D. Wilson Construction Co. v. Cris Equipment Co.

988 S.W.2d 388, 1999 WL 178725
CourtCourt of Appeals of Texas
DecidedApril 8, 1999
Docket13-98-373-CV, 13-98-439-CV
StatusPublished
Cited by34 cases

This text of 988 S.W.2d 388 (D. Wilson Construction Co. v. Cris Equipment Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D. Wilson Construction Co. v. Cris Equipment Co., 988 S.W.2d 388, 1999 WL 178725 (Tex. Ct. App. 1999).

Opinion

OPINION ON MOTION FOR REHEARING

Opinion by

Justice HINOJOSA.

We issued our original opinion in these cases on December 30,1998. Appellant/rela *391 tor, D. Wilson Construction Company (“Wilson”), subsequently filed motions for rehearing. We deny Wilson’s motion for rehearing in Cause No. 13-98-439-CV. We grant Wilson’s motion for rehearing in Cause No. 13-98-373-CV, withdraw our opinion of December 30, 1998, and substitute the following as the opinion of the Court.

Wilson filed both of these cases after the trial court denied its motion to compel appel-lee/real party-in-interest, Cris Equipment Company, Inc. (“Cris”), to submit all claims to arbitration. In the interlocutory appeal (No. 13-98-373-CV) Wilson asserts arbitration is mandatory under the Texas General Arbitration Act (TGAA). 1 In the petition for writ of mandamus (No. 13-98-439-CV) Wilson contends arbitration is also mandatory under the Federal Arbitration Act (FAA). 2

We deny Wilson’s petition for writ of mandamus. In the interlocutory appeal, we reverse the trial court’s order and remand the case to the trial court with orders to abate the underlying suit and to compel Cris Equipment Company, Inc. to submit all claims against D. Wilson Construction Co. to arbitration.

A. BACKGROUND AND PROCEDURAL HISTORY

Wilson, a general contractor, performed work on a project for the McAllen Independent School District (“School District”) in McAllen, Texas. The work was substantially completed in October 1990. Shortly thereafter, the School District found deficiencies and attempted to resolve them with Wilson. When the parties 1 were unable to reach a resolution, the School District filed suit against Wilson and others. Wilson then moved to compel arbitration which the trial court denied. In an interlocutory appeal from the denial, this Court found the trial court erred and ordered the trial court to compel arbitration. See D. Wilson Constr. Co., Inc. v. McAllen Indep. Sch. Dist., 848 S.W.2d 226, 232 (Tex.App.—Corpus Christi 1992, writ dism’d w.o.j.). The parties subsequently settled the dispute for $2,150,000. Wilson then demanded that Cris indemnify it for the amount of the settlement agreement in accordance with the terms of a subcontract. Wilson also demanded that the matter be submitted to arbitration as required by the subcontract.

Wilson’s claim arises from a February 1989 subcontract between Wilson and Cris in which Cris agreed to provide the fill dirt for the School District project in exchange for a payment of $212,000. The subcontract specifies:

[t]he Contract Documents for the Subcontract consist of this Agreement and any Exhibits attached hereto, the Agreement between the Owner and Contractor dated as of January 27, 1989, the Conditions of the Contract between the Owner and Contractor (General, Supplementary and other Conditions), the Drawings, the Specifications, all Addenda issued prior to and all Modifications issued after execution of the Agreement between the Owner and Contractor and agreed upon by the parties to the Subcontract. These form the Subcontract, and are as fully a part of the Subcontract as if attached to this Agreement or repeated herein.

The general conditions of the subcontract provide:

[a]ll claims, disputes and other matters in question arising out of, or relating to, this Subcontract, or the breach thereof, shall be decided by arbitration, which shall be conducted in the same manner and under the same procedures as provided in the Contract Documents with respect to disputes between the Owner and the Contractor. ...

The contract documents and the subcontract state that arbitration will be conducted according to the Construction Industry Arbitration Rules of the American Arbitration Association (“AAA”). The contract documents further specify that the contract will be governed by the law of the place where the project is located. Cris completed its contract obligations in April 1990.

