Curtis Manufacturing Co. v. Spencer Wire Co.

89 N.E. 534, 203 Mass. 448, 1909 Mass. LEXIS 953
CourtMassachusetts Supreme Judicial Court
DecidedOctober 21, 1909
StatusPublished
Cited by26 cases

This text of 89 N.E. 534 (Curtis Manufacturing Co. v. Spencer Wire Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Curtis Manufacturing Co. v. Spencer Wire Co., 89 N.E. 534, 203 Mass. 448, 1909 Mass. LEXIS 953 (Mass. 1909).

Opinion

Hammond, J.

Webster Court is a private way the fee of which, subject to the defendant’s right of way and to the right of the city of Worcester to maintain a sewer therein, is in the plaintiff. As to the foundation which the defendant has projected into the way, the master has found as follows:

“ The respondent has projected the foundation of its building (but'no part of the superstructure) over into Webster Court.
“ Said projections consist of a concrete foundation twelve feet deep at its westerly end, five feet at its easterly, fifty-five and [450]*450four tenth's (55.4) feet long, and extending into the limits of the way, two and forty-six hundredths (2.46) feet at»the bottom, sixty-five hundredths (.65) feet at the top.
“ Thus occupying one hundred thirty-six and twenty-eight hundredths (136.28) square feet.
“ This foundation was begun and finished within the three weeks preceding Feb. 12, 1909.
“ This foundation is substantially on a line with or below the surface of the way. The superstructure of the building sets back from the way four or five inches.
“ The respondent company knew the line of the way and extended its foundation beyond said line with full knowledge thereof. It did not notify the complainant that it proposed so to do or ask consent therefor, but it was told by the contractor of the building that it was all right to extend foundations over the lines of streets and ways. With this information and in the desire to obtain as large a mill building as possible, it erected its mill on the line of the court, and extended the foundation therefor into the limits of Webster Court, the fee of which subject to the rights above mentioned was owned by the complainant. ”

In this manner the master finds that the respondent has “ deliberately appropriated to itself the right to project its foundation two and forty-six hundredths (2.46) feet into the limits of the court.” While no part of the superstructure projects into the court, still the master has found that if this projection be cut off the remaining foundation would not be adequate to support the superstructure. In a word, the building is in part supported by the projecting part of the foundation, and that support is essential to the maintenance of the building in its present condition. And all this has been done without any claim of right, or even a plausible pretense of such a claim. The statement made to the defendant by the contractor that “it was all right to extend foundations over the lines of streets and ways,” was manifestly applicable only to such ways as were public, and falls far short of showing or justifying the inference that the defendant was acting under a claim of right.

Moreover the defendant had notice. While it is true that the foundation had been laid before the defendant received the letter [451]*451from, the plaintiff of February 11, 1909, still no part of the superstructure had been then built. In the letter the defendant was told in plain and emphatic language that the plaintiff was surprised at his (the defendant’s) conduct in projecting the foundation into the court, and that “ no encroachments will be allowed on same . . . the bounds of which are so clearly defined.” Notwithstanding this notice the defendant used this foundation as an essential support for the building, or in other words, proceeded to erect the building, considered as a whole, in part upon the court.

Here, then, is a plain, intentional violation of the right of the plaintiff as owner of the fee of the way, made under no mistake of fact, or of law, or claim of right, and (as to a considerable part of the building) after an express warning that the owner would allow no encroachments.

That in such a case equity can give relief by way of mandatory injunction is too clear for discussion, and we do not understand the defendant to contend to the contrary. It contends, however, that in many cases this kind of relief is refused, and the party whose right is violated has been remitted to his remedy at law upon the ground that it would be inequitable and oppressive to compel the defendant to restore things to their former condition; and in support of this contention it has cited several cases in this State, among which are Lynch v. Union Institution for Savings, 159 Mass. 806, Jackson.v. Stevenson, 156 Mass. 496, Harrington v. McCarthy, 169 Mass. 492, and Levi v. Worcester Consolidated Street Railway, 193 Mass. 116, as well as many in other jurisdictions where this principle has been recognized and applied. They need not be considered here in detail. The principles governing the action of a court of equity have been considered in many recent cases beside those above mentioned. See among others Tucker v. Howard, 128 Mass. 361, Starkie v. Richmond, 155 Mass. 188, Methodist Episcopal Society v. Akers, 167 Mass. 560, Attorney General v. Algonquin Club, 153 Mass. 447, Codman v. Bradley, 201 Mass. 361.

We see no redeeming feature in the case before us so far as respects the manner of the trespass. Nor do we think that the fact that an injunction will impose upon the defendant an expense disproportion ate to the apparent benefit to the plaintiff is [452]*452of itself enough to deprive the latter of its right to an injunction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J. William Winney, Jr. v. Michael Troy Jerup
2023 WY 113 (Wyoming Supreme Court, 2023)
L'Enfant Plaza East, Inc. v. John McShain, Inc.
359 A.2d 5 (District of Columbia Court of Appeals, 1976)
Tamburello v. Monahan
73 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1947)
Ferrone v. Rossi
42 N.E.2d 564 (Massachusetts Supreme Judicial Court, 1942)
Westhampton Reservoir Recreation Corp. v. Hodder
29 N.E.2d 913 (Massachusetts Supreme Judicial Court, 1940)
Triulzi v. Costa
4 N.E.2d 617 (Massachusetts Supreme Judicial Court, 1936)
Gray v. Howell
198 N.E. 516 (Massachusetts Supreme Judicial Court, 1935)
Reppucci v. Poleari
291 Mass. 424 (Massachusetts Supreme Judicial Court, 1935)
Geragosian v. Union Realty Co.
289 Mass. 104 (Massachusetts Supreme Judicial Court, 1935)
Welton v. 40 East Oak St. Bldg. Corporation
70 F.2d 377 (Seventh Circuit, 1934)
Tyler v. City of Haverhill
172 N.E. 342 (Massachusetts Supreme Judicial Court, 1930)
Nelson v. American Telephone & Telegraph Co.
170 N.E. 416 (Massachusetts Supreme Judicial Court, 1930)
Crosby v. Blomerth
154 N.E. 763 (Massachusetts Supreme Judicial Court, 1927)
Marcus v. Brody
149 N.E. 673 (Massachusetts Supreme Judicial Court, 1925)
Hutton v. School City
142 N.E. 427 (Indiana Supreme Court, 1924)
Siegel v. Starzyk
130 N.E. 499 (Massachusetts Supreme Judicial Court, 1921)
Congregation Beth Israel v. Heller
231 Mass. 527 (Massachusetts Supreme Judicial Court, 1919)
Inhabitants of Brookline v. Whidden
229 Mass. 485 (Massachusetts Supreme Judicial Court, 1918)
Brooks v. Rosenbaum
217 Mass. 172 (Massachusetts Supreme Judicial Court, 1914)
Stevens v. Rockport Granite Co.
216 Mass. 486 (Massachusetts Supreme Judicial Court, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
89 N.E. 534, 203 Mass. 448, 1909 Mass. LEXIS 953, Counsel Stack Legal Research, https://law.counselstack.com/opinion/curtis-manufacturing-co-v-spencer-wire-co-mass-1909.