Daniel Lucey v. Chesapeake Appalachia, LLC

CourtCourt of Appeals for the Fourth Circuit
DecidedOctober 1, 2019
Docket19-1150
StatusUnpublished

This text of Daniel Lucey v. Chesapeake Appalachia, LLC (Daniel Lucey v. Chesapeake Appalachia, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Daniel Lucey v. Chesapeake Appalachia, LLC, (4th Cir. 2019).

Opinion

UNPUBLISHED

UNITED STATES COURT OF APPEALS FOR THE FOURTH CIRCUIT

No. 19-1150

DANIEL M. LUCEY; COLLEEN S. LUCEY; ABEL LUCEY,

Plaintiffs - Appellants,

v.

CHESAPEAKE APPALACHIA, LLC,

Defendant - Appellee,

and

SWN PRODUCTION COMPANY, LLC,

Defendant.

Appeal from the United States District Court for the Northern District of West Virginia, at Wheeling. John Preston Bailey, District Judge. (5:17-cv-00066-JPB)

Submitted: August 9, 2019 Decided: October 1, 2019

Before KING, AGEE, and HARRIS, Circuit Judges.

Vacated and remanded by unpublished per curiam opinion.

David C. Hook, HOOK AND HOOK, Waynesburg, Pennsylvania, for Appellant. Nicolle R. Snyder Bagnell, Justin H. Werner, Kevin C. Abbott, REED SMITH LLP, Pittsburgh, Pennsylvania, for Appellee. Unpublished opinions are not binding precedent in this circuit.

2 PER CURIAM:

Daniel Lucey, Colleen Lucey and Abel Lucey (the “Luceys”) appeal from the

district court’s order granting Chesapeake Appalachia’s motion to dismiss for failure to

state a claim. On appeal, the Luceys contend that the district court erred in interpreting the

plain language of the parties’ contract. We agree, and we vacate and remand.

The Luceys entered into an Oil, Gas and Coalbed Methane Lease (the “Lease”) with

Great Lakes Energy Partners, LLC (“GLEP”). GLEP later assigned its interests in the

Lease to Chesapeake. The Lease had a primary term of five years with an expiration date

of August 21, 2011, and an option to extend or renew the lease within sixty (60) days of

the expiration date.

On May 31, 2011, Chesapeake attempted to extend the Lease by executing a Notice

of Extension of Oil and Gas Lease. The Luceys rejected Chesapeake’s attempt to extend

the lease and subsequently filed suit against Chesapeake in the United States District Court

for the Northern District of West Virginia (the “Initial Lawsuit”). Subsequently, the parties

settled the Initial Lawsuit by entering into a Settlement Agreement and Release (the

“Settlement Agreement”) and a Ratification of Oil and Gas Lease which extended the

Lease’s primary term to August 21, 2016. * The effective date of the Settlement Agreement

was October 29, 2012.

The Settlement Agreement provided the following:

* There are actually two materially identical settlement agreements, involving different plaintiffs. Our analysis applies to both agreements.

3 NOW, THEREFORE, in consideration of the following premises and the mutual covenants, the Parties hereby agree as follows:

1. In compromise and settlement of any and all claims, demands, actions, and damages of every kind and character brought by Plaintiffs against Releasees . . . all Parties agree that Chesapeake shall pay to Releasors total consideration in the amount of $2,000.00/acre for 203.39 acres totaling $406,780.00 (the “Consideration”). In addition, Chesapeake agreed to pay Releasors an additional $500.00/acre for 203.39 acres, totaling $101,695.00 (“Additional Consideration”) if there is not a commencement of two (2) wells within one (1) year of the effective date of this agreement. For the purpose of this agreement, commencement of a well is defined consistent with the terms of the Lease.

The ratified Lease provided that, “[a] well shall be deemed commenced when preparations

for drilling have been commenced.” Under the Settlement Agreement, the deadline for

commencement of two wells before “Additional Consideration” would be owed was one

year from the effective date of the Settlement Agreement, which would be on October 29,

2013.

