Dave's Excavating, Inc. and Liberty Mutual Insurance Co. v. City of New Castle, Indiana

CourtIndiana Court of Appeals
DecidedJanuary 11, 2012
Docket33A04-1104-PL-199
StatusPublished

This text of Dave's Excavating, Inc. and Liberty Mutual Insurance Co. v. City of New Castle, Indiana (Dave's Excavating, Inc. and Liberty Mutual Insurance Co. v. City of New Castle, Indiana) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dave's Excavating, Inc. and Liberty Mutual Insurance Co. v. City of New Castle, Indiana, (Ind. Ct. App. 2012).

Opinion

FILED Jan 11 2012, 9:08 am FOR PUBLICATION CLERK of the supreme court, court of appeals and tax court

ATTORNEYS FOR APPELLANTS: ATTORNEYS FOR APPELLEE:

MICHAEL L. EINTERZ DAVID K. HERZOG MICHAEL L. EINTERZ, JR. JON LARAMORE Einterz & Einterz APRIL E. SELLERS Zionsville, Indiana Baker & Daniels LLP Indianapolis, Indiana

IN THE COURT OF APPEALS OF INDIANA

DAVE‟S EXCAVATING, INC., and ) LIBERTY MUTUAL INSURANCE CO., ) ) Appellants-Defendants, ) ) vs. ) No. 33A04-1104-PL-199 ) CITY OF NEW CASTLE, INDIANA, ) ) Appellee-Plaintiff. )

APPEAL FROM THE HENRY CIRCUIT COURT The Honorable Bob A. Witham, Special Judge Cause No. 33C01-0601-PL-1

January 11, 2012

OPINION - FOR PUBLICATION

NAJAM, Judge STATEMENT OF THE CASE

Liberty Mutual Insurance Company (“Liberty Mutual”) appeals two orders entered

by the trial court granting summary judgment in favor of the City of New Castle (“the

City”) in its suit against Dave‟s Excavating, Inc. (“Dave‟s”) on a construction contract

and against Liberty Mutual under a performance bond. Liberty Mutual presents four

issues for review, which we restate as:

1. Whether the trial court erred when it granted summary judgment in favor of the City on the issue of Dave‟s‟ liability under the construction contract.

2. Whether the trial court erred when it granted summary judgment in favor of the City on the issue of Liberty Mutual‟s liability under the performance bond.

3. Whether the trial court erred when it granted summary judgment in favor of the City and awarded attorney‟s fees.

We affirm.

FACTS AND PROCEDURAL HISTORY

On February 9, 2004, the City accepted bids for a sanitation project in the recently

annexed McGrew Sanitation Area for a sanitary sewer and watermain extension (“the

Project”). The bidders were informed that the engineer‟s estimated cost was $1,319,279.

Dave‟s was the lowest bidder at $983,737.61.1 On March 5, 2004, the City and Dave‟s

executed a construction contract for the Project (“the contract”).2 Liberty Mutual

1 The parties agree that the engineer served as the City‟s agent for the Project. United Consulting Engineers and Architects served as the engineer on the Project but is not a party in this case. 2 All references to the “construction contract” or “the contract” indicate the Standard General Conditions of the Construction Contract, which the parties referred to as the General Conditions. The 2 guarantied Dave‟s performance with its performance bond (“the performance bond” or

“the bond”).

After the Project was underway, Dave‟s requested change orders. In one instance,

the City allowed Dave‟s to use excavated materials as backfill to reduce additional costs

arising from the nature of subsurface conditions. Then, on June 17, 2004, Dave‟s sent a

letter to the engineer “declaring „Differing Subsurface Conditions‟ in accordance with

Section 4.03 of the General Conditions[.]” Appellant‟s App. at 140. Dave‟s also stated

that it was “stop[ping] Work until direction has been received by [sic] the Engineer.” Id.

Section 4.03 of the General Conditions provides:

4.03 Differing Subsurface or Physical Conditions

A. Notice: If CONTRACTOR [Dave‟s] believes that any subsurface or physical condition at or contiguous to the Site that is uncovered or revealed either:

1. is of such a nature as to establish that any “technical data” on which CONTRACTOR is entitled to rely as provided in paragraph 4.02 is materially inaccurate; or 2. is of such a nature as to require a change in the Contract Documents; or 3. differs materially from that shown or indicated in the Contract Documents; or 4. is of an unusual nature, and differs materially from conditions ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract Documents;

then CONTRACTOR shall, promptly after becoming aware thereof and before further disturbing the subsurface or physical condition or perform any Work in connection therewith . . . notify OWNER and ENGINEER in writing about such condition. CONTRACTOR shall not further disturb such condition or perform any Work in connection therewith . . . until receipt of written order to do so.

entire contract was comprised of the General Conditions as well as other documents. Other documents will be named specifically as referred to in this opinion. 3 B. ENGINEER‟s Review: After receipt of written notice as required by paragraph 4.03.A, ENGINEER will promptly review the pertinent condition, determine the necessity of OWNER‟s obtaining additional exploration or tests with respect thereto, and advise OWNER in writing (with a copy to CONTRACTOR) of ENGINEER‟s findings and conclusions.

