Dan's Excavating Inc v. Department of Transportation

CourtMichigan Court of Appeals
DecidedApril 11, 2024
Docket365489
StatusUnpublished

This text of Dan's Excavating Inc v. Department of Transportation (Dan's Excavating Inc v. Department of Transportation) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dan's Excavating Inc v. Department of Transportation, (Mich. Ct. App. 2024).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

DAN’S EXCAVATING, INC and SPARTAN UNPUBLISHED SPECIALTIES, LTD, April 11, 2024

Plaintiffs-Appellants,

v No. 365489 Court of Claims MICHIGAN DEPARTMENT OF LC No. 22-000191-MZ TRANSPORTATION and STATE OF MICHIGAN,

Defendants-Appellees.

Before: GADOLA, C.J., and BORRELLO and M. J. KELLY, JJ.

PER CURIAM.

Plaintiffs, Dan’s Excavating, Inc (DEI) and Spartan Specialties, LTD (Spartan), appeal as of right the order of the Court of Claims granting defendants, Michigan Department of Transportation (MDOT) and State of Michigan, summary disposition of plaintiffs’ claims under MCR 2.116(C)(7) and (8). We affirm. I. FACTS

This appeal arises from a contract dispute, the underlying facts of which essentially are undisputed. In 2018, DEI and MDOT entered into a contract known as MDOT Contract ID No. 38101-115861, under which DEI agreed to undertake reconstruction of 9.87 miles of I-94 in Jackson, Michigan. The contract provided that the project would be governed by MDOT’s Standard Specifications for Construction. The contract also provided for the establishment of a Dispute Resolution Board (the Board) to “evaluate and provide recommendations as to the entitlement of claims arising out of the work on the contract.” The Board’s dispute resolution procedure was governed by the DRB Procedures in effect between October 6, 2017, and June 4, 2020.

DEI subcontracted portions of the work under the contract to Spartan, including certain mine void grouting work, which was to be performed in accordance with plans provided by MDOT. After beginning work on the project, Spartan discovered that the mine voids were not as represented on MDOT’s plan; the voids were smaller but more numerous than represented by

-1- MDOT, which required the mine void grouting to proceed at a much slower rate, resulting in a greater labor cost than anticipated. Plaintiffs assert that they incurred more than $850,000 in additional costs as a result of the increased labor required to complete the mine void grouting work.

In January 2020, DEI brought Spartan’s claim to the Board. The procedures in effect provided that a party to the contract could bring a dispute to the Board, which would then provide a recommendation on the claim. A party then could appeal that decision to the Board’s hearing panel, which would issue a recommendation. The procedures further provided:

Upon receipt of the DRB appeal hearing recommendation, the Contractor and Engineer have five (5) business days to initiate one of the following options:

1. Accept the DRB appeal recommendation as issued for any submitted claim issue.

2. Reject the DRB appeal recommendation as issued for any submitted claim issue.

***

If the Contractor or Engineer fails to document acceptance or rejection of the DRB appeal recommendation to the other party, in whole or in part, within five (5) business days of receipt of the DRB appeal recommendation, that failure to respond will constitute full acceptance of the DRB appeal recommendation by the Contractor or Engineer.

In July 2020, the Board held an advisory hearing and recommended “some entitlement through negotiation.” Plaintiffs then sought a formal hearing before the Board, after which the Board issued a recommendation of non-entitlement on the claim. DEI requested an appeal hearing on behalf of Spartan, which was held November 9, 2020. On November 30, 2020, the Board issued its appeal hearing recommendation of non-entitlement on the claim, and advised DEI and MDOT of its decision.

Under the DRB Procedures, each party had five business days after receiving the Board’s recommendation to send its acceptance or rejection of the recommendation to the other party, with a copy to the Board. The parties do not dispute that DEI did not respond to the Board’s recommendation within the allotted five business days. On December 15, 2020, MDOT confirmed by email to the Board and DEI that DEI had failed to respond to the Board’s recommendation.

On November 29, 2021, DEI filed its Notice of Intent to File Claim with the Court of Claims. On November 17, 2022, plaintiffs filed their complaint with the Court of Claims initiating this action and alleging breach of contract, breach of warranty, and unjust enrichment. In response, defendants moved for summary disposition under MCR 2.116(C)(7) and (8), contending that the claims were barred by the terms of the contract, that Spartan lacked standing to bring the claims, and that unjust enrichment could not be demonstrated because the dispute was governed by express contractual provisions.