Between May 11 and October 10, 2012, Chesapeake applied for permits to drill four

wells that would be located within the Michael Dunn Southwest Unit (the “Dunn Unit”).

No permit applications were filed within the one-year period after October 29, 2012.

However, Chesapeake started drilling the four wells on December 13, 2012, and completed

all four wells within one year of the execution of the Settlement Agreement. On January

3, 2013, Chesapeake recorded a Declaration and Notice of Pooled Unit, identifying the

Luceys’ property as part of the Dunn Unit.

On May 17, 2017, the Luceys brought the instant suit against Chesapeake and its

successor-in-interest SWN Production Company, LLC, asserting claims for breach of

contract. On November 30, 2017, Chesapeake filed a motion to dismiss the Luceys’ claims

4 for breach of contract pursuant to Federal Rule of Civil Procedure 12(b)(6). The district

court granted Chesapeake’s motion and dismissed the Luceys’ claims for breach of contract

with prejudice.

The district court reasoned that the plain language of the Settlement Agreement

provided that, in order to avoid paying Additional Consideration, Chesapeake only needed

to commence two wells at any time prior to October 29, 2013:

This language speaks only to a deadline for completion—within one year, two wells must be commenced—not to a range of dates within which the commencement of two wells must be commenced. The clear language of the agreement reflects only a one year deadline defined, but not limited, by the date the settlement agreement was actually signed.

The district court ruled that, because “[f]our wells were completed within that deadline,”

the Luceys could not present a cognizable claim for relief. The Luceys timely appealed.

We review de novo a district court’s ruling on a Rule 12(b)(6) motion, accepting

factual allegations in the complaint as true and drawing all reasonable inferences in favor

of the nonmoving party. Mason v. Machine Zone, Inc., 851 F.3d 315, 319 (4th Cir. 2017).

To survive a Rule 12(b)(6) motion to dismiss, a complaint must contain sufficient “facts to

state a claim to relief that is plausible on its face.” Bell Atl. Corp. v. Twombly, 550 U.S.

544, 570 (2007). In addition, we review de novo a district court’s decision on an issue of

contract interpretation, as the interpretation of a contract is a question of law that turns on

a reading of the document itself, and a district court is in no better position than this court

to decide such an issue. Seabulk Offshore, Ltd. v. Am. Home Assurance, Co., 377 F.3d

408, 418 (4th Cir. 2004).

5 A federal court sitting in diversity must apply the substantive law of the state in

which it sits, as there is no federal common law. See Erie R. Co. v. Tompkins, 304 U.S.

64, 78 (1938). Under West Virginia law, “the function of a court is to ascertain the intent

of the parties as expressed in the language used by them” in their contract. Zimmerer v.

Romano, 679 S.E.2d 601, 610 (W. Va. 2009). Therefore, the court must read the contract

as a whole, taking into consideration all the parts together. Id. Moreover, “specific words

or clauses of an agreement are not to be treated as meaningless, or to be discarded, if any

reasonable meaning can be given them consistent with the whole contract.” Dunbar

Fraternal Order of Police v. City of Dunbar, 624 S.E.2d 586, 591 (W. Va. 2005) (internal

quotation marks omitted). Additionally, West Virginia courts “will not interpret a contract

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Zimmerer v. Romano
679 S.E.2d 601 (West Virginia Supreme Court, 2009)
Lee Enterprises, Inc. v. Twentieth Century-Fox Film Corp.
303 S.E.2d 702 (West Virginia Supreme Court, 1983)
Wilson v. Gentile
8 Cal. App. 4th 759 (California Court of Appeal, 1992)
Mia Mason v. Machine Zone, Inc.
851 F.3d 315 (Fourth Circuit, 2017)
Dunbar Fraternal Order of Police, Lodge 199 v. City of Dunbar
624 S.E.2d 586 (West Virginia Supreme Court, 2005)
Consol Energy, Inc. v. Hummel
792 S.E.2d 613 (West Virginia Supreme Court, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Daniel Lucey v. Chesapeake Appalachia, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/daniel-lucey-v-chesapeake-appalachia-llc-ca4-2019.