Daugherty Cattle Co. v. General Construction Co.

839 P.2d 562, 254 Mont. 479, 49 State Rptr. 820, 1992 Mont. LEXIS 263
CourtMontana Supreme Court
DecidedSeptember 22, 1992
Docket92-029
StatusPublished
Cited by6 cases

This text of 839 P.2d 562 (Daugherty Cattle Co. v. General Construction Co.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Daugherty Cattle Co. v. General Construction Co., 839 P.2d 562, 254 Mont. 479, 49 State Rptr. 820, 1992 Mont. LEXIS 263 (Mo. 1992).

Opinion

JUSTICE WEBER

delivered the Opinion of the Court.

Defendant, General Construction Company, appeals from the summary judgment ruling of the District Court of the Thirteenth Judicial District, Yellowstone County, in favor of plaintiffs. We affirm.

The issues for our review are:

1. Whether the District Court erred by refusing to consider reasonable rental value of the property subject to a land contract for purposes of computing damages upon foreclosure by the seller.

2. Whether Montana’s anti-forfeiture statute, § 28-1-104, MCA, applies to prohibit the seller from declaring a forfeiture when the purchaser tenders a portion of the property back to the seller as “full compensation” for the balance owing on the contract.

On February 13, 1981, Meyer Construction Company, a predecessor company of defendant General Construction Company (General), *481 and the plaintiffs Daugherty Cattle Co., a partnership consisting of Emerald Daugherty, William Daugherty and John Daugherty, Jr.; Emerald Daugherty; William Earl Daugherty; and John Emerald Daugherty, Jr. (Daugherty), as sellers, entered into a written contract for deed for the sale and purchase of real property located on the outskirts of Billings in Yellowstone Comity, Montana. The purchase price of the property was $1,195,000.00 plus interest at the rate of nine percent per annum. General and its predecessor made annual payments as scheduled until 1987, when the contract was amended. On July 8,1987, General and Daugherty agreed to revise the payment schedule and reamortize the unpaid principal of $422,500.00. The amendment lowered the payments and split them, with interest payments (continuing at nine percent) and principal payments due on different dates during the year. The contract also recited the name change from Meyer Construction Company to General Construction Company.

General continued to make payments as scheduled until 1989, when General failed to pay the scheduled payment due on July 15, 1989. On October 10,1989, Daugherty sent by certified mail a written notice of default giving General thirty days within which to make payment, as required by the contract. In early November, 1989, Daugherty extended the default period for sixty days beyond November 9, 1989.

On January 8, 1990, General made an “offer of performance” in writing, which General considered to be full performance and compensation under the contract. In its offer, General offered to convey back to Daugherty an 85-acre portion of the property (approximately 47% of the land covered by the contract) together with payments already made totalling $1,273,290.00, in return for termination of the contract and retention of the remaining 53% of the land. This would have left Daugherty with the portion of the land it had leased back from General as farmland since 1981 and would have left General with the portion on which it mined gravel for construction purposes.

On January 31, 1990, also pursuant to the contract, Daugherty sent by certified mail a “Notice of Continued Default and Acceleration of Remaining Purchase Price,” notifying General that it was accelerating the entire contract balance and giving General thirty days to pay the accelerated balance in full. Again General failed to make any payment on the contract. Daugherty, electing to terminate the contract, sent to General a “Notice of Termination of Contract for Deed” dated July 18, 1990.

*482 General refused to execute special warranty deeds to reconvey the property to Daugherty and refused to deliver possession to Daugherty to effect the termination of the contract. Daugherty filed this action to quiet title and to obtain possession of the property.

The District Court granted Daugherty’s motion for summary judgment on the quiet title and ejectment claims, rejected General’s claim that termination and forfeiture were not enforceable remedies under the contract and allowed Daugherty to retain all monies previously paid by General and its predecessor. The District Court refused to apply Montana’s anti-forfeiture statute, § 28-1-104, MCA, because General’s tender of a portion of the property did not constitute “full compensation” as required by the statute. From this judgment, General appeals.

I.

Did the District Court err by refusing to consider reasonable rental value of the property subject to a land contract for purposes of computing damages upon foreclosure by the seller?

The appellant, General, contends that there are genuine issues of fact and that evidence relating to these factual issues should have been introduced into evidence at a trial. Specifically, General claims that a clause included in the parties’ contract requires the court to determine the relationship between payments retained and actual damages suffered by Daugherty and to determine whether the retention of contract payments constitutes a penalty rather than damages. The pertinent clause is underlined in the following excerpt from Paragraph 5 of the contract for deed:

(1) If Buyer fails to cure such default or breach within the aforesaid 30 day period, the Seller may then declare the outstanding balance of the purchase price together with all other unpaid obligations of the Buyer undertaken in this contract due and payable within an additional 30 days. If the outstanding balance of the purchase price together with all other unpaid obligations of the Buyer are not paid within the second 30 day period, the Seller may either:

(a) declare this contract terminated. In the event of such termination, Buyer agrees on demand to surrender possession of the property, and any improvements thereon immediately and peaceably, and to execute and deliver such instruments as Seller may require to evidence of record the termination of this contract and Buyer’s interest in the contract and real property, and Seller *483 may retain all payments made hereunder as reasonable rental for the use of the property and as liquidated damages, ... (Emphasis supplied.)

General claims there is no evidence that the damages Daugherty recovered have any relationship to the actual damages suffered by Daugherty. General has made payments of principal and interest totalling $1,242,447.50 on the original contract amount of $1,195,000.00. The amounts applied to principal total $857,000.00, leaving a principal balance of $338,000.00. General farther claims that liquidated damages must bear a reasonable relationship to the actual damages or such damages will constitute an invalid penalty. Daugherty contends that the language quoted above from Paragraph 5 of the contract is neither ambiguous nor uncertain in any sense and maintains that to accept General’s argument would essentially convert the contract from a purchase agreement to a lease, as noted by the District Court.

We agree with the District Court’s assessment relating to the result which would ensue if we were to depart from longstanding interpretation of land sale contract provisions. In effect, the result would be to rescind the contract at the whim of the defaulting purchaser whose wrongdoing caused the vendor to terminate the contract.

Long ago, in Cook-Reynolds Co. v. Chipman (1913), 47 Mont. 289, 133 P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arrowhead Sch. Dist. 75, Park Co. v. Klyap
2003 MT 294 (Montana Supreme Court, 2003)
Glacier Park Co. v. Mountain, Inc.
949 P.2d 229 (Montana Supreme Court, 1997)
Club Buffet Bar, Inc. v. Lilienthal
885 P.2d 526 (Montana Supreme Court, 1994)
Federal Deposit Insurance Corporation v. Shoop
2 F.3d 948 (Ninth Circuit, 1993)
Federal Deposit Insurance v. Shoop
2 F.3d 948 (Ninth Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
839 P.2d 562, 254 Mont. 479, 49 State Rptr. 820, 1992 Mont. LEXIS 263, Counsel Stack Legal Research, https://law.counselstack.com/opinion/daugherty-cattle-co-v-general-construction-co-mont-1992.