Davenport & Co. v. Spieker

197 Cal. App. 3d 566, 242 Cal. Rptr. 911, 1988 Cal. App. LEXIS 5
CourtCalifornia Court of Appeal
DecidedJanuary 4, 1988
DocketA036948
StatusPublished
Cited by7 cases

This text of 197 Cal. App. 3d 566 (Davenport & Co. v. Spieker) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davenport & Co. v. Spieker, 197 Cal. App. 3d 566, 242 Cal. Rptr. 911, 1988 Cal. App. LEXIS 5 (Cal. Ct. App. 1988).

Opinion

Opinion

MERRILL, J.

The Spiekers, Mr. and Mrs. Warren Edward Spieker, Jr., 1 appeal from a judgment awarding damages in the sum of $14,350, plus interest, to Davenport & Co., Inc. (Davenport) for breach of a construction contract.

I

The parties entered into a written contract which provided that Davenport, a licensed general contractor, would construct a cabana and a garage on the Spiekers’ residential property. The contract provided that Davenport was to perform the work in accordance with drawings prepared by the Spiekers’ architect and changes to those drawings made by the Spiekers. Some changes to the drawings were excluded from the contract price and *568 would be charged to the Spiekers as “extras.” The parties agreed that the price for the work specified in the contract would be on a time and material basis, plus a 15 percent fee, not exceeding $130,000. In the event that the work described in the contract cost less than $130,000, the Spiekers would only be billed the actual cost plus 15 percent. Any changes or additions to the contract would be charged as extras. The contract also provided that changes would not be made without the Spiekers’ approval. There was no explicit provision in the contract requiring change orders to be in writing.

Davenport began construction on the Spiekers’ home in October 1984 and completed it in May 1985. During the construction, the Spiekers made substantial changes which increased the scope of the work to be performed and the compensation due Davenport. They ultimately paid Davenport a total of $178,623 for the work performed pursuant to the initial contract and for the extras. However, Davenport claimed that $37,331 was still unpaid for extra work performed on the Spiekers’ residence.

At the court trial in this action, evidence was presented as to the cost of the contract work and the cost of the extras. Copies of the weekly invoices mailed to the Spiekers, indicating the costs for all materials, suppliers, subcontractors, labor and miscellaneous services provided, were admitted into evidence. Also admitted into evidence was a compilation of the costs incurred as of April 4, 1985, and a projection of costs yet to be incurred. The Spiekers requested further delineation of the cost of extra work, so an additional document was prepared outlining all the changes performed and their respective costs. Such document was also received in evidence. Mike Mclnnis, the job supervisor, and Mac Mclnnis, Davenport’s president, prepared the document from the following: Mike Mclnnis’s daily record of each change requested by the Spiekers, material invoices, subcontractor invoices, and employee timecards. The labor cost for each item of extra work was determined by a review of the timecards and by multiplication of the number of man-hours by the average labor rate. In those instances where the carpenter or laborer failed to designate the amount of time spent on the extra work, Mac Mclnnis estimated the labor cost. He testified that he had 10 years of construction experience and that he provides estimates for all the jobs on which Davenport submits bids.

In July 1985, upon the Spiekers’ request, a second cost breakdown for the extra work was prepared. Again, the Mclnnises relied on material invoices, subcontractor invoices and timecards. However, as the July cost breakdown was compiled after the job was complete, it set forth a more accurate total price for the extra work performed.

The court determined that the actual cost of the contract work, exclusive of extras, was less than the $130,000 guaranteed maximum contract price *569 agreed upon by the parties. Further, the court found certain extra charges were not justified and awarded Davenport the sum of $14,350 plus interest.

II

The Spiekers argue that Davenport’s failure to comply with a provision of the Business and Professions Code, 2 which requires all home improvement contracts and changes thereto to be in writing, precludes its recovery for unwritten changes. We disagree.

Pursuant to section 7159, home improvement contracts for work in excess of $500 and any changes in such contracts, between a licensed contractor and an owner or tenant, must be evidenced by a writing and signed by all the parties. A violation of this provision by the licensee is a misdemean- or.

The question of the effect of noncompliance with section 7159 was considered by our Supreme Court in Asdourian v. Araj (1985) 38 Cal.3d 276 [211 Cal.Rptr. 703, 696 P.2d 95]. In that case, a contractor sued the owner for the balance due on remodeling work performed on the owner’s property. The owner argued that the contractor was barred by section 7159 from recovering for the completed work as it was done pursuant to oral agreements. The court rejected this argument, holding that an oral contract in violation of section 7159 is merely voidable and not void.

The court stated that the public policy interest underlying section 7159 is to encourage written contracts for home improvements in order to protect unsophisticated consumers. (Asdourian v. Araj, supra, 38 Cal.3d at pp. 290, 292.) Further, although there is a general rule that contracts made in violation of a regulatory statute are void, courts will not apply such rule in certain situations. For example, the rule will not be applied where the statutory penalties exclude by implication the additional penalty of holding the contract void. In addition, in compelling cases, where the defendant’s unjust enrichment will result at the plaintiff’s expense, courts will enforce illegal contracts. (Id., at pp. 291-292.)

The Asdourian court reasoned that although the present statute only makes violation punishable as a misdemeanor, the apparent legislative intent was that such penalty was not exclusive of others. The original version of section 7159 included the provision that “ ‘[contracts which fail to comply with the provisions of this section shall not be deemed to be invalid *570 solely because of noncompliance.’ ” (Id., at p. 292, italics added, quoting Stats. 1969, ch. 1583, § 15, pp. 3220-3221.) As this express provision was deleted by subsequent amendment, it must be presumed that the Legislature intended to change the law. The court concluded that the Legislature did not intend the express penalty provisions of section 7159 to be exclusive. (Id., at p. 292.)

The court stated: “Although the penalties provided by section 7159 are no longer exclusive, there is no indication that the Legislature intended that all contracts made in violation of section 7159 are void. Absent an express statutory prohibition, other exceptions to the general rule that illegal contracts are unenforceable may be applied.” (Asdourian v. Araj, supra, 38 Cal.3d at p. 292.)

The Asdourian

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Star Restoration v. Salame CA2/2
California Court of Appeal, 2022
Redlich v. Reliance Management Group CA1/1
California Court of Appeal, 2021
Hinerfeld-Ward, Inc. v. Lipian
188 Cal. App. 4th 86 (California Court of Appeal, 2010)
Dunkin v. Boskey
98 Cal. Rptr. 2d 44 (California Court of Appeal, 2000)
Arya Group, Inc. v. Cher
91 Cal. Rptr. 2d 815 (California Court of Appeal, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
197 Cal. App. 3d 566, 242 Cal. Rptr. 911, 1988 Cal. App. LEXIS 5, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davenport-co-v-spieker-calctapp-1988.