Daniels v. Big Horn Federal Savings & Loan Ass'n

604 P.2d 1046, 1980 Wyo. LEXIS 225
CourtWyoming Supreme Court
DecidedJanuary 10, 1980
Docket5167
StatusPublished
Cited by4 cases

This text of 604 P.2d 1046 (Daniels v. Big Horn Federal Savings & Loan Ass'n) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Daniels v. Big Horn Federal Savings & Loan Ass'n, 604 P.2d 1046, 1980 Wyo. LEXIS 225 (Wyo. 1980).

Opinion

ROSE, Justice.

The issue in this appeal is whether plaintiffs-appellants, Larry and Gloria Daniels, presented a sufficient case to the trial court for it to find that defendant-appellee, Big Horn Federal Savings and Loan Association, was liable for negligent disbursement of construction-loan proceeds borrowed by the Danielses. This appeal involves no factual disputes. Appellants’ sole contention is that the facts of this case, even when conflicts are resolved in favor of Big Horn, establish liability on the part of Big Horn.

*1047 The Savings and Loan Association correctly conceded at trial that it was chargeable with exercising due care in looking after the Danielses’ interest when disbursing their funds. The trial judge found that Big Horn had exercised due care and awarded judgment in its favor. Thus, the issue on appeal becomes this: How much care did the Savings and Loan Association owe to the Danielses and, under the facts of record, was its duty of care discharged? We will affirm the trial judge on the ground that Big Horn did exercise whatever care with which it could, in law, be chargeable.

THE FACTS

In the summer of 1977, the Danielses, for the sum of $38,500.00, contracted with one Jerry Wood to build a house in Thermopolis, Wyoming, on a lot provided by the Daniels-es. Mr. and Mrs. Daniels arranged with Big Horn for a construction loan of $33,-000.00, contemplating that they would utilize $18,000.00 of their own money with which to purchase a $12,300.00 lot and make an initial payment to the contractor. (Although the contract called for a 20% initial payment, the contractor agreed to accept $5,000.00.)

Big Horn became involved as a lender on October 6, 1977, and at that time made a controversial disbursement. By that date, construction on the house had progressed to the point where 45% of the contract price— the 20% initial payment and a 25% progress payment — minus the $5,000.00 already paid, was owed the contractor by the Danielses under the contract between these parties. By that time some disturbing things had happened. Mr. Daniels had discovered that three subcontractors or materialmen were threatening liens on the property; Kay O’Leary, manager of the Thermopolis branch of Big Horn, had received a call from one George Bower, a director of Big Horn and a Worland “customer” of Wood, wherein she was advised to be careful about the loan because Bower had doubts about Wood’s financial and building abilities. Ms. O’Leary was aware that Wood owed money in Worland and correctly surmised that he would use some of the loan-disbursement proceeds to pay off his Worland obligations. She also knew that Wood was to receive a final payment on a Worland project when he settled the remaining debts incurred while building that project.

Before making any disbursements on October 6, 1977, Ms. O’Leary met with Larry Daniels. It was Ms. O’Leary’s suggestion that Wood be required to present her with a list of all debts owed on the Danielses’ house. Checks, jointly payable to Wood and his creditors, would then be issued in payment of these debts. In addition, Ms. O’Leary proposed retaining 10% of the 25% progress payment which was due. This 10% “retainage,” as well as the final payment due upon completion, would be withheld pending receipt of lien waivers.

Mr. Daniels agreed to both of these measures and to the loan disbursements that were actually made. The trial judge found that Mr. Daniels had signed an acknowl-edgement of receipt of a list of the disbursements before the disbursements were made.

On October 6, 1977, Big Horn disbursed $3,961.19 in the form of joint checks to Wood and his creditors and $11,379.00 to Wood only. This last-mentioned disbursement to Wood appears to be the only payment that the Danielses specifically complain about. O’Leary testified that she arrived at the $11,379.00 figure due Wood by computing 45% of the contract price and then subtracting $5,000.00, as well as 10% of the 25% progress payment. The Danielses have not alleged that it was negligent of O’Leary to fail to subtract the $3,961.19 paid Wood’s creditors from the $11,379.00 that was calculated to be due Wood. Accordingly, we will consider the disbursements as having been made within the framework of the contract schedule and with the Danielses’ consent.

Several weeks later, Wood walked off the job leaving an unfinished house and unpaid bills. Another builder was hired to complete the work, the bills were paid, and the structure wound up costing the Danielses about $60,000.00. (The trial court did *1048 award the Danielses a judgment of approximately $23,000.00 against Wood. However, the strong implication is that this judgment represents only a symbolic victory.)

The record shows that the $3,961.19 paid jointly to Wood and his creditors on October 6 failed to extinguish all of Wood’s liability existing at that date on the Danielses’ house.

At trial there was uncontradicted expert testimony to the effect that: (1) It was uncommon in Wyoming at that time to obtain lien waivers from a contractor before the project was completed; and (2) contractors usually kept only one account out of which they paid bills due on various projects and into which they put money received from various projects.

Appellants’ Contentions

The Danielses recognize that part of the difference between the bid price of the house and the ultimate cost comes about by reason of the fact that Wood underbid the house, which underbid they estimate to be $5,000.00. After allowing for this, they calculate that they suffered a “loss” of $17,-994.58 on the construction of the house and argue that “Big Horn Federal should have been assigned the burden of proving that the remaining $17,994.58 of the Daniels’ [sic] loss actually went into the Daniels’ [sic] house.” 1

The Law

The litigants do not cite us, nor have we found, any Wyoming cases the subject of which is a claim by a borrower that a construction lender made a negligent disbursement of proceeds to the contractor.

Many courts conclude that when the lender insists on making the disbursements, it is obligated to take some steps to protect the borrower’s interest along with its own.

Thé Supreme Court of Alaska, in Fikes v. First Federal Savings and Loan Association of Anchorage, Alaska, 533 P.2d 251, 261 (1975), quotes with approval language in a New Jersey decision:

“ ‘[W]e think plain principles of equity at least call for ... a construction lender to make and administer the loan in the conventional manner of a construction lender rather than mask what is essentially a loan on the general credit and reliability of the borrower and the security of the land value as a construction loan, and act accordingly in disbursing the funds.’ ” (From Cambridge Acceptance Corporation v. Hockstein, 102 N.J.Super. 435, 246 A.2d 138, 141 (App.Div.1968).)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cooley v. Gulf Bank, Inc.
773 So. 2d 1039 (Court of Civil Appeals of Alabama, 1999)
Moewes v. Farmer's Insurance Group
641 P.2d 740 (Wyoming Supreme Court, 1982)
Garbish v. Malvern Federal Savings & Loan Ass'n
17 Pa. D. & C.3d 202 (Chester County Court of Common Pleas, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
604 P.2d 1046, 1980 Wyo. LEXIS 225, Counsel Stack Legal Research, https://law.counselstack.com/opinion/daniels-v-big-horn-federal-savings-loan-assn-wyo-1980.