This text of Cunningham Energy, LLC v. Board of Education of the County of Kanawha (Cunningham Energy, LLC v. Board of Education of the County of Kanawha) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cunningham Energy, LLC v. Board of Education of the County of Kanawha, (W. Va. 2021).

Opinion

STATE OF WEST VIRGINIA SUPREME COURT OF APPEALS

Cunningham Energy, LLC, FILED Proposed Intervenor Below, Petitioner March 23, 2021 EDYTHE NASH GAISER, CLERK SUPREME COURT OF APPEALS vs.) No. 20-0346 (Kanawha County 20-P-20) OF WEST VIRGINIA

Board of Education of the County of Kanawha, a Statutory Corporation, Petitioner Below, Respondent

MEMORANDUM DECISION

Petitioner Cunningham Energy, LLC, by counsel Gerald M. Titus III, Travis H. Eckley, and Wesley A. Shumway, appeals the March 10, 2020, order of the Circuit Court of Kanawha County denying its motion to intervene in the underlying condemnation action. Respondent Board of Education of the County of Kanawha, by counsel J. Nicholas Barth, filed a response in support of the circuit court’s order. Petitioner filed a reply.

This Court has considered the parties’ briefs and the record on appeal. The facts and legal arguments are adequately presented, and the decisional process would not be significantly aided by oral argument. Upon consideration of the standard of review, the briefs, and the record presented, the Court finds that the court below erred by failing to apply the correct standard in ruling on petitioner’s motion to intervene. Accordingly, we reverse the circuit court’s order and remand this case for further proceedings consistent with this decision. Because this case satisfies the “limited circumstances” requirement of Rule 21(d) of the West Virginia Rules of Appellate Procedure, we find that a memorandum decision is appropriate to resolve the issues presented.

The dispute in this case concerns a 34.66-acre parcel of land (“the parcel”) in Kanawha County and the mineral interests underneath and adjacent to the parcel. Until her death in March of 2011, Patsy Haas owned the surface of the parcel. She died intestate, and her children, Kelly Barnhart and James Haas, Jr., each inherited an undivided one-half interest in the surface of the parcel. On August 11, 2011, by general warranty deed, petitioner obtained an interest in the surface of the parcel. 1 Beginning in 2010 and continuing through September 2018, petitioner also

1 Petitioner and respondent dispute whether petitioner obtained only Kelly Barnhart’s interest in the surface of the parcel or whether petitioner obtained both Kelly Barnhart’s interest and James Haas, Jr.’s interest. Regardless, petitioner was assessed the county property taxes on the full surface of the parcel from tax year 2013 through 2019, and petitioner paid those taxes.

1 accumulated various leasehold interests in the minerals underneath the parcel and underneath the property surrounding the parcel. 2 Petitioner is a business that owns and develops oil and gas interests.

On November 29, 2018, petitioner and Vesta O&G Holdings, LLC (“Vesta”) executed a letter of intent (“the first LOI”), agreeing that Vesta would form a Delaware limited liability company for the purpose of acquiring and holding certain real property and leases held by petitioner (“the assets”). Among other things, the assets included petitioner’s interest in the surface of the parcel, petitioner’s leasehold interests in the minerals underneath the parcel, and petitioner’s leasehold interests in minerals underneath property adjacent to the parcel. Under the first LOI, petitioner proposed transferring the assets to Vesta for Vesta to then transfer to a new limited liability company. Petitioner would be offered a minority ownership position in the new company, and Vesta would contribute capital to pay certain debts of petitioner and fund the drilling of seven oil wells in West Virginia. Petitioner claims that, within days of executing the first LOI, Vesta began paying petitioner’s debts as agreed, and on December 4, 2018, petitioner transferred the assets to Vesta. Petitioner claims that although Vesta formed the new limited liability company as agreed, Vesta did not transfer the assets to that company.

In December of 2018, petitioner applied to the West Virginia Department of Environmental Protection (“WVDEP”) for five “well work” permits for shallow horizontal oil wells. 3 The following February, petitioner applied to the WVDEP for two additional permits. The applications for the permits proposed that a well pad would be located on the surface of the parcel, with “laterals” extending through and beyond the parcel. WVDEP granted the applications and issued the seven permits in February and March of 2019.

Meanwhile, respondent was considering the parcel as the location for a new elementary school. On March 19, 2019, respondent purchased a special warranty deed from James Haas, Jr. purporting to convey to respondent a one-half undivided interest in the surface of the parcel.

On May 15, 2019, petitioner filed a lawsuit against Vesta in federal district court, alleging, among other things, that Vesta had breached the terms set forth in the first LOI. Vesta asserted a counterclaim against petitioner. A few months later, on October 18, 2019, they executed a second letter of intent (“the second LOI”) along with a Memorandum of Understanding (“MOU”). Through these two documents, petitioner and Vesta agreed to dismiss all claims pending in federal district court without prejudice. The claims were eventually dismissed as agreed. Petitioner and Vesta also agreed to perform certain proposed transactions by November 15, 2019. The second LOI stated that, “[i]n the event the parties do not consummate the Proposed Transaction by [] [November 15, 2019], the [assets] shall be immediately assigned back to [petitioner].”

2 We note that while the appendix record includes information concerning the various mineral leases obtained by petitioner, such as when they were obtained and from whom, these details are not germane to the resolution of this appeal. 3 “It is unlawful for any person to commence any well work, including site preparation work which involves any disturbance of land, without first securing from the [WVDEP] a well work permit.” W. Va. Code § 22-6-6(a) (in part). 2 The second LOI and the MOU acknowledged that the parcel would most likely be sold or condemned so that a school could be built on the parcel. The MOU stated that “[c]ondemnation and subsequent construction of the school would disrupt and effectively prohibit planned development of oil and gas resources underlying the [parcel], [and] the valuation of such development is projected to be $42,000,000 in present day terms.” In the MOU, petitioner and Vesta agreed that, upon sale or condemnation of the parcel, Vesta would receive the first $5,000,000 and the remaining funds would be distributed as follows:

(1) if Vesta and [petitioner] are able to finalize a deal for further development of West Virginia and Canada resources, the next $25,000,000 of proceeds from the [parcel] will be allocated to development and operation of West Virginia resources, with any remaining funds directed to Canada operations. (2) If, after good-faith negotiation, a deal for further development in West Virginia and Canada is not reached, the any [sic] remaining proceeds from the sale of the [parcel] (i.e. those above the first $5,000,000) will be allocated as follows: 80% to [petitioner] and 20% to Vesta. Additionally, all leaseholds and other interests previously transferred to Vesta from [petitioner] would be conveyed/transferred to [petitioner].

Petitioner obtained a report from a licensed professional engineer estimating the present value of future revenue that would be lost if petitioner was unable to drill seven horizontal wells. That report estimated the lost revenue would total $58,800,000. The report also estimated that an additional $21,000,000 would have been paid to the royalty owners during the estimated years of production.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. Ball v. Cummings