Appellant‟s App. at 490. Dave‟s followed its June 17 letter with another letter on June

22, requesting a contract price increase to $1,807,960.73, an eighty-four percent increase,

to complete work under the construction contract due to the alleged differing subsurface

conditions at part of the Project site.

The Project‟s engineer replied by letter dated July 6, informing Dave‟s that the

engineer was reviewing the claim of differing subsurface or physical conditions. The

letter also referred Dave‟s to Article 6, Paragraph 18 of the General Conditions, which

provides in relevant part that

CONTRACTOR shall carry on the Work and adhere to the progress schedule during all disputes or disagreements with OWNER. No Work shall be delayed or postponed pending resolution of any disputes or disagreements, except as permitted by paragraph 15.04 or as OWNER and CONTRACTOR may otherwise agree in writing.

Appellant‟s App. at 503. The engineer‟s letter stated further that it was “to serve as

[Dave‟s] written notice that in accordance with the Contract Documents, Dave‟s is not to

delay or postpone work on the Project during resolution of [the] claim. Please

recommence work immediately.” Id. at 347. Counsel for Dave‟s replied on July 7 that

“it is not possible for the work to be recommenced until the differing condition issue

ha[d] been resolved.” Id. at 348. Dave‟s also stated that the engineer‟s failure to

investigate and propose a change order “renders the City in default of the contract, and

4 allows Dave‟s Excavating, Inc. the opportunity to rescind the contract, cease work, and

avoid any further liability.” Id. at 348.

The engineer replied on July 9, stating in part:

Please be aware that [neither] we nor the City agree with the interpretation of your legal council [sic] that you can refuse to re-commence work on the project on Monday[,] July 12 as previously agreed. There will be no additional tests or other subsurface investigation provided by the Owner as such investigation was otherwise your responsibility if deemed necessary prior to committing to the Contract Price and Time.

. . . The City has also advised our office to inform you that they [sic] will consider you in breach of this Contract if you are not present and working on the project at 8:00 a.m. local time on July 12, 2004[,] and will be pursuing your bond as well as other available legal remedies that may be appropriate.

Id. at 146 (emphasis added). Dave‟s completed work on the Project in all areas except

those related to the change order requests, but the City and Dave‟s could not reach an

agreement about the change orders based on the differing subsurface conditions claim.

On July 15, the engineer sent notice to Dave‟s and Liberty Mutual that the City

was considering declaring Dave‟s in default on the construction contract. That letter also

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bules v. Marshall County
920 N.E.2d 247 (Indiana Supreme Court, 2010)
Bailey v. Mann
895 N.E.2d 1215 (Indiana Supreme Court, 2008)
Bradley v. City of New Castle
764 N.E.2d 212 (Indiana Supreme Court, 2002)
Oxley v. Lenn
819 N.E.2d 851 (Indiana Court of Appeals, 2004)
Heeb v. Smith
613 N.E.2d 416 (Indiana Court of Appeals, 1993)
Rogier v. American Testing & Engineering Corp.
734 N.E.2d 606 (Indiana Court of Appeals, 2000)
Shelter Insurance Co. v. Woolems
759 N.E.2d 1151 (Indiana Court of Appeals, 2001)
Collins v. McKinney
871 N.E.2d 363 (Indiana Court of Appeals, 2007)
Whitaker v. Brunner
814 N.E.2d 288 (Indiana Court of Appeals, 2004)
Weigand Construction Co. v. Stephens Fabrication, Inc.
929 N.E.2d 220 (Indiana Court of Appeals, 2010)
Town of Plainfield v. Paden Engineering Co.
943 N.E.2d 904 (Indiana Court of Appeals, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Dave's Excavating, Inc. and Liberty Mutual Insurance Co. v. City of New Castle, Indiana, Counsel Stack Legal Research, https://law.counselstack.com/opinion/daves-excavating-inc-and-liberty-mutual-insurance--indctapp-2012.