Cuthbertson v. Harry C. Harter Post No. 839 of Veterans of Foreign Wars of the United States

65 N.W.2d 83, 245 Iowa 922, 1954 Iowa Sup. LEXIS 411
CourtSupreme Court of Iowa
DecidedJune 15, 1954
Docket48476
StatusPublished
Cited by15 cases

This text of 65 N.W.2d 83 (Cuthbertson v. Harry C. Harter Post No. 839 of Veterans of Foreign Wars of the United States) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cuthbertson v. Harry C. Harter Post No. 839 of Veterans of Foreign Wars of the United States, 65 N.W.2d 83, 245 Iowa 922, 1954 Iowa Sup. LEXIS 411 (iowa 1954).

Opinion

Wennerstrum, J.

— Plaintiff sought judgment on a claimed oral contract entered into with representatives of the defendant-organization. He claims as a result of this agreement he is entitled to ten per cent compensation based on the gross expenditures made in remodeling a building owned by the defendant. He also sought the confirming and establishing of a mechanic’s lien against the building for the amount of his claim. In his original petition filed he sought an accounting, a judgment for the amount due with interest from and after March 15, 1947, and a foreclosure of a mechanic’s lien. However, such a lien claiming $7177.89 was not filed until September 12, 1951. A copy of it was attached to an amended and substituted petition filed on September 15, 1951. The trial court found generally for the plaintiff but held his claim had been barred by the statute of limitations (section 614.1(9), 1950 Code) .and dismissed his petition. He has appealed.

The filing of several amendments to plaintiff’s petition with resulting counterpleadings on the part of the defendant, plaintiff’s application to reopen the case after its original submission, and defendant’s resistance thereto, the granting of the right *924 to reopen with the consequent change of pleadings, and the introduction of additional evidence have developed an involved situation.

Plaintiff is a general contractor and builder. The defendant is a corporation and is organized as Harry C. Harter Post-No. 839, of the Veterans of Foreign Wars. Early in the year 1945 the plaintiff was employed by representatives of the defendant-corporation by oral contract to draw plans for the remodeling of a business building owned by the Post and formerly used as a garage and to personally work on it and to supervise the remodeling work. The defendant-organization proposed to convert the building into clubrooms for its members. As shown by the plaintiff’s original petition and amendments thereto and later supporting evidence he was to be paid the regular wage of a carpenter based upon the number of hours he worked, and in addition he was to receive on completion of the work .a further sum equal to ten per cent of the cost of all labor and materials for his services as architect and general supervisor of the improvements. There was excepted from the agreement the cost of labor and materials in connection with the electrical work, plumbing and the installation of an air conditioning unit.

The work was commenced in 1945 and dedicatory ceremonies were held in 1946. Plaintiff in his testimony during the original submission testified the work for which he claimed a ten per cent compensation was completed in March 1947. However, it is plaintiff’s claim as shown by his amendment to the original petition there was additional work done at the request of the defendant during the years 1948 and 1949 by reason of the changing of a card room from the second floor to the first floor. There is ample showing, upon which the court could and apparently did find, the total cost of the improvements, including the items for work done in 1948 and 1949, amounted to $65,-184.50. This amount is based in part upon the testimony of Glen Warden, an auditor. The court found there was due plaintiff, according to the contract, the sum of $6518.45.

Inasmuch as this action must be determined on the basis of the plaintiff’s original petition as well as his several amend *925 ments we should give consideration to his respective claims. This is particularly true in the light of the present claim of the defendant that the plaintiff’s action is barred by the statute of limitations previously mentioned. It is repeatedly asserted in the original petition and the amendments thereto that the plaintiff’s claim for compensation was for his services rendered and that he was to be paid a regular wage of a carpenter and was also to receive a further sum of ten per cent of the cost of the labor and materials that went into the improvements for his supervisory services. In plaintiff’s original testimony he stated, “* * * I was to furnish my contracting equipment and the 10% was to be my commission over and above regular wages as a carpenter * *

The record disclosed he was paid on March 15, 1947, and April 15,1947, for work done through these dates as a carpenter. It is also shown that he was paid about April 24, 1948, and March 4, 1949, for carpenter work. There is testimony of other witnesses concerning these several payments. It is thus shown that plaintiff has been paid wages for all the carpenter work he did.

