Dauer v. Safeco Insurance Co. of America
This text of 394 So. 2d 128 (Dauer v. Safeco Insurance Co. of America) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
This is a timely appeal by Maxwell Dauer and Reva B. Dauer, his wife, hereinafter called the Dauers, and Lauderdale Lakes Medical Center, Inc., hereinafter called the hospital, from a final judgment and order denying rehearing. We affirm.
Peninsular Supply Company brought an action against the Dauers, the hospital, Standard Systems Corporation and the latter’s surety, Safeco Insurance Company of America, to foreclose a mechanic’s lien. Final judgment of foreclosure recited that Peninsular was due $23,377, plus interest, from the hospital, Standard and Safeco. Also included in the final judgment was an [129]*129award to Safeco of $9,856.01, plus interest, on its crossclaim against the hospital. A subsequent cost judgment of $8,098.14 was entered in favor of Peninsular against the Dauers and the hospital for attorney’s fees and costs.
The facts reflect the hospital to be the lessee of real property in Broward County, Florida, owned by the Dauers. On March 25,1974 the hospital entered into a contract with Standard for plumbing work in the expansion of the former’s medical center located on the subject property. Standard ran into financial difficulty in late September 1974. On November 1, 1974 Standard informed the hospital that all payments due it should be paid to its surety, Safeco. Without any additional written agreement with the hospital other than the March 25th contract and surety bond, prior to November 6, 1974 Safeco paid out over $42,000 to parties who had supplied labor or material to Standard on this job. Then, on the last mentioned date, Safeco executed and tendered to the hospital a written agreement acknowledging Safeco’s obligation to complete the contract, and providing, inter alia:
(1) Lauderdale Lakes agrees that the unpaid balances of the contract prices at the date hereof, including retainages, is in the amount of $29,542 and that it will pay that amount to Safeco for the performance of the contract and the completion of the PROJECT in accordance with the terms of the contract.
The hospital eventually executed the agreement but did not pay any of the retainage to Safeco, allegedly because the contract had not been completed.
The hospital’s basic contention was that since the specifications required domestic water and fire pumps on the ground floor of the mechanical room located in a one-story building connected to the hospital, Standard-and Safeco-were obligated to furnish and install them. The pumps appear to have cost almost $17,000, plus installation. The hospital also contended that it completed other required work and expended funds for material and labor in doing so.
Mr. C. W. Ackerman, whose firm Safeco had hired to complete Standard’s contract, disputed the hospital’s contentions. He testified that the pumps were not part of Standard’s contract; that the entire cost of his firm’s completion of the job exclusive of the pumps, did not exceed $4,500; and that his firm completed it.
In its final judgment the trial court found that the express language in Standard’s contract with the hospital eliminated any obligation of Standard below the fourth floor slab. Consequently, the court determined that any work on the ground floor pumps was not part of the contract. As shall be discussed later, this finding was essential to Peninsular’s recovery in the trial court.
Peninsular was one of the materialmen Standard had been using. Although, as noted above, Safeco paid out in excess of $42,000 to Standard’s creditors prior to November 6, 1974, it did not pay Peninsular most of its invoices because it learned that Peninsular had neglected to file a Notice to Owner. Peninsular attempted to correct its error by serving a notice to owner on December 20, 1974. It thereafter filed a Claim of Lien on January 8, 1975. Apparently, Peninsular prevailed in the trial court because it sent its belated Notice to Owner on December 20, 1974 when the Hospital was still holding the retainage. Crane Co. v. Fine, 221 So.2d 145 (Fla.1969). Had the trial court found the pumps were part of the contract, the necessary corollary of that would have been to reduce the retainage that had been held by the hospital by whatever the pumps had cost to purchase and install.
On appeal the Dauers and the hospital do not dispute the trial court’s awards to Peninsular, but they raise two other points:
I. The attorney’s fees and cost judgment of $8,098.14 in favor of Peninsular and against appellants should have been set off against Safeco’s judgment on the latter’s crossclaim against the hospital.
II. The attorney’s fees and costs incurred by appellants in the defense of the [130]*130mechanic's lien foreclosure brought by Peninsular should have been awarded to them and against Safeco.
I.
In support of their first point, appellants rely upon the language of the bond1 and Standard’s March 25,1974 sub-contract with the hospital,2 Section 713.29, Florida Statutes (1973),3 and the theory of indemnity as a matter of law.4 Notwithstanding the forcefulness of appellants’ arguments, there remains in our minds one overriding and determinative fact in this case; namely, the failure of the hospital to pay the retainage to Safeco prior to Peninsular’s notice of December 20, 1974. The trial court ultimately found this retainage to be $33,233.01, and, as stated above, awarded Peninsular $23,377.00 of it and the balance of $9,856.01 to Safeco because of the sums expended by the surety. Had the retainage been paid by the hospital to Safeco prior to December 20th, it follows that neither award would have been necessary or appropriate. Peninsular could not have prevailed because of its failure to send a timely notice to owner as required by Section 713.06, Florida Statutes (1973),5 and Safeco would have been relieved of any necessity to cross-claim for the funds rightly due it.
As between Safeco and the hospital, the latter would have us look only to the original sub-contract and bond and ignore the agreement of November 6, 1974. This we cannot do. There were three, not two, instruments which governed the relationship of the parties. While it has been said that one cannot recover on a single contract unless one performs his material obligations [131]*131thereunder,6 when there are interdependent contracts or instruments, we hold that one cannot enforce obligations under one in the absence of performing interdependent obligations under the others. Accordingly, the hospital was not entitled to a set-off of the judgment for cost and attorney’s fees in favor of Peninsular.
II.
As to the second point, appellants again rely on the sub-contract7 as well as the theory of indemnity,8 and also contend that Sections 627.4289 and 627.756,10 Florida Statutes (1973), apply. The same principle governs this point as did the first. Had the hospital performed, paid over the re-tainage to Safeco and tendered to it the defense of the foreclosure, the hospital would not have incurred attorney’s fees. Similarly, the Dauers would have been the beneficiaries of such performance because their obligation for attorney’s fees arose out of their failure to prevail in the foreclosure action.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
394 So. 2d 128, 1980 Fla. App. LEXIS 17622, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dauer-v-safeco-insurance-co-of-america-fladistctapp-1980.