Dahlgren v. Brooks

CourtNebraska Court of Appeals
DecidedNovember 28, 2017
DocketA-16-1215
StatusPublished

This text of Dahlgren v. Brooks (Dahlgren v. Brooks) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dahlgren v. Brooks, (Neb. Ct. App. 2017).

Opinion

IN THE NEBRASKA COURT OF APPEALS

MEMORANDUM OPINION AND JUDGMENT ON APPEAL (Memorandum Web Opinion)

DAHLGREN V. BROOKS

NOTICE: THIS OPINION IS NOT DESIGNATED FOR PERMANENT PUBLICATION AND MAY NOT BE CITED EXCEPT AS PROVIDED BY NEB. CT. R. APP. P. § 2-102(E).

GREGG DAHLGREN AND KRISTEN DAHLGREN, APPELLEES, V.

DENNIS BROOKS, DOING BUSINESS AS COBRA POOL AND SUPPLY ET AL., APPELLANT.

Filed November 28, 2017. No. A-16-1215.

Appeal from the District Court for Buffalo County: JOHN H. MARSH, Judge. Affirmed. Mitchell C. Stehlik, of Lauritsen, Brownell, Brostrom, & Stehlik, P.C., L.L.O., for appellant. Kane M. Ramsey, of Jacobsen, Orr, Lindstrom & Holbrook, P.C., L.L.O., for appellees.

MOORE, Chief Judge, and INBODY and BISHOP, Judges. MOORE, Chief Judge. INTRODUCTION Gregg Dahlgren and Kristen Dahlgren filed a complaint against Dennis Brooks for breach of contract and negligence stemming from the construction of a residential swimming pool and spa. Brooks filed a counterclaim against the Dahlgrens, alleging breach of contract or, in the alternative, unjust enrichment. The district court for Buffalo County found for the Dahlgrens, awarding them $40,770.02 in damages. On appeal, Brooks alleges the district court erred in entering judgment against him and for the Dahlgrens and in failing to entering judgment in Brooks’ favor on his counterclaim. He also alleges the court erred in its calculation of damages. For the reasons set forth below, we affirm.

-1- BACKGROUND In the spring of 2014, the Dahlgrens made arrangements to install an underground pool and spa in their backyard to enjoy that summer. Because Brooks recently installed a pool in their neighborhood, the Dahlgrens contacted him about the costs, feasibility, and completion date of the project. Brooks met with the Dahlgrens at their home in April 2014 at which time they indicated their desire for a pool and spa and where they wanted it located in their backyard. Dahlgrens wanted the pool and spa to be installed in time to be used for the summer of 2014 and discussed the feasibility with Brooks. After Brooks inspected the Dahlgrens’ property, the Dahlgrens contracted with Brooks to install a pool and a spa in their backyard. The contract set forth the cost of the pool and spa, together with various other items such as heat pump, lights, power cover, and spa heater. The “complete installation” included “[e]xcavation and installation of the pool [and spa], plumbing, pump, filter, and manual cleaning equipment. Prices are based on a level lot, easy access, and pre-site approval.” The contract price was $79,309. The contract expressly excluded costs associated with “decking & cement, stone, brick, etc.; landscaping; crane; sewer connection; permits, taxes, & fees; and electrical hookups.” Brooks required the Dahlgrens to pay the contract in three installments. The Dahlgrens made three payments to Brooks: (1) $28,000 on April 24, 2014, (2) $26,436.33 on May 19, 2014, and (3) $26,436 on June 9, 2014. In total, the Dahlgrens paid Brooks $80,872.33, which was $1,566.33 above the contracted amount. In early May of 2014, Brooks began construction. When asked “Can you remind me when Mr. Brooks identified the pool and spa would be completed,” Gregg replied “We were anticipating early June the pool was to be completed.” During Brooks’ initial construction, he questioned the Dahlgrens about the “elevation” of their pool. Gregg and Kristen asked Brooks to refer his questions about the project to Kristen’s father, Gene McElhinney, a general contractor with over forty-two years of experience in construction. When Brooks initially set the pool’s fiberglass shell in the ground, its edge sat above the ground at about knee level, which Gregg found unacceptable. Gregg testified that he directed Brooks to lower the shell further into the ground. Brooks testified he lowered the pool at McElhinney’s instruction only after McElhinney agreed that the Dahlgrens would pay the additional costs. McElhinney denied he discussed additional costs with Brooks. By the end of May--when the Dahlgrens and Brooks had initially planned the project to be nearing completion--Brooks and his employees had set the pool in the ground, but they had not yet stabilized and backfilled dirt around its walls. Prior to completing this work, Brooks left the country for vacation. During his absence, a heavy rain fell. Because Brooks’ crew did not stabilize the pool, the rain caused the fiberglass shell to float more than six feet above the hole in which it sat. The standing water in the hole required Brooks to hire a crane to lift the fiberglass shell and allow both the hole and the shell to dry. At some point after the free-floating shell required Brooks’ to hire a crane, Gregg asked Brooks to rotate the fiberglass shell so that the pool would face the opposite direction. Gregg testified that Brooks agreed to rotate the fiberglass shell, adding the change in orientation would make the project’s plumbing easier to complete and that the additional digging would not be a “big deal.” According to Gregg, Brooks did not indicate that there would be additional costs associated with rotating the pool. However, Brooks testified that he rotated the

