Danielson v. Cline

12 N.W.2d 254, 234 Iowa 167, 1943 Iowa Sup. LEXIS 89
CourtSupreme Court of Iowa
DecidedDecember 14, 1943
DocketNo. 46367.
StatusPublished
Cited by2 cases

This text of 12 N.W.2d 254 (Danielson v. Cline) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Danielson v. Cline, 12 N.W.2d 254, 234 Iowa 167, 1943 Iowa Sup. LEXIS 89 (iowa 1943).

Opinion

Miller, J.

This is an action to quiet title. Plaintiff owns certain lands within Cedar Drainage District No. 6 in Jefferson county. On October 10, 1928, special assessments were levied thereon for the construction of said drainage project. On November 19, 1940, additional assessments were levied. The assessments on plaintiff’s lands were not paid. Plaintiff asserted that the assessments did not constitute valid liens upon his lands and prayed for a decree to that effect. Defendants as *168 serted and the court found that each assessment was a valid lien. The decree dismissed the action. Plaintiff appeals.

The issues presented by the pleadings are stated in general terms. The record made at the trial is voluminous. However, the propositions asserted by plaintiff-appellant as grounds for reversal at our hands clarify the situation and narrow the scope of our inquiry considerably. The original assessments are claimed to be void for the following reasons: Before a valid contract for the construction of the ditch could be let, the county engineer was required to report to the county auditor the probable cost of the improvement; the board was required to find that the cost thereof was not excessive and to give notice to bidders specifying, the approximate work to be done; these requirements were not met unless the engineer ascertained how much solid rock had to be removed; the engineer did not attempt to ascertain anything in regard to solid rock and stated that he did not know whether or not rock .would be encountered, or how much, if any. The additional assessments are claimed to be void because attempt was made to levy them pursuant to section 7479, Code, 1927, and the board failed to comply with the provision of that section that the assessments be “payable at the next taxpaying period after such indebtedness is incurred * * The trial court found no merit in either contention. We agree with the trial court.

I. It will be noted that, as to the original assessments, the establishment of the district is not challenged, only the validity of the contract for the improvement. That challenge is not made by way of appeal, authorized by sections 7513 and 7515, Code, 1927, but in a collateral attack, made some twelve years after the contract was let. Such a challenge can succeed only if the contract was let in such an irregular manner as to render it void. Chicago, M. & St. P. Ry. Co. v. Phillips, 111 Iowa 377, 380, 82 N. W. 787, and cases cited.

The plaintiff’s contention that the contract is void is predicated upon the clause relating to the removal of rock in the construction of the ditch. The plaintiff contends that such clause renders the contract wholly void. The trial court determined that the rock clause in the contract was void, that the contractor could not have recovered anything for the work *169 done under the rock clause; that the clause was separable, however, so that the rest of the contract was not jeopardized by its invalidity, and, since in fact the - contractor did not recover anything under the rock clause, the collateral attack by plaintiff could not be sustained. The crux of the inquiry is, “Was the coui’t right in holding that the rock clause was separable and the contractor did not recover anything under it?” We answer, “Yes.”

The essential facts upon which plaintiff relies to sustain his contention that the contract is entirely void are the following: W. L. Hollrook was originally employed as civil engineer. He estimated the cost of the improvement as follows: “560,000 cu. yds. @ 7c, $39,200.00; Eight of way, 10,800.00; Engineering, 7,500.00; Incidentals, 10,000.00; Total, $67,200.00 [$67,500].” Hollrook died and W. A. Griffith was employed as engineer. His estimate was as follows: “560,000 cu. yds.@ 8c, $44,800.00; Eight of way, 10,800.00; Engineering, 7,500.00; Incidentals, 5,000.00; Total, $68,100.00.” On June 13, 1928, the board determined that the cost and expense of the improvement was not a greater burden than should be justly borne by the lands benefited and that said District No. 6 should be established as set forth in the engineer’s report. The notice to contractors and the plans and specifications did not specify how much, if any, of the 560,000 cubic-yards excavation would contain rock. The notice to contractors attached to the form of contract in the specifications provided: “The total amount of the excavation is- estimated at 560,000 CY cubic yards, supposed to be earth consisting of silt and clay but the Contractor must satisfy himself as to the classifications. ’ ’ Ten bids were submitted. At the time of the letting a contractor raised the question about rock. The engineer did not know what, if any, rock would be encountered. The contractors added to their bids provisions relating to rock.

Briggs & Drew bid $0,079 per cubic yard for dirt, $1 for loose rock, $2.50 for solid rock; L. E. Sternberg’,bid $0.0865 for dirt, with the price for rock “to be mutually agreed upon”; C. E. Walker bid $0,105 for dirt, $0.75 for loose rock, $3 for solid rock; J. H. Boyce Sons Company bid $0,072 for dirt, $2.25 for rock; Matthews Brothers Construction Company bid $0.0694 for dirt, $2.50 for rock; Callahan-Walker Construction Com *170 pany bid $0.0724 for dirt, $1.90 for material requiring blasting; Fred M. Crane bid $0.10 for dirt, $3.50 for rock requiring blasting; E. L. Hatton bid $0.0824 for dirt, $2 for rock; J. AV. Boyer bid $50,000 for excavation and added “Bock $3.00 per yd.”; Jack Boyne Construction Company bid $0,072 per cubic yard for excavation, and added, “Rock Clause. Should we strike rock the following prices are to be charged for same. Solid Rock 2.50 pr. cu. yard, Loose Rock 1.50.” The contract was awarded to Jack Boyne Construction Company. The work was completed March 14, 1930. The first assessment was made by the board on October 10, 1928, based upon the engineer’s estimate, and was for $59,757.34. This assessment was insufficient to pay the cost of the improvement. Rock was encountered in three places. In one place, 3,490.4 cubic yards of solid rock were excavated; in another, 1,633.12 cubic yards were excavated; in a third, considerable rock was left in the bottom of the ditch.

In contending that the foregoing facts show that the contract between the district and Jack Boyne Construction Company was void and the assessments levied to pay the cost of the improvement likewise void, plaintiff relies upon several former decisions of this court.

In the case of Gjellefald v. Hunt, 202 Iowa 212, 210 N. W. 122, a clause in a contract for construction of a drainage ditch to the effect that if rock or quicksand is encountered the contractor shall be paid on a basis of cost plus fifteen per cent was held to be void when the specifications and advertisement for bids were silent on such contingency. In Chicago, R. I. & P. Ry. Co. v. Town of Dysart, 208 Iowa 422, 223 N. W. 371, a clause of a contract for construction of a sewer, which contained a provision for construction of a lift station on a cost-plus basis, was held to be invalid because the specifications and notice to bidders were silent as to any such provision. In Coggeshall v. City of Des Moines, 78 Iowa 235, 41 N. W. 617, a paving contract was held to be void and special assessments levied to pay for it could not be enforced because the notice to bidders was too vague and indefinite as to materials to be used. In Comstock v. City of Eagle Grove, 133 Iowa 589, 594, 595, 111 N. W.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Voogd v. JOINT DRAIN. DIST., KOSSUTH & WINNEBAGO COS.
188 N.W.2d 387 (Supreme Court of Iowa, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
12 N.W.2d 254, 234 Iowa 167, 1943 Iowa Sup. LEXIS 89, Counsel Stack Legal Research, https://law.counselstack.com/opinion/danielson-v-cline-iowa-1943.