Davey Compressor Company v. Dick Cheney, Secretary of Defense

985 F.2d 584, 1992 U.S. App. LEXIS 37555, 1992 WL 371923
CourtCourt of Appeals for the Federal Circuit
DecidedDecember 17, 1992
Docket92-1176
StatusUnpublished

This text of 985 F.2d 584 (Davey Compressor Company v. Dick Cheney, Secretary of Defense) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davey Compressor Company v. Dick Cheney, Secretary of Defense, 985 F.2d 584, 1992 U.S. App. LEXIS 37555, 1992 WL 371923 (Fed. Cir. 1992).

Opinion

985 F.2d 584

NOTICE: Federal Circuit Local Rule 47.8(b) states that opinions and orders which are designated as not citable as precedent shall not be employed or cited as precedent. This does not preclude assertion of issues of claim preclusion, issue preclusion, judicial estoppel, law of the case or the like based on a decision of the Court rendered in a nonprecedential opinion or order.
DAVEY COMPRESSOR COMPANY, Appellant,
v.
Dick CHENEY, Secretary of Defense, Appellee.

No. 92-1176.

United States Court of Appeals, Federal Circuit.

Dec. 17, 1992.

Before RICH, Circuit Judge, EDWARD S. SMITH, Senior Circuit Judge, and ARCHER, Circuit Judge.

PER CURIAM.

DECISION

Davey Compressor Company (Davey) appeals the October 7, 1991 decision of the Armed Services Board of Contract Appeals (ASBCA), which held: (1) that two claims filed by Davey with the Defense Logistics Agency (DLA) had not been properly certified under section 33.207(c)(2) of the Federal Acquisition Regulations (FAR), the implementing regulations for the Contract Disputes Act (CDA), 41 U.S.C. § 601, et seq.; and (2) that, because the claims had not been properly certified, the ASBCA lacked jurisdiction over the claims. We reverse and remand this case to the ASBCA for consideration on the merits of the DLA's March 1, 1989 decision denying Davey's claims.

DISCUSSION

* On August 24, 1988, Davey filed two claims with the DLA, which were certified by Carl Wurtz, Davey's Vice-President of Finance and Secretary/Treasurer. The DLA issued a decision denying these claims on March 1, 1989, and Davey appealed the DLA's decision to the ASBCA. On October 7, 1991, the ASBCA held that Wurtz did not have overall responsibility for the conduct of Davey's affairs, and therefore, Wurtz lacked authority to certify the claims on behalf of Davey. Accordingly, the ASBCA dismissed both of Davey's claims for lack of subject matter jurisdiction.

II

This Court's jurisdiction over appeals from decisions of boards of contract appeals arises under 28 U.S.C. § 1295(a)(10), and this Court's review of such decisions is limited by the CDA. A Board decision on an issue of fact will not be set aside unless it "is fraudulent, or arbitrary, or capricious, or so grossly erroneous as to necessarily imply bad faith, or if such decision is not supported by substantial evidence." 41 U.S.C. § 609(b) (1988). On questions of law, however, Board decisions are neither final nor conclusive, but are freely reviewable." American Elec. Labs., Inc. v. United States, 774 F.2d 1110, 1112 (Fed.Cir.1985).

III

The CDA requires that, for a claim against the government totaling more than $50,000:

the contractor shall certify that the claim is made in good faith, that the supporting data are accurate and complete to the best of his knowledge and belief, and that the amount requested accurately reflects the contract adjustment for which the contractor believes the government is liable.

41 U.S.C. § 605(c)(1) (1988). Davey is seeking $1,135,285.82 from the government, and therefore proper certification is required. United States v. Grumman Aerospace Corp., 927 F.2d 575, 578 (Fed.Cir.1991); W.M. Schlosser Co. v. United States, 705 F.2d 1336, 1338 (Fed.Cir.1983).

Section 33.207(c)(2) of the FAR limits the corporate officials who may certify a claim to:

(i) A senior company official in charge at the contractor's plant or location involved; or

(ii) An officer or general partner of the contractor having overall responsibility for the conduct of the contractor's affairs.

FAR 33.207(c)(2), 48 C.F.R. § 33.207(c)(2) (1990). Failure to comply with section 605(c)(1) of the CDA and its implementing regulations deprives the Board of jurisdiction to hear the claim. Grumman Aerospace, 927 F.2d at 579; see Ball, Ball & Brosamer, Inc. v. United States, 878 F.2d 1426, 1428 (Fed.Cir.1989).1

Davey does not argue in this appeal that Wurtz satisfied the requirements of FAR 33.207(c)(2)(i) at the time he certified the claims at issue. Therefore, that portion of the regulation is not under consideration. Rather, at issue in this appeal is whether Wurtz satisfied the second prong of the regulation, FAR 33.207(c)(2)(ii), at the time he certified the claims.

IV

As part of its review, the ASBCA made the following factual determinations regarding Wurtz's status at Davey at the time that he certified the two claims:

(1) Wurtz was the "no. 3" man in Davey's corporate hierarchy of six officers, below the two owners of Davey, Theodore Purvin, who was also the president and chief executive officer, and Thomas Purvin, who was also the vice president of operations;

(2) Wurtz "acted for" Davey in the absence of the two owners; and

(3) Wurtz was in charge of the accounting functions of Davey, as well as insurance matters, tax matters, and legal issues as they affected the company.

In addition to the foregoing, trial testimony indicated that Wurtz was authorized to sign contracts on behalf of Davey and that he also was responsible for executing Truth in Negotiating certificates on Davey's behalf.

Despite the foregoing, the ASBCA concluded that there was "no evidence that Mr. Wurtz was overall responsible for [Davey's] operations or business affairs." The ASBCA further stated that "although Mr. Wurtz could act for the corporation in the absence of its two higher officers," Wurtz had failed to suggest or prove that these superiors were absent on the day he certified the two claims.

V

The ASBCA erred in refusing to recognize Wurtz as an appropriate person to certify Davey's claims pursuant to FAR 33.207(c). As an elected senior executive officer of Davey, who was the "number 3 man" in the corporate hierarchy and who possessed the authority to sign contracts, to handle its legal and financial affairs, and to run the company in the owners' absence, Wurtz satisfied the requirements of FAR 33.207(c)(2)(ii). The ASBCA's analysis of Wurtz's functions was overly restrictive.

The ASBCA found, as a factual matter, that Wurtz "acted for" Davey in the absence of the two owners, who were the two higher ranking officers above Wurtz. Thus, notwithstanding Wurtz's numerous duties and responsibilities on a day to day basis, Wurtz was vested with the authority to manage or conduct Davey's overall affairs. There is no evidence that this authority was granted or taken away depending upon the absence or presence of the two owners. Indeed, the evidence merely establishes that Wurtz exercised this authority in the absence of the owners.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
985 F.2d 584, 1992 U.S. App. LEXIS 37555, 1992 WL 371923, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davey-compressor-company-v-dick-cheney-secretary-of-defense-cafc-1992.