DANIEL MOTLEY VS. RALPH L. FINELLI VS. STEVEN LISA (L-0834-16, ESSEX COUNTY AND STATEWIDE)

New Jersey Superior Court Appellate Division·Decided July 16, 2019·No. A-5263-17T1·Unpublished

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION

DOCKET NO. A-5263-17T1

DANIEL MOTLEY, Plaintiff-Appellant,

v. RALPH L. FINELLI,

Defendant/Third-Party

Plaintiff-Respondent,

v.

STEVEN LISA, and L&B DEVELOPERS, LLC,

Third-Party Defendants.

Argued July 8, 2019 – Decided July 16, 2019 Before Judges Yannotti and Haas.

On appeal from the Superior Court of New Jersey, Law Division, Essex County, Docket No. L-0834-16.

Kristen Ragon argued the cause for appellant (Goldman Davis Krumholz & Dillon, PC, attorneys; Evan L.

Goldman and Kristen Ragon, on the brief).

Lisa M. Leili argued the cause for respondent (Vella, Singer and Associates, PC, attorneys; Lisa M. Leili and David J. Singer, of counsel and on the briefs).

PER CURIAM Plaintiff Daniel Motley appeals from an order entered by the Law Division on June 8, 2018, which denied his motion for reconsideration of an order dated April 16, 2018, which dismissed his claims against defendant Ralph L. Finelli with prejudice. We affirm.

I.

Plaintiff and his brother are the owners of property in the Borough of Seaside Park (the Borough). The property is located in the Borough's "R -3 zone," which restricts property to single-family uses. The property contained two structures, which were constructed before the R-3 zone restrictions went into effect and qualified as pre-existing, non-conforming uses. In 2008, plaintiff made plans to renovate one of the buildings after a hot water system burst and the structure sustained significant water damage.

Initially, plaintiff planned to add a second story to the building and filed a use variance with the Borough's Zoning Board of Adjustment (Board), seeking

A-5263-17T1

to expand the nonconforming use and certain bulk variances. The Board denied the application. Plaintiff revised his approach and hired defendant, a licensed architect, to design the construction plans. Defendant completed the plans on July 18, 2009.

In August 2009, plaintiff submitted an application for a zoning permit to the Borough's zoning officer, James Mackie, seeking permission to begin construction. On the portion of the application describing the work to be performed, plaintiff wrote, "[r]epair [r]enovation of [e]xisting dwelling" and "replace A/C." He attached defendant's plans to the application.

On August 28, 2009, Mackie approved the application and issued a permit to begin construction. The permit stated there was to be "[n]o expansion of [the structure's] dimensions[.]" The permit also stated, "[s]iding, shingles, additional windows only – no bumpouts." Construction began thereafter.

On January 20, 2010, the Borough's code enforcement officer, Patrick Linkovitch, telephoned plaintiff and informed him "that the construction that is being performed is beyond the scope of [the] zoning permit." Linkovitch asked plaintiff to meet with him at the Borough's zoning office the following day.

On January 21, 2010, plaintiff and his construction manager, Steven Lisa, met with Linkovitch and Mackie. Plaintiff testified that Mackie told plaintiff

A-5263-17T1

"the building went to[o] far and [plaintiff] was going to be issued a stop order." Mackie informed plaintiff that local ordinances prohibited renovations that affect more than fifty percent of an existing structure.

That same day, the Borough issued an order that prohibited any further construction on the property (the stop-work order). The stop-work order stated that the construction on the property exceeded the scope of the construction permit and that plaintiff needed to obtain an "update" to the permit before continuing construction.

Defendant became aware of the stop-work order, and on January 22, 2010, he wrote a letter to the Borough's construction office challenging the order and detailing the scope of his design plans. Defendant stated that he "anticipate[s] the removal of the [s]top [o]rder to be imminent."

