Cummings v. Patton

2001 MT 218N
CourtMontana Supreme Court
DecidedNovember 6, 2001
Docket00-833
StatusPublished

This text of 2001 MT 218N (Cummings v. Patton) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cummings v. Patton, 2001 MT 218N (Mo. 2001).

Opinion

file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/00-833%20Opinion.htm

No. 00-833

IN THE SUPREME COURT OF THE STATE OF MONTANA

2001 MT 218N

ROBERT CUMMINGS, d/b/a

CUSTOM CUT CONSTRUCTION,

Plaintiff and Respondent,

v.

LELAND D. PATTON and

TONI M. PATTON,

Defendants and Appellants.

APPEAL FROM: District Court of the Twenty-First Judicial District,

In and for the County of Ravalli,

The Honorable Jeffrey H. Langton, Judge presiding.

COUNSEL OF RECORD:

For Appellants:

Howard C. Greenwood, Attorney at Law, Hamilton, Montana

For Respondent:

John D. Greef, Greef & Markette, Hamilton, Montana

Submitted on Briefs: May 24, 2001 Decided: November 6, 2001

file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/00-833%20Opinion.htm (1 of 7)1/19/2007 10:48:50 AM file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/00-833%20Opinion.htm

Filed:

__________________________________________

Clerk

Chief Justice Karla M. Gray delivered the Opinion of the Court.

¶1Pursuant to Section I, Paragraph 3(c), Montana Supreme Court 1996 Internal Operating Rules, the following decision shall not be cited as precedent. It shall be filed as a public document with the Clerk of the Supreme Court and shall be reported by case title, Supreme Court cause number and result to the State Reporter Publishing Company and to West Group in the quarterly table of noncitable cases issued by this Court.

¶2 Leland D. Patton and Toni M. Patton appeal from a judgment entered by the Twenty- First Judicial District Court, Ravalli County, in favor of Robert Cummings, d/b/a Custom Cut Construction. We affirm in part, reverse in part, and remand.

¶3 Cummings, a building contractor, and the Pattons entered into a contract for construction of a residence and garage on the Pattons' property. The contract price was the fixed sum of $148,823.70, less items paid directly by the Pattons and plus amounts for agreed-upon upgrades and work not originally contemplated. The contract provided for "allowances" for certain specified items which would result in adjustments to reflect actual amounts expended either greater or lesser than the corresponding amount contained in the contract. Over the course of the work, the Pattons made progress payments to Cummings in the total amount of $135,442.75.

¶4 As the work progressed, problems arose between the Pattons and Cummings over alleged unsatisfactory work. Ultimately, Cummings ceased working on correcting purported problems and the Pattons withheld the final payment due Cummings under the contract. Cummings filed a construction lien on the property alleging the amount remaining unpaid was $11,927.43, and sued the Pattons to collect that amount plus costs and attorney fees. The Pattons responded and subsequently were permitted to file an amended response and counterclaim. They denied that Cummings performed the contract in its entirety or timely and that he was entitled to the amount asserted. Via counterclaim, they alleged various breaches of the contract by Cummings including failure to complete

file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/00-833%20Opinion.htm (2 of 7)1/19/2007 10:48:50 AM file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/00-833%20Opinion.htm

the job timely, inadequate workmanship, unacceptable work and inferior materials. The Pattons sought damages for, among other things, the costs they alleged would be incurred to complete the project in compliance with the contract and reasonable construction standards.

¶5 The District Court held a bench trial which resulted in a judgment in Cummings' favor in the amount of $2,801.55. In its extensive findings of fact, the court found that the breakdown in communications between the parties resulted from the hostile work environment created by Leland Patton and that Cummings' failure to fully complete the contract in a workmanlike manner resulted from Leland Patton's failure to give him the reasonable opportunity to do so. The court also adjusted the subtotal bid amount to $130,090.27 for certain "allowances," one modification and work not done; determined the general contractor's fee of 10% of that amount would bring the total to $143,099.30; and ruled that amount would have been due Cummings had the contract been fully performed. Consequently, without further adjustments, and given the amounts already paid to Cummings, the court determined the Pattons would have owed Cummings $7,656.55, rather than the $11,927.43 alleged in Cummings' construction lien. The District Court went on, however, to detail numerous shortcomings and defects in the work performed and to determine that $4,455 in additional costs to cover labor and materials would be necessary for final repairs. It also found that Cummings overcharged the Pattons in the approximate amount of $400 for roofing materials.

¶6 The District Court concluded, based on its extensive findings, that Cummings breached the contract but that his anticipatory breach was due to hostile working conditions created by Leland Patton. It further concluded Cummings has a construction lien on the Pattons' property to secure payment of the net sum of $2,801.55, plus interest and costs, and that Cummings is statutorily entitled to reasonable attorney fees. The Pattons appeal and we affirm in part, reverse in part, and remand for further proceedings.

¶7 The Pattons set forth nine issues on appeal. They challenge several District Court findings of fact. They also argue, with regard to their counterclaim, that Cummings breached the contract by not completing their house on time and that the judgment does not fully address all the defects in the house or adequately compensate them for their damages. They contend Cummings should not have been awarded his costs and attorney fees and, finally, that the District Court improperly allocated trial time.

¶8 Our standard of review of district court findings of fact is whether those findings are

file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/00-833%20Opinion.htm (3 of 7)1/19/2007 10:48:50 AM file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/00-833%20Opinion.htm

clearly erroneous. Findings are clearly erroneous if they are not supported by substantial credible evidence, if the district court misapprehended the effect of the evidence, or if this Court is left with a definite and firm conviction that a mistake has been made. Interstate Prod. Credit Ass'n v. DeSaye (1991), 250 Mont. 320, 323, 820 P.2d 1285, 1287.

¶9 We conclude that two of the challenged findings are clearly erroneous. In Finding No. 9, the District Court found Cummings' subtotal bid amount should be reduced by $400 because Cummings only partially completed plumbing in the garage. In fact, Cummings' testimony confirmed that the bid for plumbing of the garage should be reduced by $724, as the Pattons assert. Cummings concedes on appeal that the $400 amount in Finding No. 9 is not supported by the evidence. On remand, the District Court is instructed to correct the adjustment for garage plumbing in Finding No. 9 to $724 and to flow the resulting $324 reduction through its calculations, ultimately reducing the amount of Cummings' judgment against the Pattons accordingly.

¶10 The Pattons also challenge a portion of Finding No. 15, contending they are entitled to an additional adjustment for overcharged roofing materials.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Interstate Production Credit Ass'n v. Desaye
820 P.2d 1285 (Montana Supreme Court, 1991)
Keller v. Dooling
813 P.2d 437 (Montana Supreme Court, 1991)
Nason v. Leistiko
1998 MT 217 (Montana Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
2001 MT 218N, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cummings-v-patton-mont-2001.