Curtice v. West

2 N.Y.S. 507, 18 N.Y. St. Rep. 511, 50 Hun 47, 1888 N.Y. Misc. LEXIS 814
New York Supreme Court·Decided October 19, 1888·Published·Cited by 16 cases

Opinion

Bradley, J.

In July, 1879, the parties entered into an agreement in writing by which the plaintiff agreed to erect for the defendant a hotel building in the town of Webster, N. Y., within three months, for the sum of $3,150, payable in installments,—$1,000 when the frame was erected, $1,000 when the mason work and plastering were completed, and the balance when the entire work was finished. The defendant, as the work progressed, paid the first two installments, of $1,000 each, to the plaintiff; and on January 8, 1880, he paid him the further sum of $1,000. The referee found that the building was substantially completed on or before the day last mentioned; that there were some slight defects in the building caused by inadvertence of the builder, but that they, and the deviations from the contract, were waived, and the building accepted by the defendant as finished, on or prior to January 8,1880; and that the plaintiff was entitled to recover the residue of the contract price, and -$205,69 for extra work, with interest from that day; and directed judgment accordingly. The evidence on the part of the defendant tends to prove that in many respects the plaintiff had not performed the contract, and that the defects resulting from such failure are quite substantial and pervasive. By the ■evidence, the conclusion apparently was warranted that the default of the plaintiff was such that he was not entitled to recover upon the contract. The performance of the agreement on the part of the plaintiff was a condition precedent to recovery, unless such performance was waived by the defendant, in this class of cases, however, the condition precedent may not require literal performance; but when the contractor has in good faith intended to comply with his agreement, and has substantially done so, slight defects, susceptible •of remedy, for which allowance may be made by way of adequate indemnity to the other party, may not be in the way of recovery upon the contract, subject to such allowance for damages. Woodward v. Fuller, 80 N. Y. 312. [509] There was evidence on the part of the plaintiff upon the subject, and tending to prove substantial performance within the rule before mentioned; also that some of the defects complained of in the structure were caused solely by the defective plans and specifications of the architect, which were parts of the contract; and there is some evidence bearing upon the question of waiver by the defendant of deviation from the contract, and of the defects in the work and materials. These are matters upon which there is a conflict of the evidence of the respective parties. The conclusions of fact in those respects, of the referee, not being wholly without evidence, the exceptions taken to such findings do not raise any question of law. Code Civil Proc. § 992. And as it does not appear that the case contains all the evidence bearing upon the proposition so found by him, the question whether they are against the weight of the evidence is not here for consideration, and it will be assumed that the evidence given upon the trial was sufficient to fairly support them. Porter v. Smith, 35 Hun, 118; Spence v. Chambers, 39 Hun, 193.

The same remarks are applicable to the matter of the defendant’s counterclaim alleged; and in respect to that it may also be suggested that there is no-request or refusal to find upon the subject. It is therefore unnecessary to refer specifically to the evidence bearing upon those questions of fact, for the purposes of this review. "VVe have not, however, overlooked any of the evidence, or failed to appreciate the very thorough analysis made of it by the argument of the learned counsel for the defendant, which but for the proposition before stated would properly require and have a more extended expression of consideration.

The contention that recovery upon the contract cannot be supported because the action was upon the quantum meruit is not sustained. Ho such question was raised upon the trial, and it is not available when raised for the first time upon appeal. Then the cause of action alleged is not entirely remote or distinct from that on which recovery was had. It was, as alleged, for materials furnished, and work done, in the construction of a hotel for the defendant, which is the subject of the contract in question. Southwick v. Bank, 84 N. Y. 420.

Free access — add to your briefcase to read the full text and ask questions with AI

Curtice v. West, 2 N.Y.S. 507, 18 N.Y. St. Rep. 511, 50 Hun 47, 1888 N.Y. Misc. LEXIS 814 (N.Y. Super. Ct. 1888).

2 N.Y.S. 507 (Curtice v. West) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Henderson v. Twin Falis County
80 P.2d 801 (Idaho Supreme Court, 1938)
In re the Estate of Mezger
154 Misc. 633 (New York Surrogate's Court, 1935)
Fort Worth Mut. Benev. Ass'n. v. Miller
280 S.W. 338 (Court of Appeals of Texas, 1926)
American Fidelity Co. v. Patty
19 Ohio C.C. (n.s.) 392 (Ohio Court of Appeals, 1913)
Da Rin v. Casualty Co. of America
108 P. 649 (Montana Supreme Court, 1910)
Appel v. Ætna Life Insurance
86 A.D. 83 (Appellate Division of the Supreme Court of New York, 1903)
Estabrooks' Admrs. v. Union Casualty & Surety Co.
52 A. 1048 (Supreme Court of Vermont, 1902)
Commercial Travelers Mutual Accident Ass'n v. Springsteen
55 N.E. 973 (Indiana Court of Appeals, 1900)
Hess v. Preferred Masonic Mutual Accident Ass'n
40 L.R.A. 444 (Michigan Supreme Court, 1897)
De Van v. Commercial Travelers' Mut. Acc. Ass'n of America
36 N.Y.S. 931 (New York Supreme Court, 1895)
Wehle v. United States Mutual Accident Ass'n
11 Misc. 36 (The Superior Court of New York City, 1895)
Wehle v. United States Mut. Acc. Ass'n
31 N.Y.S. 865 (Superior Court of New York, 1895)
Williams v. United States Mut. Acc. Ass'n
31 N.Y.S. 343 (New York Supreme Court, 1894)
Keene v. New England Mutual Accident Ass'n
36 N.E. 891 (Massachusetts Supreme Judicial Court, 1894)