The Court of Claims granted defendants’ motion for summary disposition under MCR 2.116(C)(7) and (8). The Court of Claims held that under the terms of the parties’ contract, DEI’s

-2- failure timely to reject the Board’s appeal hearing recommendation constituted an acceptance of the recommendation, which was a settlement of plaintiffs’ claims of breach of contract and breach of warranty. The Court of Claims further held that plaintiffs had failed to state a claim of unjust enrichment because the terms of the parties’ agreement were determined by an express contract. Plaintiffs now appeal.

II. DISCUSSION

A. STANDARD OF REVIEW

We review de novo a trial court’s decision to grant or deny summary disposition. Meemic Ins Co v Fortson, 506 Mich 287, 296; 954 NW2d 115 (2020). We also review de novo the interpretation of a contract, the application of legal and equitable doctrines, see Sylvan Twp v City of Chelsea, 313 Mich App 305, 315-316; 882 NW2d 545 (2015), and whether a plaintiff may maintain a claim for unjust enrichment, Karaus v Bank of New York Mellon, 300 Mich App 9, 22; 831 NW2d 897 (2012).

Summary disposition under MCR 2.116(C)(7) is warranted when a claim has been disposed of by a valid release of liability between the parties, among other bases. When reviewing a motion granted under MCR 2.116(C)(7), the court considers the documentary evidence submitted by the parties and accepts as true the plaintiff’s well-pleaded factual allegations, construing them in favor of the plaintiff unless disputed by documentary evidence presented by the moving party. Norman v Dep’t of Transp, 338 Mich App 141, 146; 979 NW2d 390 (2021).

A motion for summary disposition under MCR 2.116(C)(8) tests the legal sufficiency of a claim and is warranted when a claim is so unenforceable that no factual development could justify relief. El-Khalil v Oakwood Healthcare, Inc, 504 Mich 152, 159-160; 934 NW2d 665 (2019). When reviewing a trial court’s decision to grant or deny summary disposition under MCR 2.116(C)(8), the court considers the pleadings alone and accepts all factual allegations as true. Id.

B. BREACH OF CONTRACT AND WARRANTY

Plaintiffs contend that the Court of Claims erred by granting defendants summary disposition of their claims of breach of contract and breach of warranty. We disagree.

When interpreting a contract, the primary goal is to determine and give effect to the parties’ intent. Village of Edmore v Crystal Automation Sys, Inc, 322 Mich App 244, 262; 911 NW2d 241 (2017). This Court reads the contract as a whole and considers the words of the contract in context, giving the contractual terms their ordinary meaning. Id. The rules of contract construction apply regarding the scope and terms of a release. Radu v Herndon & Herndon Investigations, Inc, 302 Mich App 363, 374; 838 NW2d 720 (2013).

A cause of action may be precluded by MCR 2.116(C)(7) when a valid release of liability exists between the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Keywell & Rosenfeld v. Bithell
657 N.W.2d 759 (Michigan Court of Appeals, 2003)
Xu v. Gay
668 N.W.2d 166 (Michigan Court of Appeals, 2003)
Roberts v. Farmers Insurance Exchange
737 N.W.2d 332 (Michigan Court of Appeals, 2007)
Morris Pumps v. Centerline Piping, Inc.
729 N.W.2d 898 (Michigan Court of Appeals, 2007)
Sylvan Township v. City of Chelsea
882 N.W.2d 545 (Michigan Court of Appeals, 2015)
Rodgers v. Jpmorgan Chase Bank Na
890 N.W.2d 381 (Michigan Court of Appeals, 2016)
Village of Edmore v. Crystal Automation Systems Inc
911 N.W.2d 241 (Michigan Court of Appeals, 2017)
the Meisner Law Group v. Weston Downs Condominium Association
909 N.W.2d 890 (Michigan Court of Appeals, 2017)
Karaus v. Bank of New York Mellon
831 N.W.2d 897 (Michigan Court of Appeals, 2012)
Radu v. Herndon & Herndon Investigations, Inc.
838 N.W.2d 720 (Michigan Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Dan's Excavating Inc v. Department of Transportation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dans-excavating-inc-v-department-of-transportation-michctapp-2024.