Daugherty v. Ohio Dept. of Transp.

2013 Ohio 5918
CourtOhio Court of Claims
DecidedJanuary 30, 2013
Docket2012-04031-AD
StatusPublished

This text of 2013 Ohio 5918 (Daugherty v. Ohio Dept. of Transp.) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Daugherty v. Ohio Dept. of Transp., 2013 Ohio 5918 (Ohio Super. Ct. 2013).

Opinion

[Cite as Daugherty v. Ohio Dept. of Transp., 2013-Ohio-5918.]

Court of Claims of Ohio The Ohio Judicial Center 65 South Front Street, Third Floor Columbus, OH 43215 614.387.9800 or 1.800.824.8263 www.cco.state.oh.us

ROBERT R. DAUGHERTY

Plaintiff

v.

OHIO DEPARTMENT OF TRANSPORTATION

Defendant

Case No. 2012-04031-AD

Deputy Clerk Daniel R. Borchert

MEMORANDUM DECISION

FINDINGS OF FACT {¶1} 1) On May 17, 2012, plaintiff, Robert R. Daugherty, filed a complaint against defendant, Ohio Department of Transportation (“ODOT”). Plaintiff asserts a construction project authorized by defendant and performed by Shelly Company (“Shelly”), caused damage to his property located at “3947 SR 44.” Plaintiff contended when defendant’s agent Shelly replaced a 12" clay pipe with a 15" concrete pipe and catch basin, “the contractor never connected my line in.” Due to his disconnect, which “has been a problem for years. Pumps burn up, tanks fill up and it has been a health hazard.” Plaintiff related it was not until he contacted his contractor, Clem Excavating, that it was discovered that his pipe was not installed onto ODOT’s system. Plaintiff asserts this discovery was made on April 28, 2012 at approximately 9:00 a.m. {¶2} 2) Plaintiff seeks damages in the amount of $2,390.00, of which $290.00 represents costs incurred with Fred Septic to pump the tanks out on April 20, Case No. 2012-04031-AD -2- MEMORANDUM DECISION

2012 and $2,100.00 represents costs incurred with Clem Excavating to install a catch basin, drain line and new lift pump due to defendant’s negligence with respect to the construction project in question. {¶3} 3) Defendant’s investigation revealed “that the work in question was part of Construction Project #253(2007)-POR-SR44-0.00, which involved the replacement of four (4) culverts, planning and resurfacing the roadway, upgrading of guardrail end terminals, full and partial depth repairs of the roadway and pavement striping on eight (8) miles of SR 44 beginning at the Stark County Line. Addendum 1 added 495 lineal feet of 15" Conduit Type C, 706.02 and four (4) No. 2-2 B Catch Basins on plan pages 21A/41, 21B/41, 21C/41, 21D/41. Change Order 1 added another 253 lineal feet to the north to satisfy the intent of Addendum 1. The total length of the pipe run was 748 lineal feet. The reason for the drainage upgrade was to replace outdated existing twelve (12) and six (6) inch clay/steel drainage pipes on the west side of SR 44 between Karry Drive and Tallmadge Road in Rootstown Township which were a maintenance problem due to plugging. The pipe work was performed between the dates of September 10, 2007 and September 25, 2007. The pipe run crossed a total of nine driveways including the claimant’s. Four (4) catch basins were installed with the distance between catch basins as shown on the referenced plan pages being 117', 77', 177' and 253' respectively. (Exhibit A) District 4 Planning and Engineering provided the design criteria, i.e. spacing between the catch basins. The Ohio Department of Transportation contracted with Shelly Company to complete this construction project.” {¶4} Accordingly, defendant asserted that Shelly is the proper party to sue in this situation. Case No. 2012-04031-AD -3- MEMORANDUM DECISION

{¶5} 4) Furthermore, “[d]epartment of Transportation’s investigation reveals that neither ODOT nor Shelly Company had notice of the pipe at the 3947 residence, and therefore it was not attached. If encountered, the existing private drains were connected either to a catch basin (if in close proximity) or directly into the new conduit. Project personnel provided comments that to the best of their knowledge while installing the 748 lineal feet of conduit, septic outfalls were encountered at some of the other properties and were connected to the new system. However, no private drains were encountered/discovered at the 3947 residence including a pipe, any smell or moisture. The project inspector also made the comment the residence seemed to be vacant at the time the work was being performed.” {¶6} 5) Finally, defendant contended that plaintiff’s claim is barred pursuant to R.C. 2743.16(A), the two year statute of limitations. Defendant related that the construction project 253 (2007) was performed between September 10, 2007 and September 25, 2007. Therefore, plaintiff had two years from the later date to file his complaint, however, plaintiff did not file the complaint until May 17, 2012, two years and nine months after the statute of limitations had run. {¶7} 6) Plaintiff filed a response to defendant’s investigation report. Plaintiff contended that his pipe was originally connected to the 12" street pipe. He can not believe that either defendant or Shelly could not locate his pipe since it had been cut from the former 12" street pipe prior to the installation of the 15" street pipe. {¶8} 7) With respect to the issue of the statute of limitations, plaintiff stated in pertinent part: {¶9} “They also stated that the house was vacant, which it was not and I cannot Case No. 2012-04031-AD -4- MEMORANDUM DECISION

