Dalton v. 933 Peachtree, L.P.

661 S.E.2d 156, 291 Ga. App. 123
CourtCourt of Appeals of Georgia
DecidedMarch 21, 2008
DocketA07A1967-A07A1970
StatusPublished
Cited by3 cases

This text of 661 S.E.2d 156 (Dalton v. 933 Peachtree, L.P.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dalton v. 933 Peachtree, L.P., 661 S.E.2d 156, 291 Ga. App. 123 (Ga. Ct. App. 2008).

Opinion

ANDREWS, Presiding Judge.

Javier Berriel Lopez and Arthur Dalton, 1 employees of Glass Systems, Inc., the glass/window subcontractor on a condominium construction project, were severely shocked when an'aluminum slab edge cover they were lifting to the fourth floor of the project, owned by 933 Peachtree, L.P, contacted high-voltage power lines operated by Georgia Power Company. In these four cases, consolidated for purposes of appeal, Lopez and Dalton appeal from the summary judgments granted to 933 Peachtree, L.P, and Georgia Power on their claims based on premises liability (933 Peachtree, L.P) and negligence (Georgia Power).

Case Nos. A07A1967 and A07A1970

1. We first consider the grant of summary judgment to 933 Peachtree on Lopez and Dalton’s claims based on premises liability and their second enumeration, that the trial court erred by finding no issue of material fact regarding the owner’s control of the site and work.

In order to prevail on a motion for summary judgment under OCGA § 9-11-56,

the moving party must show that there exists no genuine issue of material fact, and that the undisputed facts, viewed *124 in the light most favorable to the nonmoving party, demand judgment as a matter of law. Moreover, on appeal from the denial or grant of summary judgment the appellate court is to conduct a de novo review of the evidence to determine whether there exists a genuine issue of material fact, and whether the undisputed facts, viewed in the light most favorable to the nonmoving party, warrant judgment as a matter of law.

(Citations omitted.) Benton v. Benton, 280 Ga. 468, 470 (629 SE2d 204) (2006).

So viewed, the evidence was that 933 Peachtree, L.E, a limited partnership, owned the property at 933 Peachtree Street, NE in Atlanta, which it sought to develop as a multi-use retail/residential project. It entered into a Development Management Agreement with 917 Peachtree, LLC, in March 2001, whereby 917 Peachtree agreed to act as development manager for the project.

On July 10, 2001, 933 Peachtree, L.E, entered into a contract with Dunn Southeast, Inc. d/b/a R. J. Griffin and Company (Griffin) pursuant to which Griffin would act as general contractor in the construction of the project, named the Metropolis.

Appellants contend that the owner maintained control over the project during the construction process, thereby subjecting it to liability. In support of this argument, they cite some portions of the contract documents. The following provisions, however, must also be considered.

Article 3, Relationship of the Parties, states that

[t]he Contractor accepts the relationship of trust and confidence established by this Agreement and covenants with the Owner to cooperate with the Architect and exercise the Contractor’s skill and judgment in furthering the interests of the Owner; to furnish efficient business administration and supervision; to furnish at all times an adequate supply of workers and materials; and to perform the Work in an expeditious and economical manner consistent with the Owner’s interests. The Owner agrees to furnish and approve, in a timely manner, information required by the Contractor and to make payments to the Contractor in accordance with the requirements of the Contract Documents.

Further, the General Conditions, which are included as part of the Agreement pursuant to Article 1, provide in Section 3.3.1 that

[t]he Contractor shall supervise and direct the Work, using the Contractor’s best skill and attention. The Contractor *125 shall be solely responsible for and have control over construction means, methods, techniques, sequences and procedures and for coordinating all portions of the Work under the Contract, unless the Contract Documents give other specific instructions concerning these matters.

(Emphasis supplied.)

Article 10 of the General Conditions, Protection of Persons and Property provides in pertinent part:

10.2.1 The Contractor shall take reasonable precautions for safety of, and shall provide reasonable protection to prevent damage, injury or loss to: .1 employees on the Work and other persons who may be affected thereby. . . .
10.2.3.1 The Contractor shall provide and maintain temporary protection, public utilities, etc. as required by the Contract Documents.

The project was located on Peachtree Street between 8th and 9th Streets. Running down Peachtree Street parallel to the buildings were three energized high-voltage power lines, with the closest one to the building (the field side phase) being 31 feet 8 inches high and 15 feet 5 inches from the building. The middle line (the middle phase), the one struck by plaintiffs, was 36 feet high and 18 feet from the building. Rick Breedlove, the superintendent for R. J. Griffin, notified the Utilities Protection Center (UPC) early in the construction of “Demolition/Grading/Setting Footers” work that was going to be performed by R. J. Griffin crews. This notice to UPC had nothing to do with work being performed by Glass Systems. In response to this notice, a Georgia Power engineer came to the site and determined that R. J. Griffin’s proposed work would not conflict with the power lines. Pursuant to Breedlove’s request, however, an orange rubber hose was placed on the field side phase in August 2001, and remained there throughout the project. Breedlove was unaware that Arthur Dalton intended to use the man-lift to lift the edge cover slabs and, had he been aware, he would have forbidden this use.

Glass Systems was the subcontractor in charge of installing the glass “skin” of the two towers being constructed. 2 Randy Dalton, appellant Arthur Dalton’s brother, was the job superintendent for Glass Systems and Arthur Dalton was the foreman of one of the crews installing the glass and the aluminum frames and edge covers. *126 Glass Systems had been on the job since late November/early December 2001. As foreman, one of Arthur Dalton’s responsibilities was conducting weekly safety meetings for Glass Systems. On May 31, 2002, the topic of the safety meeting was “Electrical Safety — Overhead Wires, Ground Faults, Overcurrent Protection.” Arthur Dalton was aware that workers should not come in contact with power lines and this was discussed at the May 31 meeting. Arthur Dalton was also aware that work should not be done within ten feet of a power line.

Deliveries of materials were generally made to the 8th Street side of the project. On June 14, 2002, a load of aluminum frames and 24-foot long aluminum edge cover slabs was delivered to the Peach-tree Street side of the job site around 8:00 a.m. by Glass Systems. The material was off-loaded by Arthur Dalton and his crew and the slabs needed to be taken to the fourth floor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scapa Dryer Fabrics, Inc. v. Roy Knight
770 S.E.2d 334 (Court of Appeals of Georgia, 2015)
GLASS SYSTEMS, INC. v. Georgia Power Co.
703 S.E.2d 605 (Supreme Court of Georgia, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
661 S.E.2d 156, 291 Ga. App. 123, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dalton-v-933-peachtree-lp-gactapp-2008.