D & J Construction Co.v. Mid-Continent Stone Co.

571 So. 2d 762, 1990 La. App. LEXIS 2861, 1990 WL 194174
CourtLouisiana Court of Appeal
DecidedDecember 5, 1990
DocketNo. 22206-CW
StatusPublished
Cited by2 cases

This text of 571 So. 2d 762 (D & J Construction Co.v. Mid-Continent Stone Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D & J Construction Co.v. Mid-Continent Stone Co., 571 So. 2d 762, 1990 La. App. LEXIS 2861, 1990 WL 194174 (La. Ct. App. 1990).

Opinion

NORRIS, Judge.

Plaintiff, D & J Construction Company (D & J), filed suit against defendants, Dolphin Construction Company (Dolphin), Mid-Continent Stone Company, Inc. (Mid-Continent), and Fireman’s Fund Insurance Company (Fireman’s) on April 17, 1989; D & J sought an award of $12,188.83 plus interest against all three defendants in solido for materials and supplies transported and delivered to a construction site as a “for-hire carrier” employed by Mid-Continent. Dol[763]*763phin and Fireman’s filed separate peremptory exceptions of prescription of one year. La.R.S. 38:2247. By judgment signed May 14, 1990, the trial court overruled Fireman’s exception of prescription. The minutes indicate Dolphin’s exception of prescription was never taken up. On June 26, 1990 this court granted Fireman’s a supervisory writ. We make the writ peremptory, reverse the judgment of the trial court and dismiss D & J’s suit as to Fireman’s for the following reasons.

FACTS

On September 12, 1986 the Louisiana Department of Transportation and Development (the State) entered into a contract with Dolphin wherein Dolphin was to perform work and provide equipment, labor and materials for Project No. 451-06-80 entitled “Lincoln Parish Line — -Britton Road, Route 1-20” (6.144 miles of road construction for $10,456,993.41). R.p. 45. Dolphin, as principal and Fireman’s, as surety provided a contract bond for the full amount of the project. Mid-Continent was a subcontractor of Dolphin, and D & J was a subcontractor of Mid-Continent. On March 14,1988 the State recorded its notice of acceptance of completion of work on the project. D & J, claiming $12,188.83 in unpaid bills, recorded a public work claim (styled by the parties as a “lien”) on April 11, 1988 pursuant to La.R.S. 38:2242. On May 31, 1988 Dolphin (principal) and Fireman’s (surety) filed a release of claim bond (styled by the parties as a “release of lien bond”) pursuant to La.R.S. 9:4941 for $15,-236.1 The release of claim bond contains the following condition:

[T]his obligation is such that in the event the legality of claim or claims is established with suit or otherwise, the bond shall remain in full force and effect to protect the interest of the Claimant in the said proceedings, but should Claimant fail to bring suit to establish claim or take steps to preserve this lien, then this obligation shall become null and void. R.p. 53.

The instant suit by D & J on its recorded claim was not filed until April 17, 1989.

Fireman’s asserts that the trial court erred by overruling its exception of prescription. It argues that R.S. 38:2247 extinguishes claims against a contractor or its surety which arise under the Public Works Act (La.R.S. 38:2241, et seq.) if no suit has been filed therein within one year of recordation of acceptance of work. D & J counters that R.S. 38:2247 applies only to a suit to collect on a contract bond, not a suit to collect from a release of claim bond as in the instant case. It further argues that the release of claim bond was to guarantee that Fireman’s as surety would pay D & J pursuant to D & J’s contract with Mid-Continent; thus the claim should prescribe in ten years rather than one. La. C.C. art. 3499; R.S. 38:2247.

DISCUSSION

The Public Works Act establishes a procedure for a claimant to file with the governing authority a sworn statement of an amount due from a contractor or subcontractor and record it in the mortgage records of the parish where the work was performed. R.S. 38:2242. It also provides a 45-day time limitation for the claim to be filed after recordation of acceptance of work by the governing authority. R.S. 38:2242 B.2 Thereafter, if an awarding au[764]*764thority pays the contractor without deducting outstanding claims or obtaining a bond from the contractor to cover any outstanding claims, the awarding authority becomes liable for the claims. R.S. 38:2242 D. In the instant case the State recorded its notice of acceptance on March 14, 1988; D & J recorded its claim on April 11, 1988. Thus, the sworn statement of the amount due was timely recorded..

R.S. 38:2247 also provides a time limitation for filing a suit to enforce a claim:

Nothing in this Part shall be construed to deprive any claimant, as defined in this Part and who has complied with the notice and recordation requirements of R.S. 38:2242(B), of his right of action on the bond furnished pursuant to this Part, provided that said action must be brought against the surety or the contractor or both within one year from the registry of acceptance of the work * * * (emphasis added)

In Honeywell, Inc. v. Jimmy B. Guinn, Inc., 462 So.2d 145 (La.1985),3 subcontractor I had a contractual relationship with subcontractor II, but not with the general contractor. Subcontractor I filed suit under the Public Works Act against the general contractor and the surety on the contract bond more than one year after notice of acceptance was recorded by the governing authority. The Supreme Court ruled the action as to these parties was barred by the one-year prescriptive period of R.S. 38:2247. In the instant case, D & J had a contract with Mid-Continent (subcontractor), but not with Dolphin (general contractor). The State filed its notice of acceptance on March 14, 1988 and D & J did not file this suit until April 17, 1989, more than one year later. Thus, in accordance with the holding in Honeywell (and assuming compliance otherwise with R.S. 38:2247), D & J’s action has prescribed.

D & J, however, argues that the prescriptive period of R.S. 38:2247 does not apply in the instant case because its suit is based on a release of claim bond, R.S. 9:4941, rather than a contract bond, R.S. 38:2247. R.S. 9:4941 states:

When any contractor shall have entered into a contract to perform public works under the laws of this state governing the letting and awarding of such contracts and in conformity with the requirements thereof, the contractor shall have the right to bond any claim or claims which may be filed or recorded against said work by depositing with the clerk of court of the parish in which such claims are filed or recorded a bond with surety signed by any surety company authorized to do business in the state for an amount equal to the claim plus one-fourth. The bond shall be approved by the clerk of court conditioned that in the event the legality of such claim or claims is established by suit or otherwise, the bond shall remain in full force and effect to protect the interest of the claimant in the premises.4 (emphasis added)

In Brunet v. Justice, 264 So.2d 743 (La.App. 4th Cir.), writ denied 262 La. 1178, 266 So.2d 451 (1972) a release of lien (claim) bond was furnished in compliance with La. R.S. 9:4841 of the Private Works Act. The defendant argued that the in rem liability of the owner’s property becomes, by “legislative novation,” the personal liability of the bond’s principal and surety subject to a ten-year general contract prescription rather than the one-year prescription provided by the Private Works Act. La.C.C. art. 3544 (1870).5 The Brunet

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gootee Construction, Inc. v. Atkins
178 So. 3d 629 (Louisiana Court of Appeal, 2015)
LeBlanc & Theriot Equipment Co. v. H & S Construction Co.
591 So. 2d 1274 (Louisiana Court of Appeal, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
571 So. 2d 762, 1990 La. App. LEXIS 2861, 1990 WL 194174, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-j-construction-cov-mid-continent-stone-co-lactapp-1990.