Dave Leonard Construction Company v. Duo Distributors, Inc.
This text of Dave Leonard Construction Company v. Duo Distributors, Inc. (Dave Leonard Construction Company v. Duo Distributors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
APPELLANT
APPELLEE
Dave Leonard Construction Company appeals from a trial-court judgment awarding DUO Distributors, Inc., money damages for breach of contract, and ordering that Leonard take nothing by its counterclaim against DUO for breach of the same contract. We will reverse DUO's judgment against Leonard and render judgment that DUO take nothing. We will affirm that part of the judgment ordering that Leonard take nothing by its counterclaim against DUO.
Leonard undertook, as general contractor, to erect a heating and cooling plant for Angelo State University. The work required the installation of skylights that Leonard contracted to buy from DUO. DUO contracted, in turn, to purchase the skylights from the manufacturer, Dawn Products.
In June 1987, Leonard executed DUO's purchase-order form. In the space provided for a delivery date, the words "See schedule" were inserted. The "job site" was specified as the place of delivery. Subsequently, in November 1987, Leonard furnished DUO a notice approving the specifications to which the skylights were to be specially fabricated. The notice included the following statement:
This material will be needed on the job no later than (as scheduled). Failure to deliver material to the job by the time stipulated will be grounds for cancellation.
Dawn fabricated the skylights to Leonard's specifications and they were delivered to the job site December 21, 1987. Leonard did not then need them because construction had progressed only as far as the basement of the plant. Leonard refused to accept the skylights for want of storage space. The shipper stored them for a period, then sold them to recover its costs.
DUO sued in the present cause to recover the contract price when Leonard refused to pay for the skylights. Leonard counterclaimed for damages and attorney's fees based on DUO's alleged failure to deliver the skylights according to the "job schedule," that is to say, when the skylights were required for incorporation in the work.
After a bench trial, the court below awarded DUO a judgment for breach of contract, in the amount of $4,094.00 and interest, while adjudging that Leonard take nothing by its counterclaim. Leonard appeals.
The trial court filed findings of fact and conclusions of law. These show that DUO's judgment rests on a premise that the parties' contract did not specify a delivery date because Leonard never supplied DUO a "job schedule." Thus, the law imputed to the contract an agreement that the skylights would be delivered at a "reasonable time." Tex. Bus. & Com. Code Ann. § 2.309(a) (1968). To recover on that premise, the burden lay upon DUO to prove delivery at such a time. City of Fort Worth v. Rosedale Park Apartments, 276 S.W.2d 395, 397 (Tex. Civ. App. 1955, writ ref'd).
"What is a reasonable time for taking any action depends on the nature, purpose and circumstances of such action," Tex. Bus. & Com. Code Ann. § 1.204(b) (1968), and usages of trade may be material and important in fixing a reasonable time in a particular case. Id., comment 2. In the present case, the findings of fact and conclusions of law set out a theory that a "reasonable time" for delivery was "as soon as possible" under the following usages of trade:
1. The reference to a "job schedule" in the purchase order and in the specifications-approval notice meant that delivery was required "as soon as possible," when no such schedule was supplied by Leonard.
2. Once approval of specifications for skylights that are to be manufactured to irregular dimensions is received, the manufacturer is notified to proceed with production, and upon completion of manufacture, to deliver the skylights to the designated site.
Among other points of error, Leonard contends on appeal that numbers 1 and 2 above are not supported by evidence that is legally or factually sufficient. We will sustain the contention that the evidence is not legally sufficient, considering the evidence in a light most favorable to DUO, and only the supporting evidence and inferences therefrom, while ignoring all contrary evidence and inferences. See W. Powers and J. Ratliff, Another Look at "No Evidence" and "Insufficient Evidence," 69 Texas L. Rev. 515, 522 (1991); Calvert, "No Evidence" and "Insufficient Evidence" Points of Error, 38 Texas L. Rev. 361, 364-65 (1960). We may not hold the evidence "legally insufficient" unless we are persuaded that a "vital fact may not reasonably be inferred from the meager facts proved in the particular case." Calvert, at 365.
We find in the statement of facts no evidence to support an inference that the reference to a "job schedule" implied that delivery must be "as soon as possible" because that is a "usage of trade" within the meaning of Tex. Bus. & Com. Code Ann. § 1.205(b) (1968). Nor can we find any evidence to support an inference that a usage of trade requires delivery of specially manufactured items as soon as approval of specifications is received.1 DUO insists the necessary inferences may be drawn from pages 83-86 of the statement of facts, setting out part of the testimony on cross-examination of Leonard's witness Roberson. We find, however, that such testimony tended to establish only the following propositions:
1. It is important for Roberson's company (a supplier of acoustical tile for ceilings) to know when it is "supposed to have [the] stuff there at a job site" in order to avoid delaying the construction project.
2. It is important for suppliers like DUO and Roberson's company to get "information" from the contractor in order that the suppliers can do their jobs on time.
3. If a contractor has stated that he is going to construct the work by a schedule, and that he is going to send the supplier a schedule, Roberson would expect to receive one; however, it is not customary for suppliers to be furnished a schedule.
4. In case of "a special order product" that would not "fit any other project in the whole world," it would be "reasonable" and "important" for the supplier to be told if the product would not be needed for about 20 months when the entire project covered two years.
5. It is "not customary" for the contractor "to send a schedule to the suppliers," and while Roberson would "suppose" it is "normal" for a contractor to print "see schedule" on printed forms like those used in the present case, and Roberson had seen that done "a few times," it means "'see schedule' or 'find out . . . when.'"
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Dave Leonard Construction Company v. Duo Distributors, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/dave-leonard-construction-company-v-duo-distributo-texapp-1991.