Daniels Co. v. Nevling

5 Pa. D. & C.2d 314, 1955 Pa. Dist. & Cnty. Dec. LEXIS 212
CourtPennsylvania Court of Common Pleas, Clearfield County
DecidedDecember 21, 1955
Docketno. 891
StatusPublished

This text of 5 Pa. D. & C.2d 314 (Daniels Co. v. Nevling) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Clearfield County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Daniels Co. v. Nevling, 5 Pa. D. & C.2d 314, 1955 Pa. Dist. & Cnty. Dec. LEXIS 212 (Pa. Super. Ct. 1955).

Opinion

Pentz, P. J.,

Plaintiff, The Daniels Company, Contractors, Inc., filed petition on September 15, 1955, requesting declaratory judgment to determine the meaning of one clause in a contract entered into under date of July 30, 1954, between plaintiffs, the Daniels Company, Contractors, Inc., and James K. Nevling, trustee for the benefit of James C. Walker, and as a trustee for the benefit of Charles Alan Walker and Susan Louise Walker, and as trustee along with Ray S. Walker and Louise S. Walker for the benefit of Lenore Ann Walker.

Defendant filed his answer to the petition and incorporated therein new matter.

Plaintiff then filed preliminary objections to the new matter, and at the same time, filed a motion for a judgment on the pleadings.

The case was set for argument October 20, 1955, and at the time of argument, defendant presented motions to strike off the two motions filed by the plaintiff.

The first consideration is the situation created by the pleadings filed and that will be disposed of before passing to the question presented by the pleadings, which are found to be in order.

The petition is based upon a contract between the parties, dated July 30, 1954, for the sale and construction of a coal washing system by plaintiff for defendants. So far as the record indicates, this system was constructed and completed in accordance with the specifications and has been paid for by defendant. The fourth paragraph of the petition sets forth the clause of the contract in dispute, as follows, appearing in the contract under the words “Auxiliary Agreements” :

“The Contractor agrees to supply the Purchaser with two (2) additional DMS Washing Systems at the Contractor’s cost plus 10% within 24 months of the date of this agreement.”

[316]*316The controversy, it is then averred, arises over the interpretation of the meaning of this particular clause. Plaintiff contends it constitutes a binding contract on defendant to purchase two additional washing systems, within the 24-month period. Defendant insists that the clause is an option only and does no more than give defendant the right to purchase at any time within the 24-month period the two additional washing systems.

The other essential averments in the petition are to the effect that if the clause is construed to mean a binding purchase agreement, plaintiff intends to enforce all his rights thereunder and bring action for damages in the event defendant does not comply therewith; that a determination by declaratory judgment, one way or the other, will end the dispute; that to wait until the expiration of the 24 months to bring an action great injury will be inflicted upon both parties.

Defendant in his pleading, designated an answer* in which is incorporated new matter, corrects the name and status of the party-defendant, without demurring to plaintiff’s designation of defendant and his status. Defendant then denies each and every averment in the petition; admits the agreement to purchase one washing system as contained in the agreement of July 30, 1954, together with the clause therein contained as set forth and quoted in paragraph four of the petition, but sets forth additional items to be added to the contract, as disclosed in three letters attached to the answer, and designated defendant’s exhibits A, B and C. Whether or not these three letters alter, vary or change the contract of July 30, 1954, is not material to the existing issue. None of these letters refers in-any way to the particular clause in question. They are all in regard to additional equipment to be added to the washing system contracted for [317]*317in the agreement of July 30th. Exhibit C reserves to defendant the right to assign his rights under the agreement of July 30, 1954 to certain specified persons, to which the petitioner agrees, and which right to assign, defendant, in his answer, adds to the clause in question, but does not assert that clause is in any way affected, other than that defendant has a right to assign all of his rights in the whole contract.

In the body of the answer, defendant sets up a breach of warranties by plaintiff provided in the original agreement, and then asserts there is a dispute between the parties concerning the length of time the warranties shall exist. Plaintiff takes the position the warranties terminated July 15, 1955, and defendant contends that they continue indefinitely.

