Darbun Enterprises, Inc. v. San Fernando Community Hospital

239 Cal. App. 4th 399, 191 Cal. Rptr. 3d 340, 2015 Cal. App. LEXIS 689
CourtCalifornia Court of Appeal
DecidedAugust 12, 2015
DocketB233078
StatusPublished
Cited by22 cases

This text of 239 Cal. App. 4th 399 (Darbun Enterprises, Inc. v. San Fernando Community Hospital) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Darbun Enterprises, Inc. v. San Fernando Community Hospital, 239 Cal. App. 4th 399, 191 Cal. Rptr. 3d 340, 2015 Cal. App. LEXIS 689 (Cal. Ct. App. 2015).

Opinion

Opinion

EPSTEIN, P. J.

Plaintiff Darbun Enterprises, Inc., doing business as All Saints Healthcare (Darbun), sued defendant San Fernando Community *402 Hospital, doing business as Mission Community Hospital (Mission), for breach of a lease agreement, seeking damages and specific performance.

The trial in this case proceeded in two phases. The first, the equity phase, was held to determine whether the equitable remedy of specific performance was available should Darbun prevail. The court reserved the issues of breach and resulting contract damages for the jury. At the end of the equity phase, however, the trial court stated it could not decide on the specific performance issue until it heard additional evidence, to be presented at the jury trial. The jury, which already had been seated and sworn, was called and the second, legal, phase of trial commenced. After Darbun presented its case, Mission moved for nonsuit. The trial court granted that motion as to specific performance only. It found that, after weighing the evidence and making credibility determinations as the equity fact finder, the lease could not be specifically performed, and that Darbun had failed to perform its obligations under the lease. Nevertheless, the trial continued, and after Mission rested, it moved for a directed verdict. The court denied that motion. The jury found in favor of Darbun and awarded damages; the court entered judgment for Darbun. Mission then filed a motion for judgment notwithstanding the verdict (JNOV). That motion was granted. The court based its decision on findings it had made on the motion for nonsuit. The court reasoned that since it already had found the lease to be “unenforceable” and Darbun had failed to perform its obligations, there was no substantial evidence to support the jury verdict in favor of Darbun.

In the published portion of this opinion, we hold that, in cases involving mixed issues of equity and law, a trial court may not act as a fact finder on issues it specifically reserves for jury determination. Here, in granting JNOV, the court improperly transformed its equitable finding of unenforceability as to specific performance into a finding of unenforceability as to the legal issue of damages. 1 In the unpublished portion of this opinion, we conclude there was substantial evidence to support the jury verdict. We therefore reverse the judgment and remand the case to the trial court for further proceedings consistent with this opinion.

FACTUAL AND PROCEDURAL SUMMARY

A. Lease Agreement

On October 18, 2006, Darbun and Mission entered into a 30-year lease for one of Mission’s hospital buildings, called the North Tower. Darbun planned *403 to redevelop the North Tower into a subacute or long-term acute care unit, though the lease permitted Darbun to operate it for “any other use allowed by law other than a general hospital.” Both parties recognized that Darbun would be required to “invest hundreds of thousands of dollars in due-diligence investigation, planning, permitting and development costs over a substantial and undetermined period of time, before it could improve and utilize the North Tower.” Accordingly, the lease provided that Darbun would not be responsible for rent payments until its first patient had been admitted, after completion of construction and licensure of the facility. Although the lease noted that time was of the essence, it did not specify time limits within which Darbun was required to complete renovations. This was due to the fact that Darbun’s progress was heavily dependent upon approvals from government entities. The lease contained no provision pertaining to Darbun’s use of Mission’s license to operate the property. Further, the lease provided that Darbun’s failure to perform any of its contractual duties, aside from failure to pay rent, would not constitute a breach unless (1) Mission provided a 30-day notice to cure, and (2) Darbun failed to cure within the 30 days or failed to proceed to “prosecute[] the cure to completion with dispatch.’.’

B. Darbun’s Performance and Mission’s Termination of Lease

Darbun initially planned to operate the North Tower as a long-term acute care hospital (LTACH). In March 2007, Darbun discovered that developing the tower as an LTACH would require significant seismic improvements, rendering the project “economically unfeasible.” It began to explore the idea of operating a skilled nursing facility. Darbun believed it was possible to operate a skilled nursing facility under Mission’s license, essentially being “grandfathered” in to avoid having to make costly seismic upgrades.

