Cully Corporation v. United States

United States Court of Federal Claims·Decided May 19, 2022·No. 19-339·Published

Opinion

In the United States Court of Federal Claims No. 19-339C Filed: May 19, 2022

CULLY CORPORATION, Plaintiff, v.

THE UNITED STATES, Defendant.

ORDER AMENDING SUMMARY JUDGMENT

TAPP, Judge.

On April 14, 2022, the Court denied summary judgment for both parties and made substantive findings about the property interest at issue, but it ultimately found that factual issues remained for trial. Cully Corp. v. United States, ___ Fed. Cl. ___ 2022 WL 1115107 (April 14, 2022) (Cully Sum. J. Op., ECF No. 122). That Opinion was issued after several years of litigation including amended pleadings, dispositive motions, exhaustive discovery, pretrial filings, and a working trial schedule; all providing a seemingly stable landscape only weeks before trial scheduled in Fairbanks, Alaska. At the summit of trial preparation, the United States substantially altered its legal position. This pivot is the catalyst for the Court’s determination that a portion of the Summary Judgment Opinion must be amended.

This takings case has been litigated for three years and has been the subject of three substantive opinions, thus an in-depth factual recitation is unnecessary. (See ECF Nos. 36, 59, 122). In its April 14 Summary Judgment Opinion, the Court determined that Plaintiff, Cully Corporation (“Cully”), holds a valid reversionary interest in the properties at issue and that the United States’ letter 1 of March 16, 2013 challenging Cully’s ownership interest was “baseless.” (Cully Sum. J. Op. at 17). However, the Court also found genuine issues of material fact necessitating trial. These issues included whether the United States’ actions qualified as an interference necessary to prove a taking and whether Cully had incurred damages from the taking of its reversionary interest or could incur damages from the United States’ continued interference. (Id.). 2 The parties and the Court marched toward the May 9 trial date.

1 This has also been referred to as the “ouster letter.” 2 Also remaining for trial was a second claim asserting quantum meruit. The Summary Judgment Opinion made no substantive findings regarding that claim. Those findings, or lack thereof, remain undisturbed by this Order. On April 27, 2022, at 10:34 p.m. ET, the eve of the Final Pretrial Conference, the United States filed the following notice:

Defendant . . . respectfully notifies the Court that on April 27, 2022, the United States Air Force sent a letter to the President of Cully Corporation (Cully), Ms. Martha Awalin, rescinding the March 6, 2013 letter from Air Force Colonel Robyn Burk to Ms. Awalin (that, in turn, rescinded the March 27, 2006 Letter of Transfer). A copy of the April 27, 2022 letter was also sent on the same day to plaintiff’s counsel and is attached as an exhibit to this Notice. Because the March 6, 2013 letter serves as the basis of Cully’s Fifth Amending [sic] takings claim against the United States, see ECF No. 42 ¶ 34 (2nd Amended Complaint), and consistent with this Court’s recent decision on the matter, see ECF No. 122, the rescission of the March 6, 2013 letter moots plaintiff’s takings claim.

(Recission Notice, ECF No. 137). 3 The referenced letter is signed by Colonel Paul S. Cornwell, Commander of Pacific Air Forces Regional Support Center. (2022 Recission Letter, ECF No. 137-1). That letter states:

In the 6 March 2013 letter from Colonel Robyn M. Burk, Commander, 611th Air Support Group to Martha Awalin, President/CEO, Cully Corporation, concerning facilities 2, 3, and 4 at Point Lay Long Range Radar Site, the Air Force determined that the 27 March 2006 Letter of Transfer was not authorized and not effective. That 6 March 2013 determination is hereby rescinded, and the letter of 6 March 2013 is hereby withdrawn. A copy of the 6 March 2013 letter, as well as the 27 March 2006 Letter of Transfer, are enclosed.

(Id.). This recission recognizes the validity of the 2006 Letter of Transfer, a dramatic and unilateral shift in the government’s legal position. The United States asserts this change was spurred by the Court’s Summary Judgment Opinion issued almost two weeks earlier. During the Final Pretrial Conference, after some discussion about the effects of this double recission, the Court afforded Cully additional time to review the letter and form a position on its practical effects.

