D & M Painting Corp. v. City of Perrysburg

927 N.E.2d 60, 186 Ohio App. 3d 231
CourtOhio Court of Appeals
DecidedFebruary 12, 2010
DocketNo. WD-09-033
StatusPublished
Cited by1 cases

This text of 927 N.E.2d 60 (D & M Painting Corp. v. City of Perrysburg) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D & M Painting Corp. v. City of Perrysburg, 927 N.E.2d 60, 186 Ohio App. 3d 231 (Ohio Ct. App. 2010).

Opinion

Handwork, Judge.

{¶ 1} This case is before the court on appeal from the judgment of the Wood County Court of Common Pleas, which, on March 17, 2009, granted summary judgment in favor of appellee and cross-appellant, D & M Painting Corporation (“D & M”), against appellant and cross-appellee, the city of Perrysburg, in the amount of $31,756.50, plus interest. For the reasons that follow, we reverse the judgment of the trial court.

{¶ 2} On appeal, the city raises the following assignments of error:

{¶ 3} “1. The trial court erred in denying the city’s request for summary judgment and in failing to enforce the unambiguous terms of the parties’ settlement agreement.
[233]*233{¶ 4} “2. The trial court erred in granting plaintiffs request for summary-judgment and in relying on extrinsic evidence in the interpretation of the parties’ contract.
{¶ 5} “3. The trial court erred in granting plaintiffs request for summary judgment and in resolving a genuine issue of material fact on which the city had introduced evidence in support of its position.”

{¶ 6} In its cross-appeal, D & M raises the following assignments of error:

{¶ 7} “1. The trial court erred when it refused to award attorneys’ fees to cross-appellant/appellee.
{¶ 8} “2. The trial court erred when it refused to hold a hearing to determine if attorneys’ fees should have been awarded pursuant to R.C. 2323.51.”

{¶ 9} On June 21, 2006, the parties entered into a contract (“the contract”) whereby D & M was to paint and rehabilitate one of the city’s water towers. The original amount due D & M pursuant to the contract was $328,120; however, during the course of the contract period, the amount was reduced to $317,565. Eventually, a dispute arose between the parties regarding the city’s payment under the agreement and D & M’s performance of the work. On July 24, 2007, the parties entered into a settlement agreement and mutual release (“the agreement”) regarding their conflicts pursuant to the contract. The parties mutually released any claims they had against the other party concerning the contract. In particular, the settlement stated:

{¶ 10} “Entire Agreement
{¶ 11} “This Agreement constitutes the full and complete agreement between the Parties with respect to its subject matter. Except as otherwise expressly provided herein, this Agreement supersedes all prior agreements, understandings and discussions relating to the claims raised. There are no representations, agreements, arrangements, or understandings oral or written, concerning the subject matter hereof between the parties which are not fully expressed or incorporated by reference herein. This Agreement may be amended, modified or waived only by an agreement in writing signed by all parties.”

{¶ 12} The settlement terms were stated in their entirety as follows:

{¶ 13} “Consideration of the Parties
{¶ 14} “a. In consideration of the mutual promises set forth in this Agreement and the releases set forth in Paragraphs 1 and 2 above, the City will pay to D & M a one-time, lump sum payment in the amount of $30,000.00 in good funds as consideration for this Agreement and the resolution of the Dispute. This $30,000.00 does not include the retainage currently being held by the City.
[234]*234{¶ 15} “b. The Owner shall retain 5% of the contract bid price until after the eleventh month warranty inspection. Should the delivered materials and/or equipment and workmanship differ in any respect from the specifications, payment will be withheld until such time as supplier or Contractor takes necessary corrective action. If the proposed corrective action is not acceptable to the Owner, final acceptance of the equipment or work may be refused, in which case the nonconforming materials and/or equipment shall remain the property of the supplier, and the Owner shall not be liable for payment of any portion thereof. D & M and the City further agree that the anniversary testing for the subject water tank will be on or before November 30, 2007 and that all attempts will be made to move the anniversary testing to a date earlier than November 30, 2007.
{¶ 16} “e. The City, based upon the recommendation of Norman Noe, allegedly asserted liquidated damages against D & M on the Project for certain allegations regarding performance and time of performance. As additional consideration for this Agreement, the City has agreed to waive these asserted liquidated damages and the total sum of $30,000.00 will be paid to D & M in one lump sum as set forth above without any set-offs or deductions, which $30,000.00 does not include the current amount being held as retainage by the City.
{¶ 17} “d. It is specifically acknowledged that the above consideration and the discontinuance of D & M’s claims are sufficient consideration to induce the parties to enter into this Agreement and the parties accept such consideration in full and final settlement of the Dispute.”

{¶ 18} Despite the parties’ settlement, on April 9, 2008, D & M sued the city for $31,756.50, alleging breach of contract and unjust enrichment. Relying on correspondence dated December 26, 2006, prior to the date of the parties’ agreement, D & M claims that the city retained $31,756.50 from the original contract price and that this was the amount owed to D & M following the November 2007 warranty inspection of the water tank. The city, however, counterclaimed and sought a declaration that the amount owed D & M totaled $15,878.25, representing “5% of the contract bid price [of $317,565].”

{¶ 19} Each party filed a motion for summary judgment. In its March 17, 2009 judgment entry, the trial court noted that the parties agreed that the terms of the agreement are clear and unambiguous. Nevertheless, the trial court held that the amount due D & M following the warranty inspection was “the amount that was retained,” rather than five percent of the contract price. The trial court further held that introduction of correspondence outside of the agreement did not invoke the parol-evidence rule because “plaintiff is not attempting to introduce evidence that would vary the terms of the agreement, rather plaintiffs evidence is offered to show that the defendant retained 10% of the contract price instead of the 5% that is called for in the agreement.”

[235]*235{¶ 20} In reviewing a motion for summary judgment, we must conduct a de novo review and grant summary judgment only if there “is no genuine issue as to any material fact and * * * the moving party is entitled to judgment as a matter of law.” Civ.R. 56(C). This case concerns the effect of the terms of the settlement agreement entered into on July 24, 2007, between the parties.

{¶ 21} The construction of written contracts is a matter of law, and courts must give common words in a written instrument their plain and ordinary meaning “unless manifest absurdity results, or unless some other meaning is clearly evidenced from the face or overall contents of the instrument.” Alexander v. Buckeye Pipe Line Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zimmerman v. Bowe
2019 Ohio 2656 (Ohio Court of Appeals, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
927 N.E.2d 60, 186 Ohio App. 3d 231, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-m-painting-corp-v-city-of-perrysburg-ohioctapp-2010.