Curtis v. Bradley

28 L.R.A. 143, 31 A. 591, 65 Conn. 99, 1894 Conn. LEXIS 69
CourtSupreme Court of Connecticut
DecidedOctober 4, 1894
StatusPublished
Cited by30 cases

This text of 28 L.R.A. 143 (Curtis v. Bradley) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Curtis v. Bradley, 28 L.R.A. 143, 31 A. 591, 65 Conn. 99, 1894 Conn. LEXIS 69 (Colo. 1894).

Opinion

Hamersley, J.

In the summer of 1890 the plaintiff sold the defendant a building lot. In September of that year the defendant decided to have a house erected on the lot. It was then understood that one Simeon E. Plumb, a builder, should build the house, and that the plaintiff, a merchant, should advance the money for the cost of construction. The decision of this case depended on the actual terms of the agreement then made, the defendant subsequently claiming that his only agreement was with the plaintiff, and that by such agreement the plaintiff undertook to have the house built for the agreed price of $1,700. Plumb built the house under the directions of the defendant. The plaintiff paid to Plumb the amount of all bills for labor and materials as ¿hey came due. The house was finished in March, 1891, and the defendant accepted and occupied it. At the time the house was completed Plumb and the plaintiff went over [102]*102the labor and other bills, and the account of money paid for the cost of construction as charged on the plaintiff’s ledger, and at the foot of that account Plumb wrote the following: “I have examined the above account, and find it correct. S. Plumb.” The 14th of the same month the plaintiff made a copy of this ledger account and gave it to the defendant as the bill due from him to the plaintiff, in pursuance of their agreement. The defendant examined the bill, obtained the labor and material bills, made inquiries among the men who furnished materials whether the prices of the materials were correct, and found that they were correct. The defendant made no objection to the bill rendered as regards amount or price, except the claim that one item of thirty-two cents was charged twice; but the defendant did object to the total amount of the bill, and refused payment. Subsequently Plumb, as an original contractor, placed a mechanic’s lien on the land upon which the house stood, to enforce payment for its construction, and brought an action against the defendant for the foreclosure of said lien. The plaintiff then brought an action against Plumb to recover the money paid for the cost of the house, and garnisheed the defendant as the debtor of Plumb. Subsequently Plumb assigned to the plaintiff his interest in said mechanic’s lien, and in the sum due from the defendant to Plumb for the construction of the house, and the plaintiff then withdrew his action against Plumb, and became substituted as party plaintiff in the action to foreclose said lien. The action of foreclosure was tried, and in December, 1892, judgment was rendered in favor of Bradley the present defendant. By the record of the judgment it appeared that the court found that the lien had been made and recorded and had been assigned to the plaintiff, who became sole owner and was the actual and bona fide holder and owner of the chose in action; but that the contract for the building of the house had not been made with Simeon Plumb, as alleged in the complaint, and that neither he nor the plaintiff as his assignee was entitled to foreclose the same. After this judgment was rendered the plaintiff brought the present action.

[103]*103The complaint follows the form called the “ common counts,” authorized for the commencement of an action. The counts relied on are those for money paid, goods sold and delivered, goods bargained and sold, and work performed and materials furnished, under which counts a bill of particulars was filed detailing each item that the plaintiff claimed entered into the cost of the house; and also the count for money due on account stated, under which count the bill rendered the defendant in March, 1891, was filed as the bill of particulars. The answer is a general denial.

Upon the trial there appears to have been no contest as to the fact that the plaintiff had paid for the construction of the house, and no serious contest as to the accuracy of his account as rendered. The claim of the defendant appears to have been in the alternative — either the defendant’s contract was made with the plaintiff for a fixed price, or the contract was made only with Plumb, and therefore the plaintiff has no cause of action against the defendant; the position of the defendant under the latter claim — which was the one mainly relied on in argument — being, that having induced the court in the former actiou to hold that the contract was not with Plumb, he had escaped all liability on that ground; and if he now induced the court to hold that the contract was made with Plumb, he would escape all liability whatever, and secure his house without any payment, obtaining judicial sanction for the practical theft, under two contradictory judgments.