Both parties understood that construction could not begin until Darbun obtained a parking variance from the city. Darbun sought the variance upon the signing of the lease and did not commission construction plans until the variance was approved. The variance was approved 13 months later in November 2007; the parties stipulated this was a reasonable amount of time. In early December of 2007, Darbun was notified of a public law placing a moratorium on new LTACHs. As a result, Darbun decided to pursue development of a skilled nursing facility and no longer considered running the North Tower as an LTACH. Darbun drafted preliminary conceptual plans and submitted them to the Office of Statewide Health Planning and Development (OSHPD) in December 2007. It also sent a copy of the plans to Mission. The plans omitted structural, mechanical, and electrical specifications because Darbun sought to ensure that its proposal “would be acceptable to OSHPD” before investing additional time and resources into the project.

*404 In that same month, Mission’s attorney told representatives of Darbun that Mission wanted to terminate the lease. No written notice was provided at this time, and Darbun continued to perform under the lease. Mission was aware of Darbun’s ongoing efforts because Mission’s representatives visited the North Tower at least four times between November 2007 and August 2008, and during those visits, Mission did not indicate dissatisfaction with Darbun’s performance. In February 2008, OSHPD reviewed and returned the preliminary plans for “further work,” which Heidi Lennartz, chief executive officer of Mission, testified was the “typical course” of procedure. In September 2008, John Paul Sensibile, facility administrator of Darbun, met with Ms. Lennartz, and expressed Darbun’s intent to begin operating its skilled nursing facility under Mission’s license. Although Ms. Lennartz “felt that the hospital was beginning to be kind of cornered into cooperating beyond the terms of the lease,” she did not express her concern to Mr. Sensibile. A few weeks later, Ms. Lennartz learned that the plans Darbun had submitted to OSHPD were designed in such a way that they would “require that [Mission] license the skilled nursing facility under its own license” and allow Darbun to operate under it. Ms. Lennartz e-mailed Mr. Sensibile to “clarify the confusion,” “express to him that [the] Department of Health had concerns,” and request an update on Darbun’s progress. Mr. Sensibile sent a letter to Ms. Lennartz in response to her request. Ms. Lennartz did not respond to Mr. Sensibile’s letter. Darbun resubmitted its plans to OSHPD in October 2008.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rainey v. Nevada Irrigation District CA3
California Court of Appeal, 2026
Smith v. Superior Court CA3
California Court of Appeal, 2025
Itkin v. Greenfield CA2/3
California Court of Appeal, 2025
Khorshidi v. Javaheri CA2/4
California Court of Appeal, 2024
Tesoro Refining & Marketing Co. v. Rickley CA2/2
California Court of Appeal, 2024
Starflinger v. KBC Capital CA4/1
California Court of Appeal, 2024
Rostack Investments v. Sabella CA2/8
California Court of Appeal, 2023
Jarecki v. Zitter CA4/1
California Court of Appeal, 2023
Reliant Life Shares, LLC v. Cooper
California Court of Appeal, 2023
Tidwell v. Tidwell CA1/3
California Court of Appeal, 2023
Ortiz v. Eisler CA2/5
California Court of Appeal, 2022
Grosman v. Kasloff CA2/7
California Court of Appeal, 2022
Smyth v. Berman
California Court of Appeal, 2019
Smyth v. Berman
242 Cal. Rptr. 3d 336 (California Court of Appeals, 5th District, 2019)
Orange Co. Water Dist. v. Alcoa
California Court of Appeal, 2017
Orange Cnty. Water Dist. v. Alcoa Global Fasteners, Inc.
219 Cal. Rptr. 3d 474 (California Court of Appeals, 5th District, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
239 Cal. App. 4th 399, 191 Cal. Rptr. 3d 340, 2015 Cal. App. LEXIS 689, Counsel Stack Legal Research, https://law.counselstack.com/opinion/darbun-enterprises-inc-v-san-fernando-community-hospital-calctapp-2015.