-2- pool at McElhinney’s instruction only after he agreed to the additional costs. McElhinney could not recall such a discussion. After another rain fell just over two weeks later, the Dahlgrens again found a free-floating fiberglass shell in the pool hole. The saturated shell again required Brooks to hire a crane to dry the shell and hole. By the end of June 2014, Brooks had installed the fiberglass pool shell, spa vessel, and most of the plumbing. However, the project was still not complete. Brooks did no additional work on the project for the remainder of the summer, other than collecting his tools and retrieving a pool filter. On July 21, 2014, Brooks sent the Dahlgrens an invoice for his services in rotating and lowering the pool. A little over a week later, Gregg called Brooks to ask if he planned to finish the pool and spa. Brooks replied by demanding payment from Gregg on the July invoice. According to Brooks, Gregg notified him that he did not believe he owed Brooks for the additional work but that if Brooks would get the pool done, Gregg would think about paying the invoice. Brooks informed Gregg that he would not do further work until the Dahlgrens paid the invoice. The Dahlgrens did not pay the additional invoice, and Brooks did not complete the project and failed to deliver the pool cover for which he billed the Dahlgrens. At the time that Brooks’ work on the pool and spa installation ceased, the Dahlgrens could not use the pool and the spa’s jets did not work properly. The Dahlgrens hired Artisan Pools to complete the pool installation. Artisan charged the Dahlgrens $2,848.56 to purchase and install various items necessary for the operation of the pool. In addition, Artisan Pools charged Brooks $3,000 for a pool cover. Artisan did not alter any of Brooks’ construction and plumbing, and it did not address the spa jets’ deficiencies. The Dahlgrens hired Douglas Deterding, a pool and spa installation expert, to assess the situation with the spa. Deterding identified that there was not enough flow in the system to allow the jets to work properly. He testified that the number of right angles Brooks constructed in the spa’s plumbing would not allow an effective spa circulation system. Deterding additionally found that the piping was incompatible with the pump model for the spa vessel Brooks installed. He testified the only way to fix the plumbing and piping for the spa would be to dig out the shell and to install a proper pump. Deterding indicated that depending on what he found when the Dahlgrens removed the existing spa vessel, the “worst-case scenario” would require complete installation of a new spa.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nebraska Nutrients, Inc. v. Shepherd
626 N.W.2d 472 (Nebraska Supreme Court, 2001)
Schwarz v. PLATTE VALLEY EXTERMINATING, INC.
606 N.W.2d 85 (Nebraska Supreme Court, 2000)
Stauffer v. Benson
288 Neb. 683 (Nebraska Supreme Court, 2014)
Funk v. Lincoln-Lancaster Cty. Crime Stoppers
885 N.W.2d 1 (Nebraska Supreme Court, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Dahlgren v. Brooks, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dahlgren-v-brooks-nebctapp-2017.