3 The Court notes the drastic change in the United States’ legal positions throughout the course of this litigation, as they seem to be based on convenience rather than its actual stance. The uncertainty it has caused has wasted a great deal of time and that has not gone unnoticed. For example, many months after insisting that Cully acknowledge the United States’ authority for the purported taking, the resulting opinion, and Second Amended Complaint, the United States now “rescinds” the 2013 “ouster” letter and concedes it has no interest whatsoever in the property. Any legitimate purpose underlying the United States’ maneuverings, when weighed against the resulting delay and costs, are difficult to discern.

2 On May 5, 2022, the Court held a Status Conference to discuss the United States’ Recission Notice and establish its effect on trial scheduled to begin four days later. During that Conference, the United States explained the purpose of the newest recission:

[T]he sole purpose of issuing that letter is that in the Court’s opinion on page 17, the April 14th opinion, the Court posed the question whether the United States plans to continue with the ouster should the buildings revert to Cully. So in other words—and elsewhere in the opinion the Court refers to a future taking. The purpose was to reassure the Court and the parties as to any prospective—in other words, it’s our understanding that when the lease expires, those buildings, via letter of transfer, will revert to Cully. And the 2022 letter from Colonel Cornwell offers that reassurance.

(Transcript of May 5, 2022 Status Conference (“Cully 5/5/22 Tr.”) at 21:19–22:6, ECF No. 147). Given this assurance and the dramatically altered position, the Court is faced with little choice but to amend its Summary Judgment Opinion to conform to existing facts.

There has been no final judgment in this case, nor does this order constitute a final judgment. Under RCFC 54(b), the Court may reconsider its interlocutory decisions at any time before judgment “as justice requires.” E&I Glob. Energy Servs., Inc. v. United States, 152 Fed. Cl. 524, 536 (2021). RCFC 54(b) states that “any order or other decision, however designated, that adjudicates fewer than all the claims or the rights and liabilities of fewer than all the parties does not end the action as to any of the claims or parties and may be revised at any time before the entry of a judgment . . ..” RCFC 54(b). “Orderly and efficient case administration suggests that questions once decided not be subject to continued argument but the court has the power to reconsider its decisions until a judgment is entered.” Exxon Corp. v. United States, 931 F.2d 874, 877 (Fed. Cir. 1991). As long as a decision is interlocutory, the Court possesses wide discretion to depart from or stand by it depending on what justice requires. E&I Glob. Energy Servs., 152 Fed. Cl. at 533. Thus, because the Court’s Summary Judgment Opinion is interlocutory, the Court may exercise wide discretion in reconsidering its prior rulings, particularly when there has been a change in a party’s position. See Lodge Constr., Inc. v. United States, __ Fed. Cl. __, 2022 WL 1113279 at *7 n.8 (Fed. Cl. Apr. 14, 2022) (“[The Plaintiff’s] motion to reconsider, unlike the overwhelming majority of such motions, is proper because an important intervening fact occurred[.]”). The Court may exercise this discretion upon motion or sua sponte. 4 See

Free access — add to your briefcase to read the full text and ask questions with AI

Cully Corporation v. United States, (uscfc 2022).

Cully Corporation v. United States (Cully Corporation v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Dickinson
331 U.S. 745 (Supreme Court, 1947)
Caldwell, Iii v. United States
391 F.3d 1226 (Federal Circuit, 2004)
Exxon Corporation v. The United States
931 F.2d 874 (Federal Circuit, 1991)
Otay Mesa Property, L.P. v. United States
670 F.3d 1358 (Federal Circuit, 2012)
Intergraph Corporation v. Intel Corporation
253 F.3d 695 (Federal Circuit, 2001)
Linda Vaizburd and Arkady Vaizburd v. United States
384 F.3d 1278 (Federal Circuit, 2004)
Golden Blount, Inc. v. Robert H. Peterson Co.
438 F.3d 1354 (Federal Circuit, 2006)
Squantum Gardens, Inc. v. Assessors of Quincy
140 N.E.2d 482 (Massachusetts Supreme Judicial Court, 1957)
Young v. United States
60 Fed. Cl. 418 (Federal Claims, 2004)
Mission Critical Solutions v. United States
104 Fed. Cl. 18 (Federal Claims, 2012)
National Food & Beverage Co. v. United States
105 Fed. Cl. 679 (Federal Claims, 2012)
Ladd v. United States
630 F.3d 1015 (Federal Circuit, 2010)