On January 31, 2010, defendant wrote a letter to the Borough's zoning office, detailing the construction to date and stating that he "believe[d] all of the work has been carried out with the best interests of the owner and the [B]orough in mind, and with respect to all applicable codes and ordinances in effect at the date of issue." On February 4, 2010, the Borough posted a zoning violation notice on plaintiff's property.

A-5263-17T1

Plaintiff challenged the stop-work order in a petition to the Borough's Board of Adjustment (the Board), which thereafter conducted hearings on the petition. At the hearings, defendant stated that the project involved the total renovation of the building's interior and exterior, and the permit application provided for replacement of the roof, frame, and finish, installation of a new floor and staircase, as well as construction of a new upstairs bathroom. Defendant asserted that the renovation plan would not change the existing dimensions of the structure.

Lisa testified that the roof was removed first and as the work progressed, it became clear that the building had more damage than initially known. He stated that while he had hoped to retain as much of the existing walls as possible, the condition of the building did not permit that approach. He also said that many floor beams were rotted, and the main center beam was sagging six to eight inches. According to Lisa, the building inspector decided that the entire structure had to be removed.

Mackie testified that when he reviewed plaintiff's permit application and defendant's construction plans, he believed the plans called only for the construction of new windows, new shingles, and a new roof. Mackie stated that as construction progressed, he realized the construction that plaintiff was

A-5263-17T1

undertaking did not comply with the limitations imposed by the permit or with the Borough's zoning laws. Mackie testified that the demolition went beyond what he had anticipated. He stated that "everything was gone and it was all new construction."

Plaintiff testified that the plans that defendant prepared had alerted the Borough to the possibility that he might need to remove the walls. He stated that he had discussed with Mackie the replacement of the floor joists, insulation, and exterior-wall framing. In addition to seeking withdrawal of the stop-work order, plaintiff asked the Board to issue a use variance to allow him to continue the construction.

The Board upheld the stop-work order. The Board noted that under the relevant provision of the Borough's zoning ordinance, a pre-existing nonconforming use may be repaired or maintained, if such repairs or maintenance do not result in the total destruction of the property. The Board found that Mackie had approved repairs and renovations to the existing building, with certain limitations.

The Board stated that although the plans indicated a wooden floor and existing roof frame would be removed and replaced, the plans did not provide for replacement or removal of the building's walls. The Board found that the

A-5263-17T1

demolition and construction undertaken exceeded the zoning approvals which had been granted, and that the creation of additional living space in the structure constituted an impermissible expansion of the preexisting, nonconforming use.

Plaintiff appealed the Board's decision by filing an action in lieu of prerogative writs in the Law Division. The trial court found that the evidence presented to the Board did not demonstrate an "impermissible expansion of the nonconforming use," and that plaintiff's renovations did not alter the dimensions of the structure. The court set aside the stop-work order in part, and allowed plaintiff to resume certain development of the property. The Board appealed from the trial court's judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

DANIEL MOTLEY VS. RALPH L. FINELLI VS. STEVEN LISA (L-0834-16, ESSEX COUNTY AND STATEWIDE), (N.J. Ct. App. 2019).

DANIEL MOTLEY VS. RALPH L. FINELLI VS. STEVEN LISA (L-0834-16, ESSEX COUNTY AND STATEWIDE) (DANIEL MOTLEY VS. RALPH L. FINELLI VS. STEVEN LISA (L-0834-16, ESSEX COUNTY AND STATEWIDE)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

D'Atria v. D'Atria
576 A.2d 957 (New Jersey Superior Court App Division, 1990)
Fusco v. Board of Educ. of Newark
793 A.2d 856 (New Jersey Superior Court App Division, 2002)
Caravaggio v. D'AGOSTINI
765 A.2d 182 (Supreme Court of New Jersey, 2001)
Gautam v. De Luca
521 A.2d 1343 (New Jersey Superior Court App Division, 1987)
Cummings v. Bahr
685 A.2d 60 (New Jersey Superior Court App Division, 1996)
Motley v. Borough of Seaside Park Zoning Board of Adjustment
62 A.3d 908 (New Jersey Superior Court App Division, 2013)