David Bertram v. James Harberts D/B/A Exclusive Contracting L.L.C.

CourtCourt of Appeals of Iowa
DecidedJuly 19, 2017
Docket16-0919
StatusPublished

This text of David Bertram v. James Harberts D/B/A Exclusive Contracting L.L.C. (David Bertram v. James Harberts D/B/A Exclusive Contracting L.L.C.) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
David Bertram v. James Harberts D/B/A Exclusive Contracting L.L.C., (iowactapp 2017).

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 16-0919 Filed July 19, 2017

DAVID BERTRAM, Plaintiff-Appellant,

vs.

JAMES HARBERTS d/b/a EXCLUSIVE CONTRACTING L.L.C., Defendant-Appellee. ________________________________________________________________

Appeal from the Iowa District Court for Grundy County, David P. Odekirk,

Judge.

The plaintiff appeals from part of the district court’s ruling on a breach of

contract case. AFFIRMED IN PART, REVERSED IN PART, AND REMANDED.

Michael McDonough, Jacob W. Nelson, and Crystal R. Pound of Simmons

Perrine Moyer Bergmann PLC, Cedar Rapids, for appellant.

Chad A. Swanson (until withdrawal) and Nathan J. Schroeder (until

withdrawal), Waterloo, for appellee.

Considered by Vogel, P.J., Doyle, J., and Blane, S.J.*

*Senior judge assigned by order pursuant to Iowa Code section 602.9206 (2017). 2

BLANE, Senior Judge.

David Bertram appeals from the district court’s ruling in an action involving

claims and counterclaims for breach of contract. Bertram challenges the district

court’s conclusion he materially breached the written contract into which he and

the defendant, James Harberts, d/b/a/ Exclusive Contract, L.L.C., entered.

Additionally, he challenges the district court’s ruling regarding damages.

I. Background Facts and Proceedings.

Bertram, a farmer, wanted a pole barn constructed on his land. Sometime

in 2012, he contacted Harberts,1 an experienced builder.

After some back and forth regarding proposals and estimates, Harberts

completed a written contractor’s agreement on June 3, 2013, and submitted it to

Bertram. The parties signed the agreement on June 25. The agreement

provided Harberts would build an 80 foot by 105 foot pole barn, complete with

concrete floors, spray-foam insulation, and the framing for a number of interior

walls and doorways. The total cost—$265,210.00—included the necessary

supplies and labor. Bertram, by the terms of the agreement, was to initially pay

Harberts “$172,386.50 (reflecting 65% of total cost) . . . before work beg[an].

After assembly and construction of [the] building[], a predetermined amount of

$66,302.50 (reflecting 25% of total cost) [was to] be paid to the Contractor. After

interior floor installation ha[d] been completed, a predetermined amount of

$26,521.00 (reflecting 10% of total cost)” was to be paid to Harberts. The

contract also specified what Harberts was not responsible for, including the large

“overhead doors and openers,” among other things.

1 We refer to both the defendant and his business as Harberts throughout. 3

Bertram maintained he and Harberts had also agreed orally, before

signing the contract, both that Harberts would have the building completed “by

winter” and that Harberts would keep the money Bertram gave to him for the

project in a separate account. Harberts agreed he gave Bertram a projected

completion date and that he hoped to have the project completed by winter, but

he disagreed that the completion date was a contractual term. Additionally,

Harberts testified he never told Bertram his money would be kept separate from

the money Harberts’ business was receiving for other projects. Bank records

introduced at trial showed that Bertram’s money was deposited into Harberts’

business account, along with the funds for other projects.

Bertram made the first payment to Harberts of $172,386.50 on or about

the day the contract was signed. Harberts began construction at some point in

early July. The building itself was up by October 21, 2013, at which time

Harberts requested the second installment payment. Bertram made the second

payment of $66,302.50.

