Cushing Stone Co. v. United States

535 F.2d 27, 210 Ct. Cl. 62, 37 A.F.T.R.2d (RIA) 1405, 1976 U.S. Ct. Cl. LEXIS 258
CourtUnited States Court of Claims
DecidedMay 12, 1976
DocketNo. 419-70
StatusPublished
Cited by4 cases

This text of 535 F.2d 27 (Cushing Stone Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cushing Stone Co. v. United States, 535 F.2d 27, 210 Ct. Cl. 62, 37 A.F.T.R.2d (RIA) 1405, 1976 U.S. Ct. Cl. LEXIS 258 (cc 1976).

Opinion

CoweN, Chief Judge,

delivered the opinion of the court:

This case, before the court on the parties’ respective motions for summary judgment, requires us to determine whether certain expenditures incurred by a quarry operator for the removal and relocation of power transmission towers and lines located on a utility strip traversing the quarry property are “development” expenditures within the meaning of Section 616(a) of the Internal Bevenue Code of 1954.

I

The material facts are stipulated. Since 1917, plaintiff, Cushing Stone Company, Inc., has operated an open -pit dolomite limestone quarry in Montgomery County, New York, on lands which plaintiff either owned in fee (148 acres) or to which it possessed stone quarrying rights (20.46 acres). Prior to 1963, these lands were separated by a 300-foot-wide strip of land owned by Niagara Mohawk Power Corporation (Niagara Mohawk) and on which Niagara Mohawk had erected transmission towers and lines.1 Although [66]*66plaintiff had no stone quarrying rights in the utility strip, it did have the right to cross the strip by tunnel or other acceptable means in order to gain access to the remainder of its quarry lands.2

Plaintiff’s quarrying activities initially were confined to an area west of Niagara Mohawk’s utility strip. By 1962, however, plaintiff’s operations had progressed to the point where the open face of its quarry abutted the western edge of the utility strip. According to plaintiff’s estimates, the supply of quarriable stone in the lands to the west of the. strip would be completely exhausted within 5 years. Since further development of the quarry to the north and south was economically or physically impossible, orderly mining could continue only if plaintiff gained access to its land to the east of the utility strip.

The necessary access clearly could have been gained by tunneling under the transmission lines or developing a new quarry face on the eastern side of the strip. However, since 'both alternatives were prohibitively expensive and would have rendered its operations uneconomical and uncompetitive, plaintiff concluded that Niagara Mohawk’s transmission lines and towers would have to be removed and relocated on other lands.3

On September 19,1962, after several years of negotiations, plaintiff and Niagara Mohawk entered into two' separate agreements pursuant to which plaintiff agreed to exchange certain land for the utility strip and to bear the full cost of removing and relocating the transmission towers and lines. Plaintiff then purchased 22 acres of land from Edward W. Miller and 46.7 acres of land from Charles D. Persons, Jr., at an aggregate cost of $84,174. Although the principal purpose of these acquisitions was to obtain property to exchange for the utility strip, plaintiff recognized [67]*67that certain portions of the Miller and Persons tracts would be retained by plaintiff and mined to the extent that they contained exploitable quantities of stone.4

On April 12, 1963, plaintiff conveyed to Niagara Mohawk a strip of approximately 23.67 acres of land, upon which the latter’s transmission linos were to be relocated.5 This acreage consisted of part of the tracts 'acquired from Miller and Persons, as well as land previously owned by plaintiff. Ten days later, Niagara Mohawk conveyed to plaintiff in fee approximately 31.45 acres of land, including virtually all of the utility strip and approximately 11.29 ¡acres of land to which plaintiff already had stone quarrying rights.6

As a result of the exchange of land and the ultimate relocation of Niagara Mohawk’s transmission towers and lines, plaintiff gained access 'by the most economical means to 11.08 million tons of accessible and quarriable stone.7 Of this amount, 4.28 million tons are contained in lands which plaintiff previously owned or to which it had quarrying rights, 'but to which access had been effectively blocked by Niagara Mohawk’s transmission towers and lines. The remaining 6.80 million tons represent the net gain to plaintiff from the exchange of lands with Niagara Mohawk (1.94 million tons)8 and plaintiff’s retention of a portion of the Persons tract (4.86 million tons).

Niagara Mohawk eventually expended $166,614 in physically removing and relocating the transmission towers and [68]*68lines. Plaintiff was billed for this amount, which it paid on February 23,1965. The costs of acquiring the Miller and Persons tracts (i.e., $34,174), which originally had been entered on a capital account, were then transferred to an expense account and treated as a part of plaintiff’s overall cost of relocating the transmission towers and lines. The full $200,788 (i.e., the $166,614 and the $34,174) was deducted on plaintiff’s 1965 tax return as a mine development expenditure.9

When the Internal Revenue Service (IRS) audited plaintiff’s 1965 return, it disallowed the claimed deduction on the ground that the $200,788 was a nondeductible capital outlay within the meaning of section 263 of the Code. Plaintiff was then assessed an additional $42,725 in taxes and interest. After paying the IRS the full amount of the assessment, plaintiff filed a timely claim for refund, which was denied.10 This action ensued.

Plaintiff originally claimed in its petition that both the $166,614, expended to remove and relocate the transmission towers and. lines, and the $34,174, expended to acquire the Miller and Persons tracts, were fully deductible as mine development expenditures under section 616(a). At oral argument, however, plaintiff informed the court that it was willing to charge the entire $34,174, including any part thereof which might be deductible, to a capital account. As a result of this concession, we need only consider the deducti-bility of the $166,614.

II

Section 616 (a) provides a current deduction from taxable income for

all expenditures paid or incurred during the taxable year for the development of a mine or other natural deposit (other than an oil or gas well) if paid or incurred after [69]*69the existence of ores or minerals in commercially marketable quantities has been disclosed.11

Since it is undisputed that plaintiff’s $166,614 expenditure was incurred after commercially marketable quantities of limestone had been disclosed, the only issue we must decide is whether that expenditure was “for the development of a mine or other natural deposit.11

Neither section 616(a) nor the regulations promulgated thereunder articulate a standard for determining when an expenditure is for the development of a mine. The Senate Finance Committee, in its report accompanying the enactment of the predecessor to section 616(a), merely indicated that such expenditures include “the costs of shafts, tunnels, galleries, etc., which are necessary to malee the ore or other mineral accessible.” S. Rep. No. 781, 82d Cong., 1st Sess. 43 (1951) (emphasis added).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rough v. Chase Bank
W.D. Washington, 2019
Meyers v. United States
26 Cl. Ct. 1004 (Court of Claims, 1992)
H. G. Fenton Material Co. v. Commissioner
74 T.C. 584 (U.S. Tax Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
535 F.2d 27, 210 Ct. Cl. 62, 37 A.F.T.R.2d (RIA) 1405, 1976 U.S. Ct. Cl. LEXIS 258, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cushing-stone-co-v-united-states-cc-1976.