Cummings v. Clark

282 F. 300, 1922 U.S. Dist. LEXIS 1393
CourtDistrict Court, E.D. Pennsylvania
DecidedJune 9, 1922
DocketNo. 7230
StatusPublished
Cited by3 cases

This text of 282 F. 300 (Cummings v. Clark) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cummings v. Clark, 282 F. 300, 1922 U.S. Dist. LEXIS 1393 (E.D. Pa. 1922).

Opinion

DICKINSON, District Judge.

The question of law raised goes to “a part of the claim” of the plaintiff, but not “to the whole” of it. In consequence, we now enter no judgment or order. Counsel may be able to put the record in such shape as that final judgment may be entered to await any appellate action either party may desire to take. The question is a very interesting one, and is made interesting because of its difficulty. The difficulty is in reaching any judgment which will not visit upon one party or the other an unrequited loss. In common with many situatidns, our view of the merits of this one is affected by our approach to it. One mode of approach induces us to look upon it as a contract which the defendant was not only willing, but was selfishly interested, and because of this, desirous, to be performed, but performance of which was made impossible by the subsequent acts of the lawmaking power. This is the view which defendant presents. Another approach presents the view of a contract, performance- of which may be had, notwithstanding the later requirements of the law have made it necessary to dispense with some purely formal features which had been incorporated into the contract. This is the view which the plaintiff presents.

The cause presents the distinction, sometimes of importance to observe and sometimes not, between justice and legal justice. This is the general view of the cause. More particularly the case is that of one who felt that he owned, and was in a position to control, the title to two properties, one an electric plant and the other a railway. Neithér had been a financial success, as before conducted, and both had been made the subject of receiverships. They were rec'ognized to have, however, a substantial value which could, by proper management, be realized. In other words, the familiar situation was presented of utilities companies in need of reorganization.

The plaintiff and defendants were brought together by this situation and entered into a contract which contemplated, as both parties agree, that the defendants should take over the properties, and as the defendants insist, should take them over in a particular way, and in the form of taking over corporate securities to be issued which would give con[302]*302trol of the properties. A plan was accordingly outlined by which the properties were, through judicial sales, to be freed from the entanglements born of former bond and stock issues, and the title to which should be held by a new corporation, the financial organization of which was to take a prescribed form. This was that the company should have authority to issue 7,500 shares of stock, of the par value of $100 each, all of which should have been issued and outstanding, and should have executed a general mortgage, in the sum of $2,000,000, to secure an issue of bonds, $500,000 of which should have been issued, leaving the remaining $1,500,000 to be in reserve as part of the means of making improvements and extensions to the properties of the corporation. This plan of reorganization was lawful at the time of the contract and practically feasible. There were a number of things to be done before it could be carried into effect.

Between the time of the making of the contract and the organization of the contemplated new corporation, the Legislature of the state of Illinois (the state of the domicile) passed a law constituting a Public Utilities Commission. Hurd’s Rev. St. 1913, c. Illa. The effect was to radically change the situation of the contracting parties. Before the law was passed they, had the privilege (so far as practically concerned them) to outline and carry into effect any plan of financial organization of the proposed corporation they thought to be wise. After the law was passed all such plans were subjected to the control and sanction of the commission. It thus became necessary to submit the plan outlined to the commission for approval. In the effort to secure this approval the defendants co-operated with the plaintiff. Approval was, however, refused, and a different plan became the only one on which the organization of the company could proceed. This reduced the issue of stock from 7,500 shares to 1,420, of the same par value, and the mortgage bond issue from $2,000,000 to $500,000. Plaintiff carried out all the requirements of his undertaking, except in the foregoing particulars of stock and bond issues, and made demand for his agreed compensation. This the defendants refused, on the ground that he had not performed.

This raises the issue between the parties and presents the question to be determined. In thus presenting it, we have ignored the distinction between the two properties. In point of fact, the outline given pertains only to the railway property. The electric plant was free from this complication, and the contract with respect to it was followed to delivery, and the payment of one-half of the contract price. It is involved, however, as the unpaid balance is not payable until there had been performance of the entire contract. The plan, so far as it affects the issue of bonds, has not been accurately stated, but so as to present the point involved. The plaintiff was to retain as part of what he was to receive $450,000 of the bond issue. This was in fact all of the bond issue to be at first outstanding, as $50,000 of the $500,000 was to be part of the resources of the reorganized corporation.

This outlines with sufficient clearness the situation. As the plaintiff presents it, we have a contract to deliver properties, delivery of which has been tendered. The defendants have thus received all for which [303]*303they contracted, and this remains true, notwithstanding that it is also true that the ownership is represented by a fewer number of shares than contemplated by the contract. It is substantially, as well as mathematically, true that the resulting integer unit is the same, no matter what the denominator of the vulgar fraction employed to express it. On the other hand, as the defendants present the situation, we have a ■ contract to deliver bonds and stock of a named par value in a corporation, and a tender of something else. •

These presentations suggest that we look into the contract to determine whether its subject-matter was the one or the other. Such a quest is, however, futile and idle, for the reason that we would be searching into the minds of the parties for something which was not there. Neither party had the distinction in mind at the time of the contract. That they did have in mind, not that the contemplated stock and bond issues could not be made, but that the plaintiff might not be able to deliver them, is clear from the proviso to the sixth paragraph. The provision is that, if the plaintiff is unable to deliver “the stock of said reorganized company,” the parties shall be absolved from further obligation. This provision does not lighten the labors of any one charged with the duty of making a ruling, because each party quotes this clause in his favor. Here again the plain truth is that the language quoted was employed without thought of its application to the situation which afterwards arose. The question must be faced as the broad one arising out of something being agreed to be done, or to be done in a way which was afterwards prohibited by law. The contingency was not foreseen, and the attitude of the parties to it concerns us only in the aspect of the responsibility for its not having been foreseen.

The Legal Principles Involved.

We start with general principles over which there is no controversy.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Emery Bird Thayer Dry Goods Co. v. Williams
98 F.2d 166 (Eighth Circuit, 1938)
Robbins v. Pacific Eastern Corp.
65 P.2d 42 (California Supreme Court, 1937)
Lohman v. Kansas City Southern Railway Co.
33 S.W.2d 112 (Supreme Court of Missouri, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
282 F. 300, 1922 U.S. Dist. LEXIS 1393, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cummings-v-clark-paed-1922.