Dale Luick, Doing Business as Luick Construction Company v. Graybar Electric Company, Inc., Graybar Electric Company, Inc., a Corporation v. National Surety Corporation

473 F.2d 1360
CourtCourt of Appeals for the Eighth Circuit
DecidedMarch 8, 1973
Docket72-1216
StatusPublished
Cited by15 cases

This text of 473 F.2d 1360 (Dale Luick, Doing Business as Luick Construction Company v. Graybar Electric Company, Inc., Graybar Electric Company, Inc., a Corporation v. National Surety Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dale Luick, Doing Business as Luick Construction Company v. Graybar Electric Company, Inc., Graybar Electric Company, Inc., a Corporation v. National Surety Corporation, 473 F.2d 1360 (8th Cir. 1973).

Opinion

473 F.2d 1360

12 UCC Rep.Serv. 99

Dale LUICK, doing business as Luick Construction Company,
Plaintiff-Appellant,
v.
GRAYBAR ELECTRIC COMPANY, INC., Defendant-Appellee.
GRAYBAR ELECTRIC COMPANY, INC., a corporation, Plaintiff-Appellee,
v.
NATIONAL SURETY CORPORATION, Defendant-Appellant.

Nos. 72-1216, 72-1217.

United States Court of Appeals,
Eighth Circuit.

Submitted Dec. 5, 1972.
Decided Feb. 13, 1973.
Rehearing Denied March 8, 1973.

Bruce E. Bohlman, Fargo, N. D., for appellants.

Michael L. Culhane, Minneapolis, Minn., for appellee.

Before MATTHES, Chief Judge, and GIBSON and HEANEY, Circuit Judges.

GIBSON, Circuit Judge.

This appeal concerns two separately filed actions, one in North Dakota and the other in Minnesota. The cases involve the same parties with the exception that the surety was sued in the Minnesota case. The Minnesota case subsequently was transferred to North Dakota and the cases although not consolidated were discussed together at a pretrial hearing and disposed of separately in a single unpublished memorandum by the late Judge George S. Register. They involve common questions of law and fact and will be considered together in this opinion. The cases concern an alleged breach of contract for late delivery of materials by a seller and the refusal of the buyer to pay for the unpaid balance due on the purchase.

In May 1968, Dale Luick, doing business as Luick Construction Company, contracted with Graybar Electric Company to purchase underground cable for $142,514 to be shipped the second week of July 1968 to Badger, Minnesota, for a job with Wickstrom Telephone Company. Graybar, unable to get delivery from its suppliers, did not deliver the cable to Luick in substantial amounts until November 1968. Luick, who was supposed to complete the Wickstrom installation by the end of 1968, did not complete the work until spring 1969.

In June 1969, Luick and Graybar again contracted for Graybar to sell $214,000 of cable to be delivered on or before August 1, 1969, to Underwood, Minnesota, for a job with Park Region Telephone Company, which was scheduled to be completed by the end of 1969. Graybar could not deliver the cable in substantial amounts until late October 1969. Luick completed the Park Region installation in spring 1970.

In October 1970, Luick filed suit in the North Dakota state court against Graybar for lost profits, the rental value of his idle equipment, and added construction costs for the Wickstrom and Park Region installations in the approximate amount of $230,000. On Graybar's motion, the case was removed to the Federal District Court of North Dakota.1 Graybar answered denying that it was liable for late delivery damages due to exculpatory clauses allegedly contained in contracts for both installations and counterclaimed for the value of the unpaid materials, $85,864.49. While Luick's suit was pending, Graybar filed suit against National Surety Corporation, Luick's bonding company, in Minnesota Federal District Court in December 1970 for the value of the unpaid materials and interest. National Surety answered alleging Luick's same claim for late delivery damages. This case was transferred to North Dakota on April 1, 1971.2

On July 23, 1971, Graybar, as plaintiff, moved for a summary judgment against National Surety in case No. 72-1217. On March 2, 1972, the District Court, in its unpublished memorandum and order, granted Graybar's motion for summary judgment and dismissed National Surety's counterclaim. On the same day and in the same order, the District Court, on its own motion, dismissed Luick's complaint (No. 72-1216) for failure to state a cause of action.

