BOLIN, Judge.

West Monroe Real Estate Company, Inc., plaintiff’s assignor, entered into a written contract with defendants. The general purpose of the contract was for the West Monroe Real Estate Company to provide water and sewerage service to houses which were to be constructed in a proposed subdivision to be developed by defendants. The sewerage portion of the contract was assigned to D’Arbonne Sewerage Company on September 15, 1969. A dispute arose between plaintiff and defendants concerning the interpretation of the contract and acts of the parties performed in connection with the contract. Plaintiff instituted the present suit against defendants for $7,500, allegedly due it under the contract, plus attorney’s fees and special damages. Plaintiff further sought an injunction to prohibit de[419]*419fendants from continuing to use plaintiff’s sewer system in violation of the contract. Defendants reconvened seeking damages of $7,500. From judgment in favor of plaintiff against defendants in solido for $7,500, and rejecting all other demands, defendants appeal.

For reasons hereinafter expressed, we hold the lower court erroneously construed the contract and, accordingly, the amount of the judgment should be reduced.

The contract is brief and the portion which is involved in this case provides:

“WHEREAS, Sanders plan to develop certain property which lies East of D’Arbonne Street and South of Tennessee Gas Pipe Line, and Sanders and West Monroe Real Estate Company, Inc. hereby agree as follows:
“A. West Monroe Real Estate Company, Inc. will permit up to fifty (50) houses to tap on its water and sewer lines, after sewer and water lines are engineered and laid of equal quality and workmanship of Unit No. 1 and 2 of D’Ar-bonne Hills Subdivision and inspected and approved by George M. Cox.
“B. Plats, right-of-way easements will be made and the entire water and sewer systems deeded to West Monroe Real Estate Company, Inc.
“C. These house taps are to be paid in Lots of 12, 13 and 25 at the rate of One Hundred Fifty ($150.00) Dollars each, as follows:
1st. 12 houses of $1,800.00 at the first house need
2nd. 13 houses of $1,950.00 at the first house need
Six months notice and $3,750.00 must be given for the last 25 houses.
“D. Water lines are to be tapped and copper goose neck with valve and box set. Box to be furnished by West Monroe Real Estate Company, Inc.
“E. The above figures do not include the regular ninety ($90.00) Dollar sewer tap, water tap, and inspection fee, which is paid by the plumber.
“F. This contract expires three (3) years from February 1, 1968.
“G. All expense involved in this contract will be at the cost of the developer.
“It is further agreed and understood that Sanders assume no responsibility for the water and sewerage systems.
“THUS DONE AND PASSED before me, Notary, and the two undersigned competent witnesses on this 1st day of July, 1968.”

Plaintiff expanded its sewer system sufficiently to handle the fifty houses which defendants contemplated building on the property in Unit No. 4. Defendants, on the other hand, laid and constructed sewer lines on their property which they contend met the specifications called for in the contract. George Cox, president and owner of the sewerage company, inspected the lines laid by defendants and claimed they did not comply with the specifications. A dispute arose because the plaintiff company refused to allow houses constructed by defendants to be “tapped” onto the system. Defendants caused George Cox to appear before the Louisiana Public Service Commission on numerous occasions. These hearings resulted in the Commission ordering plaintiff company to allow the houses to be connected to the system.

The record shows that on February 1, 1971, the specified date for the ending of the contract, there were only twelve houses using plaintiff’s facilities. However, on the date of trial there were twenty-four houses using the sewer service. The trial judge interpreted the contract to mean that plaintiff was obligated to provide ample [420]*420water and sewerage facilities to defendants within the three year period and that this had been done. He further found that the $7,500 consideration was to be paid plaintiff for having these facilities available within three years to serve fifty houses to be built by defendants, and upon elapse of the period the total sum was due.

Defendants delineate the following as issues presented on appeal:

(1) Can a public utility subject to regulation by the Louisiana Public Service Commission contract in such fashion as to limit its obligation to provide services to the public?
(2) Is a contract which depends solely upon the whims of the obligor legally enforceable against the obligee?
(3) Has plaintiff performed its part of the contract so as to allow recovery against defendants?
(4) Assuming plaintiff is allowed recovery, to what sum is it entitled under the contract?

We consider first the question of whether plaintiff, being a public utility, may legally enter into a contract with defendants to expand its facilities. Relative to the issue, we find the cases of Louisiana Gas Service Company v. Louisiana Public Service Commission, 245 La. 1029, 162 So. 2d 555 (1964); Waterworks District No. 3 of Rapides Parish, Louisiana v. City of Alexandria, 236 La. 804, 109 So.2d 426 (1959); Shreveport Traction Co. v. City of Shreveport et al., 122 La. 1, 47 So. 40 (1908), hold such contracts are legally permissible, and the argument to the contrary is without merit.

The contention that the contract is unenforceable because its compliance depended entirely upon the whims of George Cox is based upon Louisiana Civil Code Article 2034 which provides:

“Every obligation is null, that has been contracted, on a potestative condition, on the part of him w?jo binds himself.”

We are of the opinion this argument is unfounded. The courts of Louisiana have upheld contracts containing similar provisions. Arkansas Fuel Oil Corporation v. Maggio (La.App. 4th Cir. 1962), 141 So.2d 516; Whited & Wheless, Limited v. Calhoun, 122 La. 100, 47 So. 415 (1908). In Whited the court said:

“ . . .It [plaintiff] could be made by Calhoun to comply with those obligations, even though the title was not ‘satisfactory’ to it, if in point of law it was one which it should legally have been satisfied with . . . .”

By analogy plaintiff could have been, and in fact was, made to comply with its obligation in this case. The Public Service Commission, while denying its jurisdiction to interpret the contract, found plaintiff to be a public utility and, as such, had an obligation to the public to extend its services whenever economically feasible to do so.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sam's Style Shop v. Cosmos Broadcasting Corp.
496 F. Supp. 46 (E.D. Louisiana, 1980)
Franks v. Louisiana Health Serv. & Indem. Co.
382 So. 2d 1064 (Louisiana Court of Appeal, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
259 So. 2d 417, 1972 La. App. LEXIS 5664, Counsel Stack Legal Research, https://law.counselstack.com/opinion/darbonne-sewerage-inc-v-sanders-lactapp-1972.