Under the heading of new matter, defendant again asserts a breach of the warranties and the dispute between the parties concerning the date the warranties expired, and prays for a declaratory judgment to first dismiss the petition of the plaintiff, or, to decree, (in effect) the clause in question is-an option, or a right to purchase the two additional washers at the contractor’s cost plus 10 percent within 24 months, and third, to determine the length of time the warranties exist.

Following the filing of the answer to new matter, the subsequent pleadings mentioned were filed.

The petition asks for a declaratory judgment setting forth the reasons therefor, and although no reference is made to the Uniform Declaratory Judgments Act of June 18, 1923, P. L. 840, as amended, 12 PS § §831-853, the petition falls within the provisions of the act.

The procedure to be followed, in any petition for a declaratory, judgment* is defined by the Act of May 22, 1935, P. L. 228, 12 PS §§847-853, added as a supplement to the Uniform Declaratory Judgments Act enacted June 18, 1923, P. L. 840, 12 PS §§831-846, [318]*318847-853. Before the adoption of the supplement of 1935, supra, no procedure had been defined.

Section 2 of the Supplemental Act of 1935 was amended by the Act of April 13, 1943, P. L. 43, 12 PS §848, providing for the matter of service.

The first section of the supplemental act 12 PS §847, defines the form of petition. The fifth section defines the answer, as follows, 12 PS §851:

“A defendant may by his answer, without first replying to the averments of fact in the petition, raise any question of law which goes either to the jurisdiction of the court or to petitioner’s legal right to have the disputed matter determined in this character of proceeding, and any such question of law may be set down for hearing and disposed of in limine. If in the opinion of the court, the decision of the question, thus set for hearing, requires the determination against the petitioner of the point or points there raised, the court may make such order thereon, as the situation demands. If the court shall decide such points so raised against a defendant, he may, within fifteen days, file an answer to the averments of fact in the petition, and the case shall be set down for a hearing on. the merits of the controversy.” Act of May 22, 1935, P. L. 228, sec. 5.

Giving effect to the provisions of section 5 as quoted, it is obvious the new matter, the preliminary objections, the motion for judgment on the pleadings, and the motion to dismiss the same, are not authorized by the Uniform Declaratory Judgments Act. These pleadings, from the “New Matter” on, only serve to confuse the issue. Although the Statutory Construction Act of May 28, 1937, P. L. 1019, 46 PS §558, was enacted after section 5 of the Uniform Declaratory Judgments Law was in effect, subsection 8 of section 58 of the Statutory Construction Act expresses the policy of the law prior thereto, namely that statutes [319]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lifter Estate
103 A.2d 670 (Supreme Court of Pennsylvania, 1954)
Eureka Casualty Co. v. Henderson
92 A.2d 551 (Supreme Court of Pennsylvania, 1952)
Fischer & Porter Co. v. Porter
72 A.2d 98 (Supreme Court of Pennsylvania, 1950)
Currie v. Land Title Bank & Trust Co.
5 A.2d 168 (Supreme Court of Pennsylvania, 1939)
Korr v. Butz
40 A.2d 699 (Superior Court of Pennsylvania, 1944)
Melnick v. Melnick
25 A.2d 111 (Superior Court of Pennsylvania, 1941)
Barnes v. Rea
68 A. 836 (Supreme Court of Pennsylvania, 1908)
Barnes v. Rea
68 A. 839 (Supreme Court of Pennsylvania, 1908)
McHenry v. Mitchell
68 A. 729 (Supreme Court of Pennsylvania, 1908)
Philadelphia Manufacturers Mutual Fire Insurance v. Rose
70 A.2d 316 (Supreme Court of Pennsylvania, 1950)
Burke v. Pittsburgh Limestone Corp.
100 A.2d 595 (Supreme Court of Pennsylvania, 1953)
Heat & Power Corp. v. Foust Distilling Co.
106 A.2d 225 (Supreme Court of Pennsylvania, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
5 Pa. D. & C.2d 314, 1955 Pa. Dist. & Cnty. Dec. LEXIS 212, Counsel Stack Legal Research, https://law.counselstack.com/opinion/daniels-co-v-nevling-pactcomplclearf-1955.