understand how that would be relevant. I was renovating and there was activity. The sanitation system was being used, but not to capacity. The renovation was completed and fully occupied in 2009. That is when the problems started and that is within the statute of limitations referred to in their response. {¶10} “In 2009, the drainage problems started showing up when the system was at full capacity. . . I have attached invoices of the work done to correct the problems before realizing the disconnected pipe. I am not seeking reimbursement for these, but showing when the problems started. The one thing that CF Clem and I never questioned was if the pipe was attached at the street.” {¶11} 8) Plaintiff submitted photographs depicting the location where his pipe had not been connected to the 15" street pipe. CONCLUSIONS OF LAW {¶12} 1) R.C. 2743.16(A) in pertinent part states: {¶13} “. . . civil actions against the state permitted by sections 2743.01 to 2743.20 of the Revised Code shall be commenced no later than two years after the date of accrual of the cause of action or within any shorter period that is applicable to similar suits between private parties.” {¶14} 2) Defendant asserted that since the plaintiff’s claim was barred pursuant to R.C. 2743.16(A), he has failed to state a cause of action pursuant to Civ.R. 12(B)(6) and his claim should be dismissed. {¶15} 3) The Ohio Supreme Court has noted the necessity of construing, under Civ.R. 12(B)(6), all inferences in the plaintiff’s favor. See Wampler v. Higgins, 93 Ohio St. 3d 111, 2001-Ohio-1293, 75 N.E. 2d 962, citing Vail v. Plain Dealer Publishing Case No. 2012-04031-AD -5- MEMORANDUM DECISION

Co., 72 Ohio St. 3d 279, 1995-Ohio-187, 649 N.E. 2d 182. When reviewing a motion to dismiss pursuant to Civ.R. 12(B)(6), the court is required to view all of the allegations of the complaint as true. Butler v. Cuyahoga Cty. Dept. of Human Serv., 92 Ohio St. 3d 354, 2001-Ohio-204, 750 N.E. 2d 554. See, also, Taylor v. London, 88 Ohio St. 3d 137, 2000-Ohio-278, 723 N.E. 2d 1089, which states that it is clear, as a matter of law, that the allegations of appellant’s complaint must be accepted as true. See, also, Mitchell v. Lawson Milk Co., 40 Ohio St. 3d 190, 532 N.E. 2d 753 (1988). Further, in O’Brien v. Univ. Community Tenants Union, Inc., 42 Ohio St. 2d 242, 327 N.E. 2d 242 (1975), the Ohio Supreme Court found that it must appear beyond doubt from the complaint that plaintiff can prove no set of facts entitling him to recovery. The plaintiff must be afforded all reasonable inferences possibly derived from the allegations in the complaint. Desenco, Inc. v. Akron, 84 Ohio St. 3d 535, 706 N.E. 2d 323 (1999).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Football League Properties, Inc. v. Consumer Enterprises, Inc.
327 N.E.2d 242 (Appellate Court of Illinois, 1975)
Knickel v. Department of Transportation
361 N.E.2d 486 (Ohio Court of Appeals, 1976)
Bemmes v. Public Employees Retirement System
658 N.E.2d 31 (Ohio Court of Appeals, 1995)
Cyrus v. Henes
623 N.E.2d 1256 (Ohio Court of Appeals, 1993)
Kniskern v. Township of Somerford
678 N.E.2d 273 (Ohio Court of Appeals, 1996)
Rhodus v. Ohio Department of Transportation
588 N.E.2d 864 (Ohio Court of Appeals, 1990)
Litchfield v. Morris
495 N.E.2d 462 (Ohio Court of Appeals, 1985)
Stevens v. Industrial Commission
61 N.E.2d 198 (Ohio Supreme Court, 1945)
Neff Lumber Co. v. First National Bank
171 N.E. 327 (Ohio Supreme Court, 1930)
Bello v. Cleveland
138 N.E. 526 (Ohio Supreme Court, 1922)
State v. Dehass
227 N.E.2d 212 (Ohio Supreme Court, 1967)
O'Brien v. University Community Tenants Union, Inc.
327 N.E.2d 753 (Ohio Supreme Court, 1975)
Cascone v. Herb Kay Co.
451 N.E.2d 815 (Ohio Supreme Court, 1983)
Shinaver v. Szymanski
471 N.E.2d 477 (Ohio Supreme Court, 1984)
Menifee v. Ohio Welding Products, Inc.
472 N.E.2d 707 (Ohio Supreme Court, 1984)
Mitchell v. Lawson Milk Co.
532 N.E.2d 753 (Ohio Supreme Court, 1988)
Stinson v. England
633 N.E.2d 532 (Ohio Supreme Court, 1994)
Cyrus v. Henes
640 N.E.2d 810 (Ohio Supreme Court, 1994)
Vail v. Plain Dealer Publishing Co.
649 N.E.2d 182 (Ohio Supreme Court, 1995)
Desenco, Inc. v. City of Akron
706 N.E.2d 323 (Ohio Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
2013 Ohio 5918, Counsel Stack Legal Research, https://law.counselstack.com/opinion/daugherty-v-ohio-dept-of-transp-ohioctcl-2013.