In 1994, while Wilson and the School District were arbitrating and settling their dis *392 pute, bores of the fill dirt used in the project were tested. Results indicated the fill dirt did not satisfy contract specifications. By letter dated January 23,1995, Wilson notified Cris of the dispute and the arbitration proceedings with the School District. Although Cris was invited to lend its assistance in resolving the dispute, nothing in the record indicates that Cris responded to the invitation. In fact, Cris now contends it was not allowed to participate in the arbitration as required by the subcontract. After Wilson and the School District settled their dispute, Wilson sought to arbitrate the indemnity issue.

Wilson served its demand for arbitration on the AAA and Cris on May 18, 1995. The AAA accepted the case for arbitration, Cris responded, and three arbitrators were appointed. A preliminary hearing was held in November 1995 to establish document exchanges and discovery guidelines. A final hearing was set for June 1996, but postponed at Cris’s request for voluntary mediation. When the parties could not mediate their differences, a final hearing was set for the week of March 3,1997.

On or about February 25,1997, Cris filed a Petition for Declaratory Judgment and to Enjoin Arbitration and Request for Temporary Restraining Order in a district court in Harris County. Cris claimed that arbitration was not mandated because (1) Wilson did not sign the subcontract, (2) the demand for arbitration was not timely, (3) the indemnity provision was unenforceable, (4) limitations barred Wilson’s claim, and (5) Wilson had no legally cognizable claim. The case was transferred to Hidalgo County on May 30, 1997, by consent of the parties. Wilson filed its Plea in Abatement and Motion to Compel Mandatory Arbitration. After a hearing, the trial court denied the plea and the motion. Wilson then filed this interlocutory appeal and petition for writ of mandamus.

B. Mandamus OR InterlocutoRY Appeal

The TGAA allows Wilson an interlocutory appeal in Texas Courts from the denial of a motion to compel arbitration. See D. Wilson Constr. Co., 848 S.W.2d at 228. The FAA does not provide for an interlocutory appeal in state courts from the denial of a motion to compel arbitration. Id; see Jack B. Anglin Co. v. Tipps, 842 S.W.2d 266, 271-73 (Tex.1992). As Wilson has done, a party challenging an order denying arbitration under the FAA must seek a writ of mandamus. See D. Wilson Constr. Co., 848 S.W.2d at 228.

Thus, our first task is to determine which law applies to the contract at issue. Because the parties agreed the laws of Texas govern the contract, ie., the laws of the place where the project is located, we hold the TGAA applies, 3 see Volt Info. Sciences v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MONY Securities Corp. v. Padilla
132 S.W.3d 201 (Court of Appeals of Texas, 2004)
in Re: Peterson Construction Inc.
Court of Appeals of Texas, 2003
Perlstein v. D. Steller 3, Ltd.
109 S.W.3d 36 (Court of Appeals of Texas, 2003)
Fred Perlstein v. D. Steller 3, Ltd.
Court of Appeals of Texas, 2003
In Re Kellogg Brown & Root
80 S.W.3d 611 (Court of Appeals of Texas, 2002)
Labor Ready Central III, L.P. v. Gonzalez
64 S.W.3d 519 (Court of Appeals of Texas, 2002)
J.M. Davidson, Inc. v. Webster
49 S.W.3d 507 (Court of Appeals of Texas, 2001)
J.M. Davidson, Inc. v. Chelsey Webster
Court of Appeals of Texas, 2001
In Re Valle Redondo, SA
47 S.W.3d 655 (Court of Appeals of Texas, 2001)
In Re Van Blarcum
19 S.W.3d 484 (Court of Appeals of Texas, 2000)
In Re Conseco Finance Servicing Corp.
19 S.W.3d 562 (Court of Appeals of Texas, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
988 S.W.2d 388, 1999 WL 178725, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-wilson-construction-co-v-cris-equipment-co-texapp-1999.