Around the same time the building was finished, Harberts and Bertram

had a discussion about the large overhead doors. Bertram had yet to pick or

order the doors, and he had neither hired someone to complete nor personally

completed the work that had to be done before the doors could be installed—

tasks that were his to undertake and were not within the contract. Harberts

advised Bertram he would not complete the insulation or concrete work until after

the doors were installed.

After the second payment was made, Harberts and Bertram agreed

Harberts’ company would complete certain “extras” for Bertram, including 4

installing the liner panel and doing some work that had to be completed for the

overhead doors to be installed.

Bertram chose the overhead doors on November 1; he was told it would

take seven to eight weeks for the doors to be delivered. On November 4,

Harberts paid the $7051 deposit on the doors.

Bertram wanted Harberts to work on completing the insulation and

concrete floor while they waited for the doors to be installed, but Harberts refused

to do so. Harberts later testified that he always did flooring last, stating he did

not want to drive his heavy equipment over the newly poured floors and wanted

to make sure the doors were in place first so he could use the cement work to

make sure they sealed tightly.

On December 17, Bertram’s attorney sent Harberts a letter indicating “Mr.

Bertram does not want any more work performed this winter. You are currently

holding $123,490 of Mr. Bertram’s money.” The letter asked Harberts to “deduct

amounts that you expended for the ceiling steelwork and forward the balance of

the money” to Bertram’s attorney. Harberts did not respond to the letter.

The overhead doors were installed on December 21, and Harberts’

company was sent an invoice for the rest of the bill by the door company, totaling

$14,452.

Bertram’s attorney sent Harberts another letter on January 3, 2014. It

stated the attorney had been “instructed” to “demand $135,000 payable to the”

firm’s trust account to “be held in escrow” at the firm’s office until Harberts

finished the project. It further indicated that once Harberts “finish[ed] the project 5

in the spring, that amount” would be paid to him. Harberts was told he had seven

days to respond to the letter before Bertram commenced litigation.

The parties then scheduled a meeting, which took place on January 10 at

the lending bank. At the meeting, Bertram demanded Harberts immediately

resume construction. Harberts testified he agreed he would get back on the job

site as soon as the weather allowed. At trial, Bertram expressed that he believed

Harberts had agreed to return to work “immediately.”

Harberts did not immediately return to the job site. He did submit an

invoice to the bank for the “extras” his company had completed and for the

amount owed to the door company, totaling $48,153. $21,503 of the balance

was for the doors—both the $7051 Harberts had paid in deposit and the

remaining balance after installation.

On January 16, both Bertram and his attorney sent Harberts letters.

Harberts responded in kind on January 29. No more work was completed on the

project before February 18, when Bertram’s attorney sent Harberts a letter

terminating the contract.

Bertram initiated this lawsuit on April 30. He claimed Harberts had “failed

and neglected to complete the construction of the building, ha[d] constructed

portions in a defective and unworkmanlike manner, . . . [and had] failed to return

the unearned funds paid to [him] despite demand for return of them by

Free access — add to your briefcase to read the full text and ask questions with AI

Related

NevadaCare, Inc. v. Department of Human Services
783 N.W.2d 459 (Supreme Court of Iowa, 2010)
Timberline Builders, Inc. v. Donald D. Jayne Trust
786 N.W.2d 873 (Court of Appeals of Iowa, 2010)
Ritam Corp. v. Applied Concepts, Inc.
387 N.W.2d 619 (Court of Appeals of Iowa, 1986)
Midland Mutual Life Insurance Co. v. Mercy Clinics, Inc.
579 N.W.2d 823 (Supreme Court of Iowa, 1998)
Fausel v. JRJ Enterprises, Inc.
603 N.W.2d 612 (Supreme Court of Iowa, 1999)
Andreas & Son v. Hempy
276 N.W. 791 (Supreme Court of Iowa, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
David Bertram v. James Harberts D/B/A Exclusive Contracting L.L.C., Counsel Stack Legal Research, https://law.counselstack.com/opinion/david-bertram-v-james-harberts-dba-exclusive-contracting-llc-iowactapp-2017.