D. C. Federation of Civic Associations v. Adams

571 F.2d 1310, 11 ERC 1461
CourtCourt of Appeals for the Fourth Circuit
DecidedMarch 14, 1978
DocketNos. 77-2060 and 77-2076
StatusPublished
Cited by8 cases

This text of 571 F.2d 1310 (D. C. Federation of Civic Associations v. Adams) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D. C. Federation of Civic Associations v. Adams, 571 F.2d 1310, 11 ERC 1461 (4th Cir. 1978).

Opinion

HAYNSWORTH, Chief Judge:

The proposal to build Interstate-66, in particular, the segment running from the Capital Beltway to a connection with the Theodore Roosevelt Bridge, has spawned substantial controversy and litigation. This court enjoined construction of one 1-66 proposal in 1972 because the Secretary of Transportation had not complied with the applicable environmental protection statutes.1 Since that time, the proposals for building 1-66 have been modified substantially in response to the changing transportation plans and needs of the Northern Virginia-Washington, D. C. area2 and the criticisms of the Secretary of Transportation.3 [1312]*1312A new citizen’s group was formed to oppose the most recent incarnation of 1-66, and it initiated this round of litigation.

The district court found that the Secretary of Transportation had complied with all of the applicable environmental protection statutes in approving the final 1-66 proposal. We affirm that holding, for substantially the same reasons as were given by the district court. The context in which several of the plaintiffs’ arguments are advanced, however, justifies an explanation of the basis of our decision.

The plaintiffs’ major argument on appeal is that the Secretary of Transportation failed to comply with the procedural requirements of Section 102(2)(C) of the National Environmental Policy Act, 42 U.S. C.A. § 4332(2)(C), Section 109 of the Federal-Aid Highway Act, 23 U.S.C.A. § 109, Section 4(f) of the Department of Transportation Act, 49 U.S.C.A. § 1653(f), and Section 138 of the Federal-Aid Highway Act, 23 U.S.C.A. § 138.

The first, and most important, defect alleged by the plaintiffs is that while the Secretary approved the final 1-66 proposal because of the virtues of the combination of 1-66 and the Metro K line, the Environmental Impact Statement failed to discuss the possibility that the Metro K line would never be constructed between Vienna, Virginia and Glebe Road. We think the EIS and the Secretary adequately considered the possibility suggested by the plaintiffs, given the reasonableness of that possibility at the time of the decisions and statements by the agencies involved.

The district court found that the Supplemental EIS did mention the possibility that buses would operate in the 1-66 median, rather than the Metro K line. This fact implieitly indicates some consideration of the possibility that the Metro K line would not be completed, even though all planners believed then that the Metro K line would be built as planned. Only after the Final Supplemental Environmental Impact Statement was filed on August 10, 1976, did the events listed by the plaintiffs create any doubt about the future of the Metro K line. Although the Federal Highway Administration (FHWA) could have modified the EIS in light of these developments before approving the EIS on December 20, 1976, the FHWA was aware of those developments and legitimately could have concluded that the possibility that the Metro K line would be abandoned, as opposed to merely delayed, was not sufficiently likely, or reasonable, to merit further discussion in the EIS. Secretary Coleman’s decision approving the 1-66 proposal, after the FHWA approved the EIS, indicates that he, too, was very aware of the developments that threatened the completion of the Metro K line. Yet the Secretary’s decision also clearly indicates that he believed the Metro K line would be completed, even if later than originally planned, and the Secretary approved the 1-66 proposal on the basis of that belief.4

The consideration given to the possibility that the Metro K line would not be completed between Vienna and Glebe Road satisfies the purposes of NEPA’s procedural requirement. An EIS must discuss reasonable alternatives and issues in order to inform the public and to guarantee that the planners consider relevant alternatives and issues before such substantial inertia develops that a proposal cannot be rejected or reevaluated. The record in this case demonstrates that both the public and the planners knew of [1313]*1313and considered the questions concerning the future of Metro, as those questions developed. NEPA did not require the Secretary of Transportation to delay approving 1-66 until the Transit Authority finally resolved the questions about the Metro K line,5 especially when the proposal approved by Secretary Coleman was intended to facilitate construction of the rail line in issue. At some point, construction plans must become final. In this case, the plans were all but final when the possibility complained of first developed. Given the defendants’ consideration and treatment of that possibility, and the fact that even the plaintiffs do not contend that the approval of the EIS or the 1-66 proposal were “arbitrary and capricious,” we conclude that the EIS here satisfied the procedural requirements of the environmental protection statutes.6

The plaintiffs also allege that the EIS is procedurally deficient in another respect, because the EIS failed to discuss in sufficient detail four alternatives that the plaintiffs consider to be reasonable substitutes for the 1-66 proposal. To the extent that these alternatives were reasonable means for obtaining the benefits of the 1-66 proposal, we conclude that the EIS discussed those alternatives in sufficient detail. See Coalition for Responsible Regional Development v. Coleman, 555 F.2d 398 (4th Cir. 1977); Fayetteville Area Chamber of Commerce v. Volpe, 515 F.2d 1021 (4th Cir. 1975), cert. denied, 423 U.S. 912, 96 S.Ct. 216, 46 L.Ed.2d 140 (1976).

The third procedural defect alleged by the plaintiffs is the reliance in the EIS on projections that the plaintiffs contend are arbitrary and biased. The district court found that the projections of carpool formation were prepared by experts in the field of traffic forecasting, using accepted methodologies. The plaintiffs’ own witnesses admitted that they could not provide more reliable projections of carpool formation. Blind reliance on the projections of the impact of 1-66 on the use of the Metro K line would have been less defensible, but better data for these projections were not available, and the FHWA addendum to the EIS and Secretary Coleman adequately considered the problems with these projections. Under these circumstances, we conclude that the EIS provided an adequate record for the concerned planners to make an informed decision.7

In addition to the procedural arguments based on the aforementioned statutes, the plaintiffs contend that Secretary Coleman did not comply with the National Historic Preservation Act (NHPA), 16 U.S. C.A. § 470f, and the implementing regulations of the Advisory Council on Historic Preservation. While we do not condone what may be a failure to adhere literally to the Advisory Council’s regulations,8 we do conclude that any possible deviation from the proper procedures, under the circumstances of this ease, did not justify injunctive relief.

The NHPA obligated the Secretary to “take into account the effect” of the 1-66 proposal on properties included in the National Register.9

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
571 F.2d 1310, 11 ERC 1461, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-c-federation-of-civic-associations-v-adams-ca4-1978.