Since National Surety did not respond to Graybar's requests for admissions, the validity of Graybar's claim for materials furnished stands admitted. No real issue has been raised on the delivery or value of the materials furnished. Applying the summary judgment provision of Rule 56(c), Fed.R.Civ.P., the District Court found that there was "no genuine issue as to any material fact." In making this conclusion, the District Court found that National Surety did not respond to Graybar's requests for admissions under Fed.R.Civ.P. 36(a) and therefore admitted all matters contained in the requests. Graybar had requested that National Surety admit that the materials had been delivered for the Park Region job and that Luick owed $85,864.49, as a fair value for the delivered and unpaid materials. These requests were the basis of the Graybar complaint and its counterclaim in Luick's suit.

Unanswered requests for admissions render the matter requested conclusively established for the purpose of that suit. Fed.R.Civ.P. 36(a) and (b). See Moore's Fed.Prac. Sec. 36.01(7). Also a summary judgment may be based on admitted matter. Moosman v. Joseph P. Blitz, Inc., 358 F.2d 686, 688 (2d Cir. 1966). We agree with the District Court's determination on the contract amount owed by Luick to Graybar.

This leaves for consideration the question of whether the late delivery of the materials gave rise to an actionable claim for damages by Luick. We think Luick's suit for damages raises substantial factual issues that are not properly susceptible of determination in a summary judgment proceeding.

Graybar contends that an exculpatory clause3 in the alleged contracts exonerated Graybar from any liability for damages due to late delivery, and further that this exclusion-of-remedies clause is valid and enforceable under Minn.Stat.Ann. Sec. 336.2-719 (1965) (a provision of the Uniform Commercial Code in Minnesota).4 The District Court held that the exculpatory clauses in the alleged contracts were enforceable, that the late delivery damages were special or consequential under Minnesota law, and, therefore, that Graybar was not liable for the damages attributable to late delivery. This well may be but we don't think that conclusion can be reached in a summary judgment proceeding.

*****

* * *

The question of whether these exculpatory clauses are enforceable raises genuine factual issues, since Luick argues that there is a dispute whether these exculpatory clauses were included within the terms and conditions of the purchase contracts. The District Court assumed they were, and, again well they might be, as the exculpatory clauses are in each contract as No. 6 of the printed form on Terms and Conditions of Sale. However, Luick contends otherwise, and from the available record it is unclear exactly what written documents constituted the parties' contracts. In addition, Luick raises the issue of "unconscionability" of the exculpatory clauses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cruse v. Yates (In Re Yates)
429 B.R. 675 (E.D. Missouri, 2010)
American Petro, Inc. v. Shurtleff
159 F.R.D. 35 (D. Minnesota, 1994)
White Consolidated Industries, Inc. v. Waterhouse
158 F.R.D. 429 (D. Minnesota, 1994)
Goodnow v. Adelman (In Re Adelman)
90 B.R. 1012 (D. South Dakota, 1988)
Wibbels v. Unick
426 N.W.2d 244 (Nebraska Supreme Court, 1988)
Mattson v. Rochester Silo, Inc.
397 N.W.2d 909 (Court of Appeals of Minnesota, 1987)
Skaarer v. Fercho (In Re Fercho)
39 B.R. 764 (D. North Dakota, 1984)
Dingess-Rum Coal Co. v. Lewis
295 S.E.2d 25 (West Virginia Supreme Court, 1982)
Chess Music, Inc. v. Bowman
474 F. Supp. 184 (D. Nebraska, 1979)
Milwee v. Peachtree Cypress Investment Co.
510 F. Supp. 279 (E.D. Tennessee, 1977)
J. A. Jones Construction Co. v. City of Dover
372 A.2d 540 (Superior Court of Delaware, 1977)
Weva Oil Corp. v. Belco Petroleum Corp.
68 F.R.D. 663 (N.D. West Virginia, 1975)
George Saal v. Clarence Mielke
492 F.2d 1184 (Eighth Circuit, 1974)
Carlson Companies, Inc. v. Sperry & Hutchinson Co.
374 F. Supp. 1080 (D. Minnesota, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
473 F.2d 1360, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dale-luick-doing-business-as-luick-construction-company-v-graybar-ca8-1973.