficient to create a situation which warranted it in rescinding the contract. Rescission could only be based on mutual agreement.

The case is bare of credible evidence that any such agreement was reached. Mr. Boucher’s testimony on this point is not only squarely contradicted by Mr. Letourneau but stands without corroboration, and the record contains abundant evidence in support of defendants’ position.

The building was erected under the supervision of an architect. Plaintiff drew money from time to time on architect’s certificates.

On April 17, Certificate No. 6 was issued. It read as follows:

“$1000.00 Certificate No. 6 Plan No. Apr. 17, 1929
To George E. Letourneau.
This is to Certify that under the terms of Contract dated ............for work on Hotel at Old Orchard, Me. David Lemieux & Co., contractor for General Construction is entitled to the six payment amounting to.................. One thousand and 00/100 .....................Dollars.
Notice
Amount of Contract $13660.00 - Additions to Contract Deductions from Cont. Pulsifer & Eye, Inc., - Architects, Total $13660.00 163 Main St., Lewiston, Me.
Am’t this Cert. $1000.00 Previously paid 8132.75 Gibbs & Pulsifer, Architects Per A. G. Pulsifer. Total paid to date 9132.75 Balance $4527.25”

On April 22, the very date when Mr. Boucher says the contract was abandoned and the new contract made, he signed the following receipt on the back of this certificate:

[206]*206“$1000.00 Lewiston, Me., 4/22, 1929. Received erom George E. Letourneau................

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Torrey v. Full Gospel Church of Searsport
394 A.2d 276 (Supreme Judicial Court of Maine, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
154 A. 454, 130 Me. 201, 1931 Me. LEXIS 52, Counsel Stack Legal Research, https://law.counselstack.com/opinion/david-lemieux-co-v-letourneau-me-1931.