It is of interest to note the trial commenced on April 14, 1952, and was originally submitted April 17, 1952. On April 26, 1952, plaintiff filed a motion to reopen the case for further testimony. The defendant filed a resistance to the motion and later an amendment thereto. Plaintiff thereafter filed an amendment to his motion to reopen the case. The court sustained plaintiff’s motion to reopen the case and set aside the original submission. On April 17, 1953, plaintiff filed an amendment to his amended and substituted petition. A motion to strike this last amendment was submitted and overruled and on April 21 and 22, 1953, additional evidence was introduced. The cause was again submitted on the last named date.

•Apparently as the result of arguments presented at the time of the original submission the later proceeding developed. Plaintiff testified at the time the case was reopened concerning the work for which the checks were given him on April 24, 1948, and March 4, 1949. There was also testimony of other witnesses relative to the changes for which plaintiff was compensated.

*926 As hereinafter noted one of the grounds for reversal is the claim the statute of limitations was not properly pleaded. In this connection it should be noted the defendant in its original answer stated, “* * * that plaintiff’s petition upon its face fails to state a cause of action * * And in its answer to the amended and substituted petition defendant pleaded “* * " that the purported mechanic’s lien * * * is no proper or lawful lien and without any force and effect * * And the defendant in an amendment to its answer which was filed on April 4, 1952, further stated “* * * and while admitting that the plaintiff did certain work on its building, which was completed on the 15th day of March, 1947 as alleged * * * the plaintiff commenced the instant cause of action on November 3, 1950, but plaintiff has failed to state any cause of or for .action and any such claimed contract or mechanic’s lien is invalid, without force or effect, and void and the plaintiff is barred from recovery therefor.”

It is further shown the plaintiff in a reply to the foregoing answer pleaded that he “* * * denies that, as plaintiff, he has failed to state any cause of action, and denies that the plaintiff’s claimed contract or mechanic’s lien is invalid, without force or effect and void, .and further denies that his cause of action is barred.”

In the motion to reopen the case filed on April 26, 1952, the plaintiff stated that in connection with oral arguments at the close of the testimony defendant’s counsel for the first time presented the defense of the statute of limitations and it was further alleged that there had been no. prior definite and written allegation of this defense in any pleadings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Estate of Franken
Supreme Court of Iowa, 2020
In the Matter of the Estate of John E. Terpstra
919 N.W.2d 637 (Court of Appeals of Iowa, 2018)
Beeck v. Aquaslide 'N' Dive Corp.
350 N.W.2d 149 (Supreme Court of Iowa, 1984)
Pride v. Peterson
173 N.W.2d 549 (Supreme Court of Iowa, 1970)
Van Camp v. McAfoos
156 N.W.2d 878 (Supreme Court of Iowa, 1968)
BW Acceptance Corporation v. Saluri
139 N.W.2d 399 (Supreme Court of Iowa, 1966)
In the Matter of Estate of Plumb
129 N.W.2d 630 (Supreme Court of Iowa, 1964)
Hamilton v. Wosepka
124 N.W.2d 512 (Supreme Court of Iowa, 1963)
Uptown Food Store, Inc. v. Ginsberg
123 N.W.2d 59 (Supreme Court of Iowa, 1963)
Markman v. Hoefer
106 N.W.2d 59 (Supreme Court of Iowa, 1960)
Ashby v. School Township of Liberty
98 N.W.2d 848 (Supreme Court of Iowa, 1959)
Thorson v. BOARD OF SUPERVISORS OF HUMBOLDT COUNTY
90 N.W.2d 730 (Supreme Court of Iowa, 1958)
Thorson v. Board of Supervisors
90 N.W.2d 730 (Supreme Court of Iowa, 1958)
Morse v. Morse
77 N.W.2d 622 (Supreme Court of Iowa, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
65 N.W.2d 83, 245 Iowa 922, 1954 Iowa Sup. LEXIS 411, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cuthbertson-v-harry-c-harter-post-no-839-of-veterans-of-foreign-wars-of-iowa-1954.