Dalicandro v. Morrison Road Dev. Co., Unpublished Decision (4-17-2001)

CourtOhio Court of Appeals
DecidedApril 17, 2001
DocketNos. 00AP-619, 00AP-656.
StatusUnpublished

This text of Dalicandro v. Morrison Road Dev. Co., Unpublished Decision (4-17-2001) (Dalicandro v. Morrison Road Dev. Co., Unpublished Decision (4-17-2001)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dalicandro v. Morrison Road Dev. Co., Unpublished Decision (4-17-2001), (Ohio Ct. App. 2001).

Opinion

OPINION
Defendants-appellants, Morrison Road Development Company, Inc., and Steven M. Geiger, appeal from a judgment of the Franklin County Court of Common Pleas finding them in contempt of court for failing to comply with a court order to construct a dedicated road with utilities. In addition, appellants appeal the jury's decision to find them liable for various claims, including breach of contract and conversion, which were brought by plaintiffs-appellees, Valerio Dalicandro, Linda Dalicandro and VLD Grading, Inc.

Appellees' claims stem from the following facts. On December 8, 1993, appellees and appellants entered into a real estate purchase contract whereby appellants were to convey 4.5 acres of property located at the end of Claycraft Road in the city of Columbus. The contract was contingent on appellants constructing a road extending from Claycraft Road. The road was to be built with sewers. Although appellants had not constructed the road, a general warranty deed on the 4.5 acres was executed and delivered to appellees on November 27, 1995. The parties also entered into a closing agreement, whereby appellants again promised to build the dedicated road with sewers and a culvert.

On October 31, 1997, the parties entered into another real estate purchase contract, whereby appellants were to convey 3.308 acres westerly adjacent to the 4.5 acres previously transferred. At the time the parties contracted to convey the 3.308 acres, appellants had not built the dedicated road. However, in the real estate purchase contract, appellants promised to construct the dedicated road pursuant to city specifications with sewers and a culvert. As well, appellants promised to "clean up" the 3.308 acres within fourteen days. A deed on the 3.308 acres was executed and delivered to appellees on January 23, 1998. At the time of the closing, appellants had not constructed the dedicated road; however, the parties entered into another closing agreement obligating appellants to construct the road with sewers and a culvert.

Appellees were using the Claycraft property to store gravel that was eventually used by local developers. Trucks would either transport gravel to the property for storage, or remove the gravel for delivery to the local developers. However, on June 11, 1998, appellants blocked pathways to and from appellees' Claycraft property. Trucks were unable to leave the property because of the blocked paths. Eventually, appellees would remove the obstacles and regain control over their trucks. However, appellants re-blocked the pathways and would not allow appellees to haul gravel from their property. These activities took place until June 16, 1998, after the trial court issued a temporary restraining order prohibiting appellants from engaging in such conduct.

Thereafter, appellees filed suit against appellants alleging various claims, including breach of contract for failure to construct the dedicated road and utilities, breach of contract for failure to clean up the 3.308 acres of land, conversion of trucks, gravel and equipment, interference with appellees' business relationships, and trespass.

Before the trial commenced, the parties entered into an agreement approved and adopted on June 15, 1999, as an order of the trial court. In adopting the agreement, the trial court ordered appellants to "construct a 24 foot flex paved road over the .969 acres owned by [appellants] from the terminus of Claycraft Road." The road was to be approved by the city of Columbus. Subsequently, a jury trial commenced. The jury found appellants liable for appellees' claims of breach of contract, conversion and interference with a business relationship. In addition, the jury held Geiger personally liable for appellees' damages under the doctrine of piercing the corporate veil.

On October 15, 1999, the trial court held a hearing to determine whether appellants should be held in contempt for failure to comply with its June 15, 1999 specific performance order. After the hearing, the trial court found appellants in contempt. However, the trial court allowed appellants to purge the contempt by notifying the court when plans for the road, sewers and culvert were approved by the city of Columbus and by completing construction of the road and utilities by December 13, 1999. Because the road and utilities were not completed by the trial court's deadline, another contempt hearing was held on May 19, 2000. After the hearing, the trial court renewed its contempt finding and ordered Geiger to serve ten days in jail.

Appellants appeal, raising eighteen assignments of error:

I. The Trial Court erred in holding Appellant [sic] in contempt pursuant to the May 19, 2000 Hearing as a matter of both fact and law.

II. The Trial Court erred when it improperly denied (restricted) the testimony of Attorney Ben Hale who had specifically been engaged for the purpose of assisting the Court at the Contempt Hearing.

III. The Trial Court erred by wrongful reference and implication to Appellants being previously found in contempt.

IV. The Trial Court erred in not allowing Appellant [sic] to effectively cross-examine Appellees' main witness in the May 19, 2000 Contempt hearing.

V. The Trial Court erred in failing to grant Appellant's [sic] motion for contempt against Appellee [sic].

VI. The Trial Court erred when it gave the Jury Instruction regarding Conversion (Trial Transcript (TT) pages 927-929) because it instructed the jury to assume that Appellee's [sic] equipment was trapped on Appellee's [sic] property, thereby providing conclusions of fact to the jury and taking the burden of proving the "exercise of dominion and control over the property of another" element away from Appellee [sic]. As such, this instruction constituted Plain and Reversible Error.

VII. The Trial Court erred in allowing the jury to consider punitive damages because the Trial Court improperly tainted the jury on the issue of conversion by instructing the jury that the Defendants had "trapped" Plaintiffs' trucks and equipment.

VIII. The Trial Court erred by entering judgment for the Plaintiff [sic] for Punitive damages because when it gave the Jury Instruction regarding "Punitive Damages" (TT, pages 930-931) it improperly defined "Actual Malice" and there was insufficient evidence to go to the jury on this issue. As such, the Jury Instruction as given constituted Plain and Reversible Error.

IX. The Trial Court erred by entering judgment for the Plaintiff [sic] for Conversion because the jury verdict was against the manifest weight of the evidence presented at trial.

X. The Trial Court erred when it denied Appellant Steven Geiger's Motion to Dismiss and Motion for Directed Verdict as to claims against Steven Geiger individually on the theories of Alter Ego and Piercing the Corporate Veil, as Mr. Geiger was not a proper party to the lawsuit and no allegations regarding Alter Ego or Piercing the Corporate Veil were ever contained in the Complaint or the Amended Complaint.

XI. The Trial Court erred when it gave the Jury Instruction regarding Alter Ego (TT, pages 940-942) over Appellants' objection (TT, page 951) because that instruction failed to instruct the jury on the issue of Fraud, a requirement for the application of the Alter Ego Theory.

XII. The Trial Court erred when it allowed the jury to consider breach of contract where the evidence clearly established that no valid contract was in force relative to the January 23, 1998 closing, as a matter of law.

XIII.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zacchini v. Scripps-Howard Broadcasting Co.
433 U.S. 562 (Supreme Court, 1977)
Leichliter v. Nat'l City Bank of Columbus
729 N.E.2d 1285 (Ohio Court of Appeals, 1999)
Goldfarb v. the Robb Report, Inc.
655 N.E.2d 211 (Ohio Court of Appeals, 1995)
Nilavar v. Osborn
738 N.E.2d 1271 (Ohio Court of Appeals, 2000)
Cuyahoga County Hospitals v. Price
581 N.E.2d 1125 (Ohio Court of Appeals, 1989)
McGlothin v. Huffman
640 N.E.2d 598 (Ohio Court of Appeals, 1994)
BancOhio National Bank v. Schiesswohl
554 N.E.2d 1362 (Ohio Court of Appeals, 1988)
Leroux's Billyle Supper Club v. Ma
602 N.E.2d 685 (Ohio Court of Appeals, 1991)
Yoder v. Columbus & Southern Ohio Electric Co.
316 N.E.2d 477 (Ohio Court of Appeals, 1974)
Sanders v. Mt. Sinai Hospital
487 N.E.2d 588 (Ohio Court of Appeals, 1985)
Betz v. Timken Mercy Medical Center
644 N.E.2d 1058 (Ohio Court of Appeals, 1994)
Ohio Telephone Equipment & Sales, Inc. v. Hadler Realty Co.
493 N.E.2d 289 (Ohio Court of Appeals, 1985)
American Hardware Supply v. Alan Supply, Inc.
580 N.E.2d 473 (Ohio Court of Appeals, 1989)
Griffith v. Linton
721 N.E.2d 146 (Ohio Court of Appeals, 1998)
Ohio Historical Society v. General Maintenance & Engineering Co.
583 N.E.2d 340 (Ohio Court of Appeals, 1989)
White Co. v. Canton Transportation Co.
2 N.E.2d 501 (Ohio Supreme Court, 1936)
Gillespie v. Holland
3 Ohio App. 116 (Ohio Court of Appeals, 1914)
Rogers v. Standard Steel Castings Co.
16 Ohio App. 474 (Ohio Court of Appeals, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
Dalicandro v. Morrison Road Dev. Co., Unpublished Decision (4-17-2001), Counsel Stack Legal Research, https://law.counselstack.com/opinion/dalicandro-v-morrison-road-dev-co-unpublished-decision-4-17-2001-ohioctapp-2001.