Cunningham v. State of Indiana

182 N.E. 95, 95 Ind. App. 434, 1932 Ind. App. LEXIS 121
Indiana Court of Appeals·Decided July 27, 1932·No. No. 14,383.·Published

Opinion

Lockyear, J.

— This action was commenced by the appellants as plaintiffs against the appellee, State of Indiana, as defendant, in the Marion Superior Court sitting as a court of claims under the laws of this state.

The complaint consists of a single paragraph which alleges, in substance, that the State of Indiana, through the Director of the State Highway Commission, on April 9, 1926, entered into a written contract with the plaintiffs for the construction by plaintiffs for the State of a section of state highway No. 7 about eight and one-third miles in length between the city of Huntington and the village of Roanoke, in accordance with certain plans and specifications which are set out as exhibits to the complaint and made a part of it. That the contract called for the completion of this improvement by November 1, 1926.

That the plaintiffs supplied all things required of them, promptly began to construct said highway in accordance with said plans and specifications and would, *436 had they not been prevented from so doing by the State, its engineer, officials, and agents, have completed said improvement in accordance with said plans and specifications by November 1, 1926.

That after plaintiffs had constructed approximately 80 per cent of the grade, drains, and waterways for said highway in accordance with said plans and specifications preparatory to the laying of the pavement, and after plaintiffs had moved paving materials, machinery, and equipment to the road and were ready to begin laying pavement in accordance with said plans and specifications, the defendant, through its said highway engineer and highway officials, refused to permit plaintiffs to lay said pavement on said grade as constructed in accordance with said plans and specifications and to complete the remainder of said grade, drains, and waterways in accordance with said plans and specifications and refused to approve said work if constructed in accordance with said plans and specifications as the same existed and were a part of said contract; that without provision or authority therefor in said contract and after the grading and preparation for paving had been accomplished to the extent aforesaid by the latter part of July, 1926, defendant, through its engineer and officials, made numerous material changes, alterations, and additions in and to said plans and departures therefrom which applied to the portion of the grade, drains, and waterways already constructed as well as to the part yet to be constructed and required of plaintiffs that they reconstruct the grade, drains, and waterways, which already had been constructed, in accordance with said changes, alterations, additions, and departures in and from said original plans and to construct the remainder of the grade, drains, and waterways in accordance with said altered plans before any pavement was laid on said highway.

*437 The defendant’s refusal to permit and approve highway and pavement to be constructed in accordance with said original plans and specifications and said requirement that said highway be constructed in accordance with said altered plans constituted breaches of said contract.

That plaintiffs protested to said defendants against said changes in said plans and the delay and damages resulting to them in not being able to complete said highway within the time they otherwise would; that plaintiffs notified defendant that they would proceed to construct said highway in accordance with said altered plans under protest and would hold defendant liable for the damages caused to them on account of the resulting delays.

That while plaintiffs were engaged in reconstructing said grade already constructed, and while they were constructing the grade, drains, and waterways for said highway preparatory to paving it in accordance with said altered plans, defendant, its engineer and officials, as late as October 26, 1926, made still further alterations, and additions to the plans as already altered and required plaintiffs to do said work of grading, etc., preparatory to paving in accordance with said plans as altered the second time.

That none of said alterations in said original plans were authorized by said contract and were not consented to by plaintiffs; that said alterations were required at a late and unseasonable time; that none of said alterations were necessary in order to construct said highway in accordance with said original plans, but were necessary only in the sense of providing for materially different grades, drains, and waterways than provided for in said original plans; that the additional work caused by said alterations exceeded the quantity of additional work for which provision was made in said contract; that defend *438 ant failed to procure some necessary right of way for said highway by the time it was needed in the construction of said highway and that failure to get said right of way caused delay in doing said work.

That because plaintiffs were prevented from laying said pavement on a grade constructed in accordance with said original plans and because they were required to reconstruct said grade, etc., in accordance with said belated and unauthorized alterations and because of said failure to procure said right of way, the plaintiffs were prevented from laying any pavement on said highway during 1926; that because of the delays resulting from said breaches of said contract by defendants the plaintiffs were delayed a full year in the completion of said highway; that all of the pavement had on that account to be laid in the year 1927; that because of the lateness of the time when said changes were required plaintiffs were unable to even finish said grade and drains in 1926.

That plaintiffs were damaged by reason of said delay in laying said pavement; that plaintiffs were also required to use soft dirt for a grade in violation of the contract and specifications to their damage; that in all, plaintiffs were damaged in the sum of $48,911.09 as the. proximate result of said breaches of said contract by defendant.

The appellee filed demurrer for'want of facts to the complaint.

The appellee filed an answer in two paragraphs; the first was in general denial, and the second was on the theory that plaintiffs proceeded with the work after the alleged breaches of the contract by the defendant without protest, and that they have waived their right to damages and are estopped from claiming them.

The appellants filed a demurrer for want of facts to the second paragraph of answer.

*439 The appellants filed a reply in general denial to the second paragraph of answer.

The court overruled appellee’s demurrer to the complaint, to which ruling appellee at the time excepted.

The court overruled appellant’s demurrer to the second paragraph of answer, to which ruling the plaintiffs' at the time excepted.

The court tried the case; found generally for the appellee and rendered judgment for the appellee.

The court overruled appellant’s motion for a new trial to which ruling the appellants at the time excepted.

The assignment of error is that the court erred in overruling appellant’s motion for a new trial.

Free access — add to your briefcase to read the full text and ask questions with AI

Cunningham v. State of Indiana, 182 N.E. 95, 95 Ind. App. 434, 1932 Ind. App. LEXIS 121 (Ind. Ct. App. 1932).

182 N.E. 95 (Cunningham v. State of Indiana) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

State v. Feigel
178 N.E. 435 (Indiana Supreme Court, 1931)