So far as the record shows, the main question at issue was : What agreement if any, had the defendant made with the plaintiff? It was not claimed on the trial that any question of law was involved in the determination of this issue, and the court found from the evidence that there was an agreement between the plaintiff, Plumb, and the defendant, “ that Plumb should perform work in erecting a house for the defendant on this lot. Plumb as carpenter was to work by the day under the defendant’s directions, at twenty-five cents an hour, and was to employ other carpenters at the same rate. He was also to order materials and work [104]*104other than carpenter work for the house, and have the bills for the same charged to the plaintiff. The plaintiff, at the request of the defendant, agreed to be responsible and liable for all such materials and other work as Plumb should order for the house, and advance the money for the payment of them, and also to advance money to Plumb from time to time as he might require to meet his weekly pajr rolls. The defendant agreed that on the completion of the house, in consideration of the money thus to be advanced by the plaintiff for the building of said house, and in consideration of the building of the same, he would repay the plaintiff the total amount of the moneys so paid out by the plaintiff.” Upon these facts the court rendered judgment that the plaintiff recover of the defendant the sum of $2,974.51, such sum being, as the court found, the total amount paid by the plaintiff in pursuance of that agreement, with interest. From this judgment the defendant appeals.

The appeal contains two distinct grounds for an appeal from the judgment. • First, because the evidence introduced on the trial and printed in the record, does not support the facts found by the court below, but does support a different state of facts claimed by the defendant, and which the court below found were not proved by the evidence. The law does not authorize an appeal from the judgment of a trial court for such reasons, and this court will not take jurisdiction of such appeal. Styles v. Tyler, 64 Conn., 432. The record discloses no reason for the correction of the appeal on the ground that the finding of facts does not fairly present the questions of law actually raised and decided. Second, because the defendant is entitled to a new trial on account of errors alleged to have been made in the admission of evidence. Under this ground of appeal four errors are assigned.

First: The plaintiff offered in evidence certain slips of paper, testifying that Plumb came to the store each Saturday during the building of the house, and gave him the names of the men employed by him during the week and their time; that the plaintiff wrote down at the time in the [105]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Torres
Supreme Court of Connecticut, 2022
Ventoza v. Anderson
545 P.2d 1219 (Court of Appeals of Washington, 1976)
Fisher v. Swartz
130 N.E.2d 575 (Massachusetts Supreme Judicial Court, 1955)
Bendett v. Bendett
52 N.E.2d 2 (Massachusetts Supreme Judicial Court, 1943)
State v. Hayes
18 A.2d 895 (Supreme Court of Connecticut, 1941)
Allegretti v. Murphy-Miles Oil Co.
280 Ill. App. 378 (Appellate Court of Illinois, 1935)
The People v. Greenspawn
179 N.E. 98 (Illinois Supreme Court, 1931)
Papas v. Aetna Insurance
150 A. 310 (Supreme Court of Connecticut, 1930)
Monument Pottery Co. v. Imperial Coal Corporation
21 F.2d 683 (Third Circuit, 1927)
Katsonas v. W. M. Sutherland Building & Contracting Co.
132 A. 553 (Supreme Court of Connecticut, 1926)
People v. Krauser
146 N.E. 593 (Illinois Supreme Court, 1925)
Burn v. Metropolitan Lumber Co.
107 A. 609 (Supreme Court of Connecticut, 1919)
State v. Easter
185 Iowa 476 (Supreme Court of Iowa, 1919)
State v. Rule
1914 OK CR 153 (Court of Criminal Appeals of Oklahoma, 1914)
State v. Patton
164 S.W. 223 (Supreme Court of Missouri, 1914)
Cummings v. Pennsylvania Fire Insurance
153 Iowa 579 (Supreme Court of Iowa, 1912)
Hawken v. Daley
81 A. 1053 (Supreme Court of Connecticut, 1911)
Territory of New Mexico v. Harwood
15 N.M. 424 (New Mexico Supreme Court, 1910)
Graham v. Dillon
121 N.W. 47 (Supreme Court of Iowa, 1909)
Remington Machine Co. v. Wilmington Candy Co.
66 A. 465 (Supreme Court of Delaware, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
28 L.R.A. 143, 31 A. 591, 65 Conn. 99, 1894 Conn. LEXIS 69, Counsel Stack Legal Research, https://law.counselstack.com/opinion/curtis-v-bradley-conn-1894.