D. E. Fryer & Co. v. Thompson

127 P.2d 408, 14 Wash. 2d 141
CourtWashington Supreme Court
DecidedJuly 6, 1942
DocketNo. 28458.
StatusPublished
Cited by2 cases

This text of 127 P.2d 408 (D. E. Fryer & Co. v. Thompson) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D. E. Fryer & Co. v. Thompson, 127 P.2d 408, 14 Wash. 2d 141 (Wash. 1942).

Opinion

Driver, J.

On December 21, 1939, plaintiff corporation recovered judgment against defendants, *142 George L. Thompson and wife, in the amount of $333.47, plus interest at the rate of six per cent per annum from August 8, 1938, and costs of $19.50. A writ of garnishment issued on this judgment, directed to F. W. Erikson, was served upon him January 17, 1940. The garnishee defendant, in his answer served on February 6, alleged:

“That prior to said 17 day of January, 1940, this garnishee defendant entered into a contract with the said defendant, George L. Thompson, whereby the said defendant was to construct upon the property owned by this garnishee defendant a residence and furnish all labor and material therefor, as in said contract set forth, for the contract price of $7639; that by said contract this garnishee defendant was to withhold sufficient moneys to see that all labor and materials were paid; that said residence is nearing completion; that prior to the 17 day of January, 1940, this garnishee defendant had paid to the defendant, George L. Thompson, the full sum of $6209.00 for and on behalf of said contract, leaving a balance in the sum of $1430.00; that on said date, to-wit: the 17 day of January, 1940, the said defendant, as such contractor, had incurred bills for materials and labor for and .on account of said residence and such contract in a sum in excess of $1600.00 in addition to that previously incurred and paid for and for which this garnishee defendant is responsible and liable, and in the event that this garnishee defendant fails to make such payments for such labor and materials so furnished then the creditors thereof will have a lien upon the property of this garnishee defendant for such amounts and by reason thereof this garnishee defendant is not now and was not on the 17 day of January, 1940, indebted to the said George L. Thompson or Pauline Thompson, his wife, or either of them, in any amount whatsoever, ...”

The plaintiff controverted the answer, and a trial before the court resulted in findings of fact, conclusions of law, and judgment in its favor. The garnishee defendant has appealed.

*143 All of the witnesses who testified to facts material on this appeal were called by the appellant, and there is no substantial conflict in the testimony. The facts, as disclosed by the record, and found by the trial court, essential to determination of the questions presented here, may be summarized as follows:

On September 21, 1939, Mr. Thompson, defendant husband below, contracted to furnish all the necessary materials and labor and construct a dwelling house for appellant. By the terms of the agreement, the contractor was to be paid, as the work progressed., eighty-five per cent of the total amount of receipted bills in his possession on the first day of each month, the retained percentage to be paid “30 days after completion and acceptance of the job by the owner.”' The contract further provided that,

“Upon receipt of written notice that the work is ready for final inspection and acceptance, the owner shall promptly make such inspection, and when he finds the work acceptable under the Contract and the Contract fully performed he shall promptly issue a final certificate, over his own signature, stating that the work provided for in this Contract has been completed and is accepted by him under the terms and conditions thereof, and that the entire balance found to be due the Contractor, and noted in said final certificate, is due and payable.
“Before issuance of final certificate the Contractor shall submit evidence satisfactory to the owner that all payrolls, material bills, and other indebtedness connected with the work have been paid.”

The work was commenced in September, 1939, and, by January 1, 1940, was approximately seventy-five per cent completed. Appellant did not make any payments on the contract direct to Mr. Thompson after January 12th. By that time, the contractor was in such financial straits that he could no longer pay for labor and materials furnished for the construction of the *144 building, and thereafter, as bills were presented to him, he referred the claimants to appellant.

At the time of the service of the writ of garnishment, appellant had paid the contractor about $6,200, leaving approximately $1,440 of the contract price unpaid. Thereafter, appellant paid claims for which liens had been filed against his property in the aggregate amount of $612.86; but, prior to the service of- his answer, he also paid certain materialmen $531, for which no liens had been filed and for which no valid liens could have been filed for the reason that each of such materialmen had failed to give the owner notice in writing of the furnishing of materials to the contractor within five days after the first delivery thereof, as required by Rem. Rev. Stat., § 1133 [P. C. § 9706]. All of the bills for these materials were approved by the contractor, and, at his request, were paid by the appellant and charged to the contractor’s account. Appellant moved into the house about the first of March, 1940. At the time of the trial, the work was fully completed with the exception of some minor items of interior finish, which would cost, the contractor testified, “$25 or $30, in the neighborhood of that.”

It is appellant’s contention that, since his liability to the contractor was contingent on the future performance of the building contract, such liability was not subject to garnishment under the rule, as stated in 4 Am. Jur. 682, § 200:

“ . . . where a further performance of a contract is necessary before the money payable thereon becomes due, the view is generally taken that the payment is conditioned on the performance, and is not subiect to garnishment until the condition has been fulfilled.”

It is not necessary for us to decide whether or not the rule 'would have been applicable in the instant *145 case if the appellant had not, after service of the writ and prior to service of his answer, voluntarily paid nonlienable claims of the creditors of the contractor, totaling more than the amount of respondent’s judgment, as we think that, having done so, he is not in a position to invoke the rule.

Manifestly, it was not necessary for appellant to pay such claims to protect his property from lien encumbrances, and there was no provision in his contract authorizing him to pay the contractor’s common creditors for materials furnished in the construction of the building. Under the above-quoted provision of the contract, appellant was not required to issue the final certificate and pay the retained percentage of the contract price until the contractor had submitted satisfactory evidence that material bills and other indebtedness connected with the work, whether lienable or not, had been paid; but appellant waived that provision of the contract by making the payments in question. Furthermore, in so far as the determination his liability under the writ of garnishment is concerned, he thereby, in effect, acknowledged his indebtedness to the contractor (defendant). Rem. Rev. Stat. (Sup.), § 688 [P. C. § 8007]; Lemagie v. Acme Stamp Works, 98 Wash. 34, 167 Pac. 60; Miller v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Allen
207 F. Supp. 545 (E.D. Washington, 1962)
B-LINE TRANSPORT CO., INC. v. Poitevin
369 P.2d 310 (Washington Supreme Court, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
127 P.2d 408, 14 Wash. 2d 141, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-e-fryer-co-